Scarborough Road/Woodale Avenue Intersection -
Design Refinement to Intersection Realignment (East Toronto)
The Toronto Community Council recommends the adoption of the following report (April 15, 1998) from the
Director, Infrastructure Planning and Transportation Division, City Works Services:
Purpose:
To introduce a technical amendment to refine the previously approved realignment and narrowing of the Scarborough
Road/Woodale Avenue intersection.
Funding Sources, Funding Implications and Impact Statement:
Funds to cover the work, in the estimated amount of $20,000, are included in the Department=s 1998 Capital Budget
request.
Recommendations:
(1) That By-law No. 1997-0403 authorizing the narrowing of the Scarborough Road/Woodale Avenue intersection, be
amended to incorporate the design refinements described in the text of this report and illustrated in the attached print of
Revised Drawing No. 421F-5043, April 1998, as follows:
- delete the entries in Section 1(1) under Columns 1, 2, 3, 4, 5 and 6 and replace with the following:
(Column 1(Column 2(Column 3Column 4(Column 5(Column 6
Side orWidth)From)To)Drawing
Street)Location)No./Date)
Scarborougheastfrom: 8.5 ma point 10 ma point 10 mRevised
Roadto: 6.0 m -north of south of 421F-5043,
8.5 mWoodale AveWoodale AveApril 1998
(2) That the appropriate City officials be authorized to take whatever action is necessary to implement the foregoing,
including the introduction in Council of any Bills that may be required.
Background:
The previous Toronto City Council, at its meeting of August 21, 1997 in considering Clause 7 in City Services Committee
Report No. 10, among other things, authorized the enactment of a by-law for the physical alteration of Scarborough Road at
its intersection with Woodale Avenue. By-law No. 1997-0403 and the referenced drawing establish the configuration of
this intersection narrowing. At the request of Councillor Tom Jakobek, Works staff have assessed the approved intersection
configuration and developed refinements, which while serving the same purpose as the original plan, can be installed
effectively in conjunction with an asphalt overlay planned for this year.
Comments:
The approved configuration for the Scarborough Road/Woodale Avenue intersection involves the installation of an island
on the west side which would narrow the south leg to a width of 6.0 m. By taking advantage of the maintenance work
planned for Scarborough Road this year, there is an opportunity to extend the curb, sidewalk and boulevard areas on the
northeast and southeast corners of the intersection as illustrated in the attached Revised Drawing No. 421F-5043, April
1998. The pavement narrowings would still result in a 6.0 m width. Enhanced landscaping potential will be explored as part
of the detailed design.
Given that the proposed refinement to the approved intersection design will serve the same purpose as the original, I am of
the view that it represents a technical amendment which does not alter the intent or fundamental function of the plan, and
accordingly should not require the readvertising of the by-law.
Contact Name and Telephone Number:
Andrew Koropeski, Director
Infrastructure Planning and Transportation Division
392-7711