Toronto Heritage Fund Grant Application -
427 Bloor Street West (Trinity St. Paul Church)
The Strategic Policies and Priorities Committee recommends the adoption of the recommendation in the
following transmittal letter (June 11, 1998) from the Municipal Grants Review Committee:
Recommendation:
The Municipal Grants Review Committee on June 11, 1998, recommended to the Strategic Policies and Priorities
Committee, and Council, the adoption of the attached report (June 9, 1998) from the Acting Managing Director,
Toronto Historical Board, respecting an increase in the Toronto Heritage Fund grant for 427 Bloor Street West.
--------
(Report dated June 9, 1998, addressed to theMunicipal Grants Review Committee from theActing Managing
Director of the Toronto Historical Board)
Purpose:
To assist the owner to complete necessary restoration as part of a five-year phased restoration project.
Funding Sources, Financial Implications and Impact Statement:
Funds are provided through the Toronto Heritage Fund.
Recommendations:
It is recommended that:
(1)the Toronto Heritage Fund Application for 427 Bloor Street West, for an increased $10,000.00 from the
previously recommended sum of up to $35,000.00 to support an increased scope of restoration that includes the
north-east and north west tower roof, be approved;
(2)the grant be conditional on the Board of Trustees entering into a Restoration Grant Agreement prepared by the
City Legal Department in consultation with the Managing Director of the Toronto Historical Board; and
(3)the Trustees ensure that the Board's involvement in the project is suitably recognized.
Background:
The property at 427 Bloor Street West, Trinity St. Paul Church, was designated under Part IV of the Ontario
Heritage Act by By-law No. 166-80, passed by City Council on February 4, 1980.
On April 29, 1998, William W. Small, Chair, Board of Trustees, Trinity-St. Paul's United Church, wrote requesting
an increase in the grant from the Toronto Heritage Fund to cover costs for (1)re-roofing both towers with red slate,
(2) new gutters and downspouts, (3) masonry repointing on both towers, and (4) repair of decorative woodwork at a
total cost of $170,000.00. The grant increase request is based on completing work previously planned for 1999 this
year. Therefore, the request is for the cost of the 1998 restoration work of $135,000.00 (including a previously
approved grant for $35,000.00), plus the increased scope of work for $55,000.00 (including a requested grant of
$10,000.00) for a total of $170,000.00 of construction cost. Allowing the work to occur at one time would allow a
cost savings to the applicant.
At its meeting of May 20, 1998, the Toronto Historical Board adopted the staff recommendation that this property
receive additional financial support from the Toronto Heritage Fund.
Discussion:
The Church's Board of Trustees is undertaking a five-year restoration and renovation program. The work is being
funded through a capital fund raising campaign, with pledges paid over five years. Because the funding will be
spread out, the work has been carried out in phases. Five phases have been identified. In 1996-1997, Phases I and II
were completed with the support of Toronto Heritage Fund grants of $7,000.00 and $25,000.00, respectively. The
recently approved grant of $35,000.00 and the request are Phase III and IV to be completed in 1998. The current
application is for PhaseIV and is a request for a Toronto Heritage Fund grant of $10,000.00. The church entered
into a Heritage Easement Agreement with the City of Toronto last year.
The scope of work proposed by the architect is as follows:
"The work will entail re-roofing both tower roofs with red slate and shaped metal hip detailing to match the roof
over the centre entrance. The roof work will also include new gutters and down pipes, or in the case of the
north-east tower, spigots. In addition, we propose that complete repointing of the masonry take place on the east
face of the south-east tower as it is exhibiting deterioration. As well, the upper area, all four sides, of the north-east
tower will be repointed, as will the stones at the sides of the entry steps. Finally, the work will include making good
any deteriorated woodwork, including the south-east entry doors, and refinishing the same. There is to be a
moderate bit of glazing work to be carried out on both towers."
The Toronto Historical Board views the work as necessary to ensure the continued preservation of the building.
Staff recommends that continued support is warranted given the site's high visibility and diverse community
programming.
The grant therefore would help make good the existing roofing on the north west tower. We understand that the cost
of repairing the roof in red slate exceeds $55,000.00.
Staff recommends the additional grant of $10,000.00 to support the restoration of the significant architectural
feature of the red slate roofing at the north west tower.
Contact Name:
Winston Bridgman, Heritage Toronto, Tel: 392-6827, ext. 238/Fax: 392-6834.