BU40.6 

ACTION

Adopted 

 

Ward:38 

Toronto Public Library - Capital Budget Adjustments
Committee Decision

The Budget Committee recommends to the Executive Committee that:

 

1.         City Council approve a $1.059 million gross and $0 net increase to the Council approved Library capital budget for the Scarborough Civic Centre Library project, fully funded by a $0.659 million allocation from the City’s Land Acquisition Reserve Fund and $0.400 million from the Development Charges Reserve Fund;

 

2.         City Council approve the following cash flow reallocations that have no impact on annual debt levels:

 

a.         accelerate $0.220 million gross and debt cash flow from 2013 to 2012 to fund additional 2012 cash flow requirements for the Mount Dennis Branch project; and

 

b.         defer $0.220 million gross and debt cash flow from 2012 to 2013 for the Multibranch State of Good Repair (SOGR) project.

Origin
(April 10, 2013) Report from the City Librarian
Summary

The purpose of this report is to seek approval for capital budget adjustments for: (1) non-debt funding that has become available for the Scarborough Civic Centre Library; and (2) a cash flow deferral and acceleration that do not impact debt in order to match budget funding to actual expenditures at the end of 2012.

Financial Impact

Scarborough Civic Centre

 

The Library’s capital funding for the Scarborough Civic Centre is being increased by $1.059 million gross and $0 net, funded by a $0.659 million allocation from the City’s Land Acquisition Reserve Fund and $0.400 million from the Development Charges Reserve Fund, which brings the total project budget to $9.856 million, as detailed in the table below:

 

2013 Capital Budget In-Year Adjustments ($000s)

 

 

Pre-2013

2013

2014

2015

Project total

Scarborough Civic Centre Library

 

 

 

 

 

Council approved budget

1,392

2,385

3,883

1,137

8,797

Add funding: Land Acquisition Reserve Fund

 

 

659

 

659

Add funding: Development Charges

 

 

400

 

400

Revised Budget

1,392

2,385

4,942

1,137

9,856

 

 

There is no impact on the Council approved annual debt levels.  As a result of these adjustments, the Toronto Public Library’s 2014 gross capital budget increases from $24.665 million to $25.724 million.

 

Cash Flow Reallocations

 

The Mount Dennis renovation project was slightly ahead of schedule in 2012, requiring the acceleration of $0.220 million cash flow available in 2013.  To offset this cash flow advance, a cash flow deferral of $0.220 million from 2012 to 2013 from cash flow under-expenditures in the Multibranch SOGR project is required, as shown in the table below.

 

March 2013 Capital Budget In-Year Adjustments ($000s)

 

 

2012

2013

Total

Change in timing of cash flows

 

 

 

Mount Dennis Renovation

220

(220)

-

Multibranch SOGR project

(220)

220

-

Budget change

-

-

-

 

 

The Director, Finance and Treasurer has reviewed this financial impact statement and is in agreement with it.

Background Information
(April 10, 2013) Report from the City Librarian on Toronto Public Library on Capital Budget Adjustments
(http://www.toronto.ca/legdocs/mmis/2013/bu/bgrd/backgroundfile-57667.pdf)

(April 10, 2013) Attachment 1 - Memo dated January 29, 2013 from Ray David Director, Community Planning, Scarborough Centre Branch Library Project - 150 Borough Drive Funding Sources for Enhancements
(http://www.toronto.ca/legdocs/mmis/2013/bu/bgrd/backgroundfile-57668.pdf)