City of Toronto Council and Committees |
|
 |
All Council and Committee documents are available from the City of Toronto Clerk's office. Please e-mail clerk@toronto.ca.
|
|
|
August 20, 1999
To:Administrative Committee
From:Acting Commissioner of Corporate Services
Subject:Application for Approval to Expropriate Interests in Land,
Sheppard Subway / Sheppard Widening Project
Multiple Partial Interests
Vicinity of Intersection of Bayview Avenue and Sheppard Avenue East
(Ward 9- North York Centre South, Ward 10- North York Centre
Ward 12- Seneca Heights)
Purpose:
To authorise the initiation of the expropriation of property interests required for road widening, intersection improvements
and associated utility relocations, in the vicinity of the intersection of Bayview Avenue and Sheppard Avenue East, in
conjunction with the completion of the Bayview Subway Station.
Funding Sources, Financial Implications and Impact Statement:
Financing has previously been approved by Council and is available in Sheppard Subway Capital Account TC-392.
Inasmuch as the road widening is a Transportation Project, Account No. TC-392 will be reimbursed for 100% of the costs
through Transportation Capital Account C-TR-023.
Recommendations:
It is recommended that:
(1) authority be granted to initiate the expropriation process for the property interests detailed herein;
(2) authority be granted to serve and publish Notices of Applications for Approval to Expropriate property interests herein
detailed, to forward to the Chief Inquiry Officer any requests for hearings that are received and to report the Inquiry
Officer's recommendations to Council for its consideration;
(3) authority be granted to lay out as a public highway the lands designated in the schedule to this report for right-of-way
widening, and thereafter to dedicate such lands for public highway purposes; and
(4) the appropriate City officials be authorised and directed to take the necessary action to give effect thereto.
Council Reference/Background/History:
By approval of Clause No. 2 of Report No. 9 of The Management Committee (as amended) on March 8 and 9, 1994, and
subject to a further report regarding funding, Metropolitan Council approved construction of the Sheppard Subway from
Yonge Street to Don Mills Road. By approval of Clause No. 2 of Report No. 14 of The Management Committee (as
amended) on April 20, 1994, Metropolitan Council authorised the debenture funding to commence the project. Finally,
Metropolitan Council, by its adoption of Clause No. 2 of Report No. 21 of The Financial Priorities Committee on
September 25 and 26, 1996 (as amended), approved the completion of the Sheppard Subway Project.
By approval of Clause No. 5 of Report No. 18 of The Financial Priorities Committee on November 5, 1995, Metropolitan
Council approved modifications at the intersections of Sheppard Avenue and Yonge Street, Bayview Avenue and Leslie
Street as the first phase of the widening of Sheppard Avenue between Beecroft Road and Leslie Street, which includes the
works which are the subject of this report.
Comments and/or Discussion and/or Justification:
In order to eliminate a separate construction impact, construction associated with the widening of Sheppard Avenue East in
the vicinity of Bayview Avenue is scheduled to coincide with completion of the Bayview Station Contract. The road
widening, intersection improvements and associated utility relocations including hydro pole and wire relocations onto
privately-owned property will take place at the same time as the above grade restoration work on the Bayview Station. This
will reduce the duration of the construction impacts on residents and traffic.
The impacted properties and requirements have been identified and owners are being contacted and negotiation for the
requirements will commence shortly.
The properties and requirements are shown on five draft reference plans (series 94-21-413-52 - A to E) prepared by J.D.
Barnes Limited, copies of which are on file with the City Clerk. The dimensions and areas are based on available records
and may be subject to minor adjustments upon completion of surveys.
While it is recommended that the City commence expropriation proceedings, it is recognised that it would be preferable to
have expropriation of the Hydro requirements in the name of Toronto Hydro. The Ontario Energy Board Act 1998, has not
yet been fully proclaimed in force, consequently Toronto Hydro Electric System Limited ("Hydro") does not presently have
the authority to expropriate the Hydro requirements. As things presently stand we have to rely on expropriation by the City
and subsequent transfer of the appropriate interests to Hydro in order to assure acquisition in time for the scheduled
commencement date. In any event since the Hydro requirements arose from a City of Toronto/TTC project the acquisition
costs flow to the City.
The property interests, all of which are required by January 1, 2001, are listed on the schedule appended hereto and include
the following categories.
