Two new parks are coming to the North St. Lawrence Neighbourhood as part of mixed-use development projects at 261 Queen St. E. and 254-260 King St. E. The park designs will be determined through community engagement.

Project Timeline

  • Winter 2022: Hire a design team
  • Spring 2022 to Fall/Winter 2022: Community engagement and design development
  • Spring 2023 to Winter 2023: Detailed designs
  • New Park on Richmond Street East:
    • 2024: Hire a construction team and construction starts
    • 2025: Construction complete, park opens
  • New Park on King Street East:
    • 2025: Hire a construction team and construction starts
    • 2026: Construction complete, parks open

The timeline is subject to change.

Community engagement for both parks on Richmond Street East will start in spring 2022.

Sign Up for Updates

Sign Up Now

Sign up for updates related to the New Parks in the North St. Lawrence Neighbourhood or unsubscribe from the mailing list.

The new 1,400m2 park that will be constructed as part of the development at 261 Queen St. E. will be located just south of the development site, at Richmond Street East and Ontario Street. This park will be referred to as the New Park on Richmond Street East until the park is officially named.

The new 470m2 park that will be constructed as part of the development at 254-260 King St. E. will be located northeast of King Street East and Princess Street. This park will be referred to as the New Park on King Street East until the park is officially named.