Project update – Weekend demolition work May 13-14
View Construction Notice
(PDF)
You will need to have the FREE Acrobat Reader Get Acrobat to view PDF files.

The City of Toronto is currently rehabilitating Leaside Bridge. The Leaside Bridge is located between Millwood Road and Donlands Avenue and Pape Avenue, over the Don Valley.

New construction dates
The original Tender Call for Leaside Bridge Reconstruction was cancelled and replace by two separate Tender Calls. Both contract packages have now been awarded.

Work involving the first contract consisted mainly of work beneath the deck and was completed in 2004 with the second contract package beginning in May 2005. This work will be most visible to the public travelling on the bridge. A construction notice will be distributed to the public in mid April, 2005, approximately one month prior to the start of construction.

The City will be carrying out the following work

  • complete concrete deck replacement;
  • strengthening of the structural steel superstructure to meet the current Canadian Highway Bridge Design Code requirements;
  • substructure modifications and repairs;
  • replacement of the waterproofing and asphalt paving;
  • new barrier walls and approach slabs; and
  • replacement of the bridge railings with decorative concrete railings that conform to safety code.

Construction map
Construction map

Construction impacts
During construction, there will be periods where the bridge will be reduced to one lane of traffic in each direction. Additional lanes of traffic will be added as can be accommodated by the work plan and traffic staging.

Construction schedule
Construction work carried out below deck began in 2004 and consisted of steel strengthening and relocation of utilities. The majority of the deck and sidewalk construction however, will occur between May 2005 and late 2006.

Leaside Bridge recognized as a Heritage structure
As of March 2004, the Leaside Bridge has been included on the official list - City of Toronto Inventory of Heritage Properties, for its cultural resource value or interest. The City's Heritage and Culture Division have advised on appropriate railing design and signage.

Leaside Bridge arial view

For further information, please contact:

Vic Zubacs, P. Eng.
City of Toronto
Tel: 416-392-8322
Tty: 416-397-0831
Tel: 416-397-7777 (24-hour Comment Line)
Email: works_consultation@toronto.ca

Back to the top



Toronto maps | Get involved | Toronto links | 311 | Comment | Subscribe | Privacy statement
© City of Toronto 1998-2011