(a)Temporary Grading Easements: are required to change the grade of properties abutting the street to match the new
grade of the street and sidewalk. The requirement is for a period of approximately two to three days, barring unforeseen
difficulties, within a 10 month period between January 1, 2001 through to October 31, 2001. However expropriation of the
temporary interests must be for the full 10-month term to allow for scheduling flexibility. During construction, alternate
access/parking arrangements will be provided to property owners or occupants as required. Owners or occupants will be
notified well in advance of the two to three day construction activities.
(b)Permanent Hydro Easements (wires): are required to relocate transmission lines and /or guy wires away from the
widened roadway limits. These are interests that have been defined by Hydro as per applicable codes and/or standards.
Permanent Hydro Easements (wires, poles and anchors): are required to locate hydro poles and their anchor(s) away
from the widened roadway limits.
(d)Right of Way (ROW) widenings: are partial fee acquisitions that are required to widen the street and relocate public
sidewalks.
Conclusions:
The commencement of expropriation procedures for the acquisition of the property interests herein described is necessary
to ensure that possession of the interests are obtained in a timely manner in the event negotiated acquisitions are
unsuccessful.
Contact Name:
Daniel O'Donohue, Valuator/Negotiator (Facilities & Real Estate)(ac99131)
(416) 392-8161 Fax No.: (416) 392-1880
Brenda Glover
Acting Commissioner of Corporate Services
APPLICATION FOR APPROVAL TO EXPROPRIATE PROPERTY INTERESTS - SHEPPARD SUBWAY |
|
Prop. Address |
Owner |
Property Interests Required |
Term of Temporary
Interest (Months) |
Description |
SOUTHWEST QUADRANT OF INTERSECTION OF SHEPPARD AVENUE EAST AND BAYVIEW AVENUE |
1 |
321 Sheppard Ave E |
Thakkar, Rasesh B.
Thakkar, Menaka B. |
Temporary grading easement
(36.00 sq. m. pts 1 & 14)
Permanent hydro easement (wires)
(37.12 sq. m. pt 14) |
10 |
Part lot 22, Plan 3896, part PIN 10104-0019(R) shown
as parts 1 and 14 on draft reference plan 94-21-413-52-a
(dated August 23, 1999) |
2 |
323 Sheppard Ave E |
How, Jocelyne |
Temporary grading easement
(71.43 sq. m. pts 2,15,16 & 32)
Permanent hydro easement (wires)
(27.99 sq. m. pts 15 & 16)
Permanent hydro easement (wires, poles and
anchors)
(7.00 sq. m. pt 32) |
10 |
Part lot 21, Plan 3896, part PIN 10104-0018(R) shown
as parts 2,15,16 & 32 on draft reference plan
94-21-413-52-a (dated August 23, 1999) |
3 |
325 Sheppard Ave E |
Halsey, Farideh |
Temporary grading easement
(73.83 sq. m. pts 3 & 17)
Permanent hydro easement (wires)
(30.48 sq. m. pt 17) |
10 |
Part lot 20, Plan 3896, part PIN 10104-0017(R) shown
as parts 3 & 17 on draft reference plan 94-21-413-52-a
(dated August 23, 1999) |
4 |
333 Sheppard Ave E |
333 Sheppard Ave. East Limited |
Temporary grading easement
(216.01 sq. m. pts 4, 18 & 40)
Permanent hydro easement (wires)
(117.91 sq. m. pts 18 & 40)
Permanent hydro easement (wires, poles and
anchors) (4.00 sq. m. pt 39) |
10 |
Part lots 16,17,18 & 19, Plan 3896, part PINS
10104-0016(R),10104-0015(R),10104-0014(R),
10104-0013(R), shown as parts 4, 18, 39, 40 & 41 on
draft reference plan 94-21-413-52-a (dated August 23,
1999) |
5 |
335 Sheppard Ave E |
Tesic, Mary |
Temporary grading easement
(66.65 sq. m. pts 5,6,19 &33)
Permanent hydro easement (wires)
(27.45 sq. m. pt 19)
Permanent hydro easement (wires, poles and
anchors)
(5.44 sq. m. pt 33 ) |
10 |
Part lot 15, Plan 3896, part PIN 10104-0012(R) shown
