Dundas Street West Watermain Replacement & Road Resurfacing
The City of Toronto will replace the watermain and City-owned substandard water services on Dundas Street West between Spadina Avenue and Bay Street. The City will also be reconstructing the intersections at Carlyle Street and Casimir Street along with repairing road and sidewalks impacted by previous utility works. The road will be resurfaced where watermain work was completed.
This work is required to bring City infrastructure to a state of good repair. This project is part of the Council-approved 2018 Capital Works Program.
Construction Dates:
Start Date: September 24, 2018
End Date: Fall 2019

Phase 1: September 24, 2018 to December 31, 2018
Dundas: From Bathurst to Spadina
Crews will be:
|
|
Phase 2: Mid-October 2018 to Spring 2019
Dundas: From Spadina to Simcoe
Crews will:
|
|
Phase 3: Spring 2019 to Fall 2019
Dundas: From University to Bay
Crews will:
|
Note: Temporary pipes will be required to continue providing water services to local properties. These pipes will be placed between University and Bay. |
Construction Update #1
- Intersection Improvements at Casimir Street and Dundas Street West (Dated: October 26, 2018)
Construction Notice
- English (Dated: September 13, 2018)
- Simple Chinese (Dated: September 13, 2018)
Pre-Construction Notice
- English (Dated: July 25, 2018)
- Simple Chinese (Dated: July 25, 2018)
Garbage Information Notice
- English (Dated: September 14, 2018)
- Simple Chinese (Dated: September 14, 2018)