April 22, 1998
To:Strategic Policies and Priorities Committee
From:City Clerk
Subject:Contract No. T-42-98:
Don Valley Parkway Resurfacing at Two Locations
Recommendation:
The Urban Environment and Development Committee on April 20, 1998, recommended to the Strategic Policies
and Priorities Committee, and Council, the adoption of Recommendations Nos. (1), (2) and (3), embodied in the
attached report (April 9, 1998) from the Interim Functional Lead, Transportation, regarding Contract No. T-42-98
for the resurfacing of the Don Valley Parkway at two locations.
City Clerk
N. Rickford/lv
Attachment
Item No. 42
h:\1998prod\ud\reports.98\report6\042042.tra
Copy to:Commissioner of Works and Emergency Services
Interim Functional Lead, Transportation
Mr. R. Burlie, Manager of Resurfacing, Transportation Division, Metro Hall
(Report dated April 9, 1998, addressed to the
Urban Environment and Development Committee from the
Interim Functional Lead, Transportation.)
Purpose:
To seek early approval to allocate $2,700,000.00 from either the 1999 Capital Works Program or from the proceeds from
the sale of property assets in 1998 and to award a contract for the resurfacing of the Don Valley Parkway at two locations.
Funding Source:
The total project cost is estimated to be $2,700,000.00 and is summarized as follows:
(1)Bid Price Amount $2,554,897.17
(2)Other costs (estimate):145,102.83
(a)quality control testing;
(b)traffic signage and road closures; and
(c)bicycle proof catch basin frames and covers.
____________
Total project cost $2,700,000.00
____________
Resurfacing and rehabilitation work on the Don Valley Parkway has traditionally been carried out early in the construction
year to minimize disruption to the travelling public during the summer tourist season. Consequently,this project was
tendered prior to budget approval, on the assumption that the 1998 Transportation Capital Works Budget would be
approved at a level similar to the 1997 budget. However, based on the recommendations of the Budget Committee, the
Transportation Capital Works Budget for the City of Toronto, which is scheduled to be approved by Council at its meeting
on April 28, 1998, now does not include this project.
An unusual situation has arisen in which the Alow bidder@, Warren Bitulithic Limited, has indicated that it is willing to
proceed with this project and be paid at a later date. This could occur next year as part of the 1999 Capital Works Program
or later in 1998, if funds become available from the sale of property assets. This was proposed by the Budget Committee in
order to provide funds for works which have had to be deferred as a result of the Budget Committee=s recommendations to
delete $18.4 million from the Capital Budget submission. Warren Bitulithic Limited has confirmed in writing that it will
conform with all of the conditions in the original tender documents and that it will not seek any compensation for Alate@
payment. This proposal by Warren Bitulithic Limited does not violate the integrity of the Atender and award@ process.
The Department is recommending that the proposal from Warren Bitulithic Limited be accepted because it is important to
resurface and repair the drainage system for this section of the Don Valley Parkway in 1998 for the following reasons:
(1)previous experience with the performance of the existing steel slag surface asphalt indicates that accelerated
deterioration may occur during the next winter season. This situation would require unscheduled closures of the Don Valley
Parkway to undertake emergency repairs; and
(2)the existing drainage facilities in their current state of disrepair are capable of being rehabilitated insitu with little or
no disruption to the users of the Don Valley Parkway. Further deterioration may lead to open cut replacement of these
facilities at a significantly higher cost and requiring additional closures of the Don Valley Parkway.
Funding is currently available in Capital Account No. C-TR029, Don Valley Parkway Rehabilitation. The Treasurer
certifies that financing can be provided under the updated Debt and Financial Obligation Limit and that it falls within
Corporate Debt Guidelines.
Recommendations:
It is recommended that:
(1)pre-budget approval of $2,700,000.00 be granted for the 1999 Capital Works Program or, alternatively, that funds be
provided from the sale of property assets as outlined in this report;
(2)subject to approval of Recommendation No. (1), Contract No. T-42-98, for the resurfacing on the Don Valley
Parkway at two locations, be awarded to Warren Bitulithic Limited who submitted the lowest price bid in the amount of
$2,554,897.17;
(3)the appropriate City of Toronto officials be directed to take the necessary action to give effect thereto; and
(4)this report be forwarded to the Budget Committee.
Comments:
On March 5, 1998, the City Clerk's Department opened tenders for:
Contract No. T-42-98 -Don Valley Parkway Resurfacing at Two Locations
NumberName$ Amount
5Warren Bitulithic Limited2,554,897.17
1D. Crupi and Sons Limited2,569,306.89
6Dufferin Construction Company, 2,611,639.95
a division of St. Lawrence Cement Inc.
7Pave-Al Limited and Orlando Corporation2,613,676.89
4Graham Bros. Construction Ltd., Fairglen Excavating Ltd.,2,729,506.91
795208 Ontario Ltd., Graham Bros. Aggregate Ltd.
3Gazzola Paving Limited2,898,044.82
2Brennan Paving and Construction Limited2,921,347.98
The award is subject to receipt of a favourable report from the Fair Wage and Labour Trades Office regarding working
conditions and wages of the recommended contractor and his sub-contractors, and also from the Treasurer regarding the
surety company which issued the Bid Bond and Agreement to Bond.
Scope of Work:
The work in this contract comprises the asphalt resurfacing of the Don Valley Parkway including the rehabilitation and/or
replacement of catch basin connections, replacement of guiderail and attenuation systems and permanent pavement
markings at the following locations:
(1)southbound from Don Mills Road to Beechwood Drive; and
(2)Don Mills Road ramps.
Conclusion:
Subject to City Council approving $2,700,000.00 for the 1999 Capital Works Program, Contract No. T-42-98 should be
awarded to Warren Bitulithic Limited which submitted the lowest price bid for this Contract.
Contact Name and Telephone Number:
Mr. R. Burlie, P. Eng., Manager of Resurfacing, Metro Hall Office, 392-8322.