as parts 5,6,19 & 33 on draft reference plan
94-21-413-52-a (dated August 23, 1999) |
6 |
337 Sheppard Ave E |
Schmid, Adole
Schmid, Alice |
Temporary grading easement
(60.46 sq. m. pts 7,20,26 & 34)
Permanent hydro easement (wires)
(29.61 sq. m. pt 20)
Permanent hydro easement (wires, poles and
anchors)
(1.57 sq. m. pt 34)
ROW widening
(0.91 sq. m. pt 26) |
10 |
Part lot 14, Plan 3896, part PIN 10104-0011(R) shown
as parts 7,20,26 & 34 on draft reference plan
94-21-413-52-a (dated August 23, 1999)
|
7 |
339 Sheppard Ave E |
Tarsitano, Ferdinando
Tarsitano, Dora |
Temporary grading easement
(136.77 sq. m. pts 8 & 21)
Permanent hydro easement (wires)
(24.32 sq. m. pt 21)
ROW widening
(9.41 sq. m. pt 27) |
10 |
Part lot 13, Plan 3896, part PIN 10104-0010(R) shown
as parts 8, 21 & 27 on draft reference plan
94-21-413-52-a (dated August 23, 1999) |
8 |
341 Sheppard Ave E |
Stebelko, Wiktoria |
Temporary grading easement
( 163.42 sq. m. pts 9,22,23 & 35)
Permanent hydro easement (wires)
( 25.07 sq. m. pts 22 & 23)
Permanent hydro easement (wires,poles and
anchors)
( 6.98 sq. m. pt 35)
ROW widening
( 24.57 sq. m. pt 28) |
10 |
Part lot 12 & 13, Plan 3896, part PIN 10104-0009(R)
shown as parts 9,22,23,28 &35 on draft reference plan
94-21-413-52-a (dated August 23, 1999)
|
9 |
343 Sheppard Ave E |
Pokohoy, Sherry
Pokhoy, Neil |
Temporary grading easement
(160.02 sq. m. pts 10 & 24)
Permanent hydro easement (wires)
(29.01 sq. m. pt 24)
ROW widening
( 30.45 sq. m. pt 29) |
10
|
Part lot 11 & 12, Plan 3896, part PIN 10104-0008(R)
shown as parts 10, 24 & 29 on draft reference plan
94-21-413-52-a (dated August 23, 1999) |
10 |
345 Sheppard Ave E |
Stanco Properties Ltd. |
Temporary grading easement
(131.67 sq. m. pts 11,25 &36)
Permanent hydro easement (wires)
( 18.96 sq. m. pt 25)
Permanent hydro easement (wires, poles and
anchors)
( 10.56 sq. m. pt 36)
ROW widening
( 25.89 sq. m. pt 30) |
10 |
Part lots 10 & 11, Plan 3896, part PIN 10104-0007(R)
shown as parts 11,25,30 & 36 on draft reference plan
94-21-413-52-a (dated August 23, 1999)
|
11 |
461 Sheppard Ave E |
Imerial Oil Limited |
Temporary grading easement
(706.44 sq. m. pts 12,37 & 38)
Permanent hydro easement (wires, poles and
anchors)
(12.96 sq. m. pts 37 & 38)
ROW widening
( 339.43 sq. m. pt 31) |
10 |
Part lots 8,9 &10 and part Block A, Plan 3896, part PIN
10104-0006(R) shown as 12,31,37 & 38 on draft
reference plan 94-21-413-52-a (dated August 23, 1999)
|
12 |
2818 Bayview Ave |
IBC Ventures Inc. |
Temporary grading easement
(196.87 sq. m. pts 13) |
10 |
Part lots 5,6,7 & 8, Plan 3896, part PIN 10104-0005(R)
shown as 1,2,3 & 4 on draft reference plan
94-21-413-52-a (dated August 23, 1999)
|
NORTHWEST QUADRANT OF INTERSECTION OF SHEPPARD AVENUE EAST AND BAYVIEW AVENUE |
13 |
432 Sheppard Ave E |
Roman Catholic Episcopal Corp. For
the Diocese of Toronto on Canada |
Temporary grading easement
(253.59 sq. m. pts 11,12, 13, 19 & 20)
ROW widening
( 201.06 sq. m. pts 8,9 & 10)
Permanent hydro easement (wires, poles and
anchors) (8.00 sq. m. pts 19 & 20) |
10
|
Part lot 16, Con 1 E.Y.S., Part lot 1, Plan 3572 part PIN
10066-0141 shown as 8,9,10,11,12,13 19 & 20 on draft
reference plan 94-21-413-52-B (dated August 23, 1999)
|
14 |
436 & 438 Sheppard Ave. E |
438 Sheppard Avenue East Ltd. |
Temporary grading easement
(287.18 sq. m. pts 14 & 15)
ROW widening
( 156.95 sq. m. pts 6 & 7)
Permanent hydro easement (wires, poles and
anchors) (1.11 sq. m. pt 21) |
10 |
Part lots 1 & 2, Plan 3572, part PINs 10066-0142 and
10066-0143 shown as 6,7,14 & 15 on draft reference
plan 94-21-413-52-B (dated August 23, 1999)
|
15 |
442 & 446 Sheppard Ave E |
Berkim Holdings Ltd.
