This project is no longer active. The following information is provided for archival purposes.
The
City of Toronto is building an underground residue management facility
at the R.C. Harris Water Treatment Plant. The facility is required
by the Ministry of the Environment and will help improve local
beach water quality. The plant currently pumps untreated residues
(material left over from the water treatment process) into the lake.
When the facility is constructed, the City will treat the residues
on site.
What is a
Residue Management Facility?
A
residue management facility contains process equipment and underground
tanks to remove solid materials left over from the process of cleaning
lake water to make potable (drinking) water.
Why is the
City building this facility?
The
R.C. Harris plant was built in the 1930s and expanded
in the 1950s. At the time, it was common practice to discharge residues
back to the source. Today, new provincial
regulations require treatment of waste produced during the filtration
process. This new practice will contribute to the City's efforts
to improve the local waterfront and fulfil its requirements
to the Province.
In 2002, the
City completed a Class Environmental Assessment (EA) for this project.
An Addendum was completed in 2003. The Addendum recommends designing
and building the residue management facility underground. The design
in the Addendum does not affect the architectural or heritage features
of the plant.
Construction
details
In September 2004, Toronto Council awarded Kenaidan Contracting
Limited the contract to build the residue management facility. CH2M
HILL Canada Limited, the design engineers for this project, will
provide contract administration services.
Work schedule
Construction began in November
2004, and is anticipated to be complete in the Spring of 2007. See
the work schedule (PDF).
You
will need to have the FREE Acrobat
Reader to view PDF files. 
Limiting the effects of construction
To
reduce the impacts of construction on the neighbourhood, the project
team is putting in place numerous measures. These include:
Dust control
The contractor is using a variety of dust control measures to
limit dust production on-site. A 10-foot hoarding has been be
built around the construction area and along the outside of the
east and west access roads to reduce the amount of dust escaping
the site. The contractor will remove graffiti and unofficial postings
from the hoarding regularly.
Additional
dust control measures include:
- installation
of a filter cloth to cover the chainlink fence between the service
building and the pump station
- installation
of a filter cloth on the fence on the south side of the pump
station and gates, directly adjacent to the pile of earth
- installation
of a new fence, covered with filter cloth, on the western most
side of the construction area where the hoarding dips down,
to prevent dust from blowing over the hoarding at that point
- placement
of tarps on the north slope of the sea wall pile
Restricting
plant access
An area a little bigger than a football field is being excavated
for construction of the facility. For safety purposes, public access
to the grounds will not be allowed throughout the construction
period. A temporary road has been built at the foot of Nursewood
Road to allow access for deliveries, operations staff, and plant
maintenance vehicles during construction. Construction vehicles
related to this project are not permitted on Nursewood Road.
Noise control
All construction vehicles and equipment will have effective muffling
devices that will minimize noise in the project area. The City's
Noise By-law will also be enforced. Most of the time, construction
work will be limited to 7:00am to 7:00pm, Monday to Friday. From
time to time the hours and/or days of work may be extended. The
hoarding will also help to reduce noise from construction.
Erosion
and Sedimentation
Sedimentation ponds, silt fences, and straw bales will be used
as part of an erosion and sedimentation control plan.
Consideration
of heritage features
Construction of the facility will not affect the heritage features
of the plant. The new facility will be built underground and will
not be invisible from the plant surface. When construction is
complete, the site grading and landscaping will be completely
restored. All temporary roads installed for construction will
be removed.
The project
team regrets that public access to the R.C. Harris site will not
be permitted throughout the construction period.
Contact us
If you have any questions or concerns about this project please contact:
Public Consultation
Unit
City of Toronto
Metro Hall, 19th Floor
55 John Street
Toronto, ON M5V 3C6
Tel: 416-397-7777
Fax: 416-392-2974
TTY: 416-397-0831
Email: works_consultation@toronto.ca

|