November 10, 1999
To: Policy & Finance Committee
From: Josephine Bryant
Subject: Eatonville Library Reconstruction
430 Burnhamthorpe Road
Markland-Centennial - Ward 4
Purpose:
To transmit the Quantity Surveyor's total projected budget for the Eatonville Library
Reconstruction project to the Policy & Finance committee as requested by Budget Committee to
enable construction to proceed.
Financial Implications and Impact Statement:
City Council approved design costs of $150,000 on December 16, 1998. Council subsequently
approved additional funds in the 1999 Capital Budget to bring the funding up to $875,000. The
2000 Capital Budget provides additional funding for a total project cost of $3,050,000.
Construction costs are anticipated to be within budget.
Recommendations:
It is recommended that:
(1) the Eatonville Library Reconstruction report as requested on January 9, 1999 be received
for information; and that
(2) City Council approval be given to proceed with construction.
Background:
A design contract has been entered into with Stephen Teeple Architect Incorporated, construction
drawings are completed and tender documents are expected to be completed following an Open
House in November 1999. The Library's proposed timetable is to close the tender call before the
end of 1999, and a recommendation will be made to the Library Board at its meeting on January
24, 2000.
The work of the contractor will be to demolish the existing building on or before April 1, 2000.
Construction is expected to take one year.
The Eatonville Library reconstruction project was originally conceived of by the former
Etobicoke Public Library Board in the early 1990's, and was contained in the new Toronto
Public Library Board's 1998 Capital Budget forecast.
Comments:
Further information is available in the attached report containing a recommendation which was
approved by the Toronto Public Library Board at its meeting on October 18, 1999.
Conclusions:
Approval of the recommendation in the Library's report to the Policy and Finance Committee
will enable the Library to proceed with construction beginning in the early spring of 2000.
Contact:
Ann Eddie, Director, Administration, Tel: 393-7091, Fax: 397-5980, Email:
aeddie@tpl.toronto.on.ca.


City Librarian
List of Attachments:
(1) Eatonville Library Reconstruction report to the Toronto Public Library Board - October 18,
1999
(2) Correspondence from Stephen Teeple Architect Incorporated regarding the Eatonville Public
Library
Attachment #1
To: Toronto Public Library Board - October 18, 1999
From: City Librarian
Subject: Eatonville Library Reconstruction
Purpose:
To update the Board on the status of the Eatonville Library reconstruction project.
Funding Sources, Financial Implications and Impact Statement:
Design costs of $150,000 for the Eatonville Library project were approved by City Council at its
meeting of December 16 and 17, 1998. Approval was given to allow for the production of working
drawings, and the funding was to include the employment of a Quantity Surveyor to determine the
cost of the project. Subsequent to the cost estimate, the City Librarian was requested by the Budget
Committee to report "to Budget Committee on the details/justification of the estimated $2.9 million
Eatonville reconstruction expenditure before any construction-related expenditure is incurred."
Recommendation:
It is recommended that the Toronto Public Library Board approve the Eatonville Library
Reconstruction report for transmittal to the Policy and Finance Committee.
Comments and/or Discussion and/or Justification:
At its meeting on March 22, 1999, the Board approved awarding the contract to provide architectural
services and cost estimates for the reconstruction of the Eatonville Library to Stephen Teeple
Architect Inc.
In consultation with Public Service and Facilities staff, the architect developed a design, and working
drawings were completed in August 1999. Helyer and Associates were subsequently employed by
the architect, to determine construction costs based on a working drawing estimate.
Total cost of the project, including construction, demolition of the existing building, site
development costs and all associated costs has been submitted at $2,905,845 (see Attachment 2).
Staff will be proceeding to Budget Committee as directed to seek approval to begin construction.
Contact Names:
Ann Eddie, Director Administration, Tel: 393-7091, Fax: 397-5980, aeddie@tpl.toronto.on.ca
Nancy Chavner, Director, West Region, Tel: 394-5005, Fax: 394-5009, nchavner@tpl.toronto.on.ca


Josephine Bryant
City Librarian
Attachment #2
S T E P H E N T E E P L E
A R C H I T E C T
I N C O R P O R A T E D
VIA FACSIMILE 416.395.5916
October 6, 1999
Mr. Bruce Barnett
Toronto Public Library Board
North York District
Plant and Facilities
120 Martin Ross Avenue
Toronto, Ontario M3J 2L4
Dear Bruce:
Re: Eatonville Public Library
Our Project No. 99-111
Please find enclosed the summary sheet for costs for the Eatonville Library. As you can
see, the cost estimate has come down somewhat from the preliminary estimate, however
removal of the oil tank and asbestos have been added. The estimate is in line with the
project of the Moffat Kinoshita feasibility study.
Please note that we have included a 1% design contingency as well as a 5% construction
contingency in this estimate.
If you have any questions regarding the summary, please do not hesitate to contact me.
Yours truly,
STEPHEN TEEPLE ARCHITECT INCORPORATED

Stephen Teeple
ST/ld
Encl. (2)
Stephen Teeple B.E.S., B.Arch., M. Sc.B.D., OA, MRAIC
Associates
Cheryl Atkinson B.E.S., B.Arch., OAA
Jeff Lauo B..Arch., M.Arch
Chris Radigan B.E.S., B. Arch
|
511 King Street W., Ste. 300
Toronto, Canada
M5V 1K4
Tel 416-598-0554
Fax 416-598-1705
Email teeple@ths-wire.com |
EATONVILLE PUBLIC LIBRARY
REPLACEMENT PROJECT

PROJECT BUDGET (recommended) - October 8, 1999
1) Construction Cost* $2,091,000
*based on working drawing estimate prepared
by Helyer & Associates, August 30, 1999. This
includes demolition of existing building and all
site development costs
2) Design Contingency (1% of Construction Cost) $20,910
3) Asbestos Removal from Existing Library $45,000
4) Removal of existing oil tank $15,000
5) Construction Contingency (5% of lines 1 - 4 ) $108,595
6) Consultants' Fees* $148,275
*based on 6.5% of lines 1 - 5 (75% of fee
allocated under existing contract to end of
Construction Document. The remaining
25% of fee required to review Tendering
and Construction Phases.)
7) Disbursements $7,350
(estimated maximum amount)
8) Cost Consultant $7,000
9) Miscellaneous Expenses
Printing $20,000
Advertising 500
Solls Survey 4,000
Site Survey 3,500
Flow Teet 350
Building Permit 23,750
Site Plan Application 615
$52,715 $52,715
Subtotal $2,495,845
10) Furniture, Fittings and Equipment $400,000
11) Relocation / Moving Expenses $10,000
Total Project Budget $2,905,845
*estimate excludes GST
|