|
Temporary grading easement
( 243.67 sq. m. pts 17 & 18)
ROW widening
( 174.24 sq. m. pts 4,5 & 16)
|
10 |
Part lots 3 & 4, Plan 3572, part PINs 10066-0145 and
10066-0146 shown as parts 4,5,16,17 & 18 on draft
reference plan 94-21-413-52-B (dated August 23, 1999)
|
16 |
500 Sheppard Ave E |
Mallpaks Developments Ltd. |
Permanent hydro easement (wires)
(300.06 sq. m. pts 1,2 & 3) |
N/A |
Part lots 5,6 & 7, Plan 3572, part PIN 10066-0193
shown as 1,2 & 3 on draft reference plan 94-21-413-52-B
(dated August 23, 1999)
|
17 |
2880 Bayview Avenue |
Incumbent and Church Wardens of
All Souls Church |
Temporary grading easement
(245.68 sq. m. pts 7,9 & 10)
ROW widening
( 56.56sq. m. pts 6, 8 &11)
|
10 |
Part lot 16, Con 2, part PIN 10066-0150 shown as
6,7,8,9,10 & 11 on draft reference plan 94-21-413-52-C
(dated July 16, 1999)
|
NORTHEAST QUADRANT OF INTERSECTION OF SHEPPARD AVENUE EAST AND BAYVIEW AVENUE |
18 |
2901 Bayview Avenue |
Verdiroc Holdings Ltd.(50%)
Daniels Financial Corporation (25%)
John Henry Daniels (25%) |
Temporary grading easement
(798.33 sq. m. pts 1,2,3,4 &5) |
10
|
Part lot 16, Con 2, part PIN 10061-0152 shown as
1,2,3,4 & 5 on draft reference plan 94-21-413-52-C
(dated July 16, 1999)
|
19 |
640 Sheppard Avenue E |
Westdale Construction Co. Ltd. |
Temporary grading easement
(187.85 sq. m. pt 3) |
10 |
Part lot 16, Con 2 EYS, part PIN 10066-0194(R) shown
as part 3 on draft reference plan 94-21-413-52-E (July
16,1999)
|
SOUTHEAST QUADRANT OF INTERSECTION OF SHEPPARD AVENUE EAST AND BAYVIEW AVENUE |
20 |
593 Sheppard Avenue E |
The Trustees of the Ellis Street Free
Church |
Temporary grading easement
(208.66 sq. m. pt 1) |
10 |
Part lot 3, Plan 3583, part PIN 10090-0151(R) shown as
part 1on draft reference plan 94-21-413-52-E ( dated July
16,1999 )
|
21 |
26 Rean Avenue |
Constance Fox |
Temporary grading easement
(90.73 sq. m. pt 2) |
10 |
Part lot 4, Plan 3583, part PIN 10090-0152(R) shown as
part 2 on draft reference plan 94-21-413-52-E (dated July
16,1999) |
22 |
567 Sheppard Avenue E. |
YMCA of Metropolitan Toronto |
Temporary grading easement
(662.44 sq. m. pts 5,6 & 7)
Permanent hydro easement (wires, poles and
anchors)
(4.03 sq. m. pt 7)
ROW widening
( 58.38 sq. m. pt 8) |
10 |
Part lots 3,4 & 5 Plan 3439, part of PINs 10090-0352(R)
shown as parts 5,6,7 & 8 on draft reference plan
94-21-413-52-D (dated August 19, 1999) |
23 |
2831 Bayview Avenue |
Shell Canada Ltd. |
Permanent hydro easement (wires, poles and
anchors)
( 18.54 sq. m. pts 3,4 & 9)
ROW widening
( 207.68 sq. m. as pt 2) |
N/A |
Part lots 1 & 2, Plan 3439, part of PIN 10090-0002(R)
shown as parts 2,3,4 & 9 on draft reference plan
94-21-413-52-D (dated August 19,1999) |
|
|
|
Please note that council and committee documents are provided electronically for information only and do not retain the exact structure of the original versions. For example, charts, images and tables may be difficult to read. As such, readers should verify information before acting on it. All council documents are available from the City Clerk's office. Please e-mail clerk@toronto.ca. |
|