| Activity |
Deliverables |
Due Date |
| Inventory and Prioritization |
List of critical systems including their current status |
1998 Sept. 30 |
| Assessment |
Cost estimate and schedule for remedy of all critical systems
|
1998 Oct. 31 |
| Remedy |
Year 2000 ready critical systems |
1999 April 30 |
| Test and re-implement |
Proven Year 2000 ready critical systems |
1999 Oct. 31 |
| Millennium operational schedule |
Timetable for year-end cut-over |
1999 Nov. 30 |
| Contingency planning |
Business continuity plans for all critical business functions |
1999 April 30 |
| Contingency plan implementation |
Business continuity solution in place |
1999 Oct. 31 |