City of Toronto  
HomeContact UsHow Do I...?Advanced search
Living in TorontoDoing businessVisiting TorontoAccessing City Hall
 
Accessing City Hall
Mayor
Councillors
Meeting Schedules
   
   
  City of Toronto Council and Committees
  All Council and Committee documents are available from the City of Toronto Clerk's office. Please e-mail clerk@city.toronto.on.ca.
   

 

Main Treatment Plant - Additional Expenditure

for Construction of Digester Gas Control Building

Contract No. WPC-5-97

The Works and Utilities Committee recommends the adoption of the following report (November 27, 1998) from the Commissioner of Works and Emergency Services:

Purpose:

To obtain Council authority to negotiate and authorize additional expenditures for the performance of necessary additional work on Contract No. WPC-5-97 for the construction of the Digester Gas Control Building at the Main Treatment Plant.

Funding Sources:

Funds are available in the approved 1998-2002 Water and Wastewater Services Division, Water Pollution Control Capital Account C-WP160, Main Treatment Plant.

Recommendations:

It is recommended that:

(1)additional expenditures in the amount of $1,393,444.44, including Goods and Services Tax, be authorized for the performance of necessary additional work on Contract No. WPC-5-97 for the construction of the Digester Gas Control Building at the Main Treatment Plant in accordance with the estimates listed in Appendix A attached; and

(2)the appropriate City officials be authorized to take the necessary action to give effect thereto.

Background:

By adoption of Clause No. 28 of Report No. 12 of The Environment and Public Space Committee, the former Metro Council, at its meeting of September 24, 1997, awarded Contract No. WPC-5-97 for the construction of the Digester Gas Control Building at the Main Treatment Plant. The contract was awarded to Bondfield Construction Company (1983) Ltd. for the total lump sum tender price of $24,549,000.00 including GST and a Schedule of Prices allowance of $129,900.00 for additional work if required. The order to commence work was dated October 22, 1997, at which time the contract work began.

At the time of award, in accordance with former Metro By-law No. 146-90, as amended, a Department Head had authority to approve additional expenditures on a commitment in accordance with the By-law up to an amount equal to ten percent of the commitment. As such, under the former Metro By-law a further $2,454,900.00 or ten percent of the awarded contract amount would have been available for required extra work.

At its meeting of January 6, 1998, City of Toronto Council enacted By-law No. 7-1998, Interim Financial Control By-law, which repealed former Metro By-law No. 146-90. As the new by-law contains no provision to exceed the awarded contract value, as confirmed by the City's Legal Division, the Department has effectively lost its ability to authorize the unforeseen and necessary additional work that may arise during construction of capital projects. This is particularly problematic given that the majority of capital construction performed by this Department is tendered on a firm, lump sum basis. For contracts recently tendered, since confirmation of the repeal of former Metro By-law No. 146-90, we have been providing, on an interim basis, a general contingency allowance for possible extra work into the Schedule of Prices for Alterations, Extras, and Deductions for incorporation into the total lump sum tender price. In the case of Contract No.WPC-5-97, however, no such general contingency was added, as we believed it was still available through former Metro By-law No. 146-90.

Comments and Justification:

Since the commencement of Contract No. WPC-5-97, issues have been identified as requiring the performance of extra work. In some cases, additional information and unexpected circumstances have arisen during construction, which have necessitated changes to the original tendered scope of work. To ensure continuity with respect to liability and warranty issues under the contract, these changes must be implemented by the issuance of extra work orders. For example, unanticipated contaminated soils encountered during construction have resulted in the additional trucking and disposal costs associated with landfill disposal. In other cases, staff of the Department and/or our consultants have identified changes to the design of the original contract which are now advisable to be performed to conform to changed regulatory code requirements or operating procedures, and which should be implemented to ensure construction of the best possible finished product. For instance, proposed changes to the raw sludge distribution valving and control systems to be constructed in existing anaerobic digestion tanks nos. 5 to 12 have resulted in expediting the construction of a previously designed control room building for digestion tanks nos. 1 to 12. As well, it is proposed to install an integrated natural/digester gas flow measurement system to more accurately determine Main Plant digester gas production, and consumption of both digester gas and natural gas. Such a system will prove invaluable in improving unit process cost data during the conversion to 100 percent beneficial reuse of biosolids, and in any future district energy or co-generation initiatives. For the same aforementioned reasons of liabilities and warranty issues, these changes are required to be performed under the contract by the issuance of extra work orders.

Conclusion:

The additional expenditures required for extra work in the amount of $1,393,444.44 including GST on Contract No. WPC-5-97 are summarized in Appendix A.

Contact Name:

Mr. P.A. Bradley, P.Eng.,

Senior Project Engineer, Technical Services Division

Telephone No.: (416) 392-8251.

APPENDIX A

Main Treatment Plant

WPC-5-97 Gas Control Building

Request for Authorization of Additional Expenditures

Item

Description

Terms Authorized Amount
1 Truck/dispose registerable soil at Keele Valley LS $15,916.80
2 CREDIT: delete flanges on exterior gas piping LS -13,356.00
3 Additional Seawall Tunnel wall dowels resteel LS 3,218.15
4 Construct Dig. 1-12 control room building LS 615,250.00
5 CREDIT: mods. to combustible gas monitoring system LS -1,280.51
6 CREDIT: delete security gate and guardhouse LS -36,000.00
7 Extend height of shoreline sheetpiling LS 24,726.00
8 Remove obstruction at tunnel piles H19/H20 LS 5,000.00
9 CREDIT: construction power consumption LS -10,000.00
10 Remove obstruction at sheet pile at outfall LS 15,000.00
11 Larger openings in seawall for cable tray LS 15,000.00
12 Relocate catch basin #2 LS 2,500.00
13 Jeene joint alternative LS 1,500.00
14 Replace spool at digester gas valve chamber LS 5,500.00
15 Remove conc. saddle encasement re: 750 dia. st. sewer LS 3,500.00
16 Program seawall gates flow metersSchedule Schedule 10,000.00
17 New HSS support beam at overhead gas pipe LS 16,000.00
18 Conc. encase drain pipe E. of line 7 LS 12,500.00
19 Cut exist. steel sheeting at outfall LS 14,000.00
20 CREDIT: concrete haunch brick support at control room bldg. LS -10,000.00
21 CREDIT: clevis hangers in lieu of rollers LS -2,000.00
22 Raise tunnel roof at exist. pipe bridge supports LS 31,500.00
23 Substation grounding cable connection LS 2,500.00
24 Add resteel at top of DT #1&3 columns LS 1,750.00
25 CREDIT: gas dryer equipment alternative LS -10,000.00
26 CREDIT: alternative rolling doors LS -4,280.00
27 Additional excavation at Dig. #1-12 control room bldg. LS 30,000.00
28 Building lighting modificationsest est 60,000.00
29 Gasproofing inspectionSchedule Schedule 20,000.00
30 Shoreline restorationSchedule Schedule 25,000.00
31 Digester gas utilization system Schedule 550,000.00
TOTAL $1,393,444.44

 

   
Please note that council and committee documents are provided electronically for information only and do not retain the exact structure of the original versions. For example, charts, images and tables may be difficult to read. As such, readers should verify information before acting on it. All council documents are available from the City Clerk's office. Please e-mail clerk@city.toronto.on.ca.

 

City maps | Get involved | Toronto links
© City of Toronto 1998-2001