 |
 |
Works & Emergency
Services
"SWM-MEP"
Stakeholder Meeting
Metro Hall, Room 308
February 25, 1999
Draft
Meeting Notes/Issues List
Attendance:
| G. McGuinty |
Rail Cycle North |
|
R. Robertson
|
Port of Toronto |
| M. McGuinty |
Rail Cycle North |
|
Todd Pepper
|
EWSWA |
| R. Moskal |
Peel Region |
|
Lee Gravos
|
Toromont |
|
Ernie Pase
|
Harkow |
| F. Shilson |
Local 416 |
|
Mike Kemp
|
Local 416 |
|
Scott Wolfe
|
Rail Cycle North |
| J. Bray |
OWMA |
|
Steve Janes
|
City of Vaughan |
|
Garth Fowler
|
BFI |
|
Rino Adamo
|
BFI |
|
Jim Graham
|
Try Group |
|
John Todd
|
Todd Enterprise |
|
Clarissa Morawski
|
CM Consulting |
|
Linda Dionne
|
Pebblestone Multi-Services
Inc |
|
Don Welch
|
Pebblestone Multi-Services
Inc |
|
Phil Jenkins
|
PTJ Assoc |
| S. Wilson |
Serek Intl Wilson
Ltd |
|
P. Muldowney
|
Complete Waste Management
Services |
|
Colin Andrews
|
Plasma Environmental
Technologies |
| B. Henderson |
J & F Waste |
|
John Malvzek
|
Ontario Ministry
of Northern Development & Mines |
|
Vince Sferrazza
|
Peel Region |
| M. Dennis |
Northwood Recycling |
|
Rick Vandersluis
|
Try Group |
|
Lawson Oates
|
City - Works |
|
Angelo Babaris
|
City - Works |
|
Richard Butts
|
City - Works |
|
Tracey Ehl Harrison
|
City - Works |
|
Shane Inverary
|
City - Works |
|
Mae Lee
|
City - Works |
Meeting Format
Presentations were given outlining
the some additional issues that the City project team was seeking
feedback on before proceeding with the project. These issues included
the introduction of third party haulers for disposal contracts,
as well as muncicipal participation on the hauling component. There
were also presentations regarding tonnage quantities and contract
timeframes, the city as a preferred customer and/or revenue sharing
opportunities, and contracting for IC&I waste only.
After the presentations, a question
and answer session took place where a number of concerns were raised
by stakeholders. It should be noted that the group largely represented
disposal interests.
Questions/Concerns/Issues
Raised
The issues
raised have been categorized in order to facilitate responses.
Quantity
and Time Frames
- Proponents
have to secure specific approvals regarding tonnages/year and
must adhere to Certificates of Approval. It is very difficult
to do so if Toronto retains the right to specify the tonnages.
This doesnt allow planning at the micro level.
- Will the bidders know how the decisions
are made and how they scored in the process?
- The 20-year tonnage curve graph
for waste diversion in the City is not realistic. The surrounding
municipalities have straight line graphs. Even the slow population
growth in Toronto does not justify these diversion rates because
it is based on a projections rather than experience and statistics.
How have the tonnage curves changed from past presentations?
- The process as described in the
past, involved tonnage and price together. In the current discussion,
a companys competitive position regarding tonnages available
will be known.
Haulage
- The City
is duplicating the effort of proponents who expect to go through
their own RFP process to secure competitively price hauling, directly
related to their disposal proposal. This will hold up the process.
This change is also seen as a fundamental change in the process.
- The transfer station locations and
garbage centroids should be specified in the document.
- The haulage proposal is a very positive
one for the haulage industry. The City should be flexible in the
haulage terms and make options available to haulers.
- A rail based proposal will involve
special containers. This will necessitate that a transport component
be an integral part of the bid. In this case, a separate haul
component is not acceptable.
- The rail based proposal will keep
cost down. It is not possible to involve multiple haulers going
through the CN rail yard.
- The condition of using current levels
of city labour in the haulage component is generally acceptable.
- Is the City willing to upgrade existing
transfer station facilities to accommodate newer trucks?
- What will happen if the assets of
one hauler arent compatible with the disposal technology?
- By de-linking the haulage and disposal
component, disposal companies do not have the ability to form
a partnership with a hauler. The bidders should have control of
the whole process. If not, how will the macro environmental effects
be evaluated?
- Will a company be disqualified from
the bidding process if it does not have a separate disposal only
bid?
Preferred
Customer
- The City
as a "preferred customer" condition is too prescriptive.
It limits industry creativity. Some industry may not bid if this
condition is included.
- The requirement is financially unfeasible.
- This clause discriminates against
greenfield sites.
- The City should state their objectives,
and allow the disposal companies to be more creative in deciding
how the job will be done. There should be an opportunity for proponents
to present profit sharing ideas.
- This condition would create difficulties
for smaller municipalities in terms of getting a low rate from
disposal companies.
- On what basis will the "best
price" be determined? If there are volume differentials between
the City and other customers where other customers bring larger
volumes, it is unfair to expect the lowest price for the City.
- This clause will cause chaos with
respect to existing contractual arrangements.
- Bidders cannot finance a plan with
this condition. It is not reasonable and not fair to have future
readjustment of price downward after contract already signed.
- The preferred customer clause is
unnecessary. The City should satisfy itself that it is receiving
a competitive price.
- Margins are going to be shaved in
order to submit the most competitive price. How can the city deny
a proponent the opportunity to make revenues elsewhere?
Contracting
for ICI Waste only
- It would
be difficult for the City to segregate IC&I from household
waste at the transfer stations.
- The City does not control IC&I
volume, so how can it be contracted for?
- The City should not compete with
disposal companies for IC&I waste.
- A caution was raised, as contractors
will demand put or pay provisions.
Anti-lobbying
Ban
- Iindustry
should reserve the right to correct any misinformation in the
media and/or with Councillors. The anti-lobby ban should be introduced
at the RFP stage when the firms are short-listed, not the EOI
stage.
- Will the anti-lobbying ban apply
in the partner GTA regions?
- It is unfair that proponents can
not lobby, but special interest groups can.
General
Comments
- The public
and industry would like to see the draft report before it goes
to Works and Utilities Committee on Mar 24, 1999.
- This process is becoming more like
a tender process than a request for expressions of interest. The
process is not as open ended as it was when the draft planning
document was released.
- The growing complexity of the process
makes it very uninviting.
- Before proponents submit proposals,
there needs to be a clear understanding of how proposals will
be evaluated.
- The project timelines are very tight.
- Will all waste be going through
City transfer stations or is there flexibility to use private
transfer stations?

|
|