BU40.6 | ACTION |
Adopted |
|
Ward:38 |
Toronto Public Library - Capital Budget Adjustments |
Committee Decision | |
The Budget Committee recommends to the Executive Committee that:
1. City Council approve a $1.059 million gross and $0 net increase to the Council approved Library capital budget for the Scarborough Civic Centre Library project, fully funded by a $0.659 million allocation from the City’s Land Acquisition Reserve Fund and $0.400 million from the Development Charges Reserve Fund;
2. City Council approve the following cash flow reallocations that have no impact on annual debt levels:
a. accelerate $0.220 million gross and debt cash flow from 2013 to 2012 to fund additional 2012 cash flow requirements for the Mount Dennis Branch project; and
b. defer $0.220 million gross and debt cash flow from 2012 to 2013 for the Multibranch State of Good Repair (SOGR) project. |
|
Origin |
(April 10, 2013) Report from the City Librarian |
Summary |
The purpose of this report is to seek approval for capital budget adjustments for: (1) non-debt funding that has become available for the Scarborough Civic Centre Library; and (2) a cash flow deferral and acceleration that do not impact debt in order to match budget funding to actual expenditures at the end of 2012. |
Financial Impact | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Scarborough Civic Centre
The Library’s capital funding for the Scarborough Civic Centre is being increased by $1.059 million gross and $0 net, funded by a $0.659 million allocation from the City’s Land Acquisition Reserve Fund and $0.400 million from the Development Charges Reserve Fund, which brings the total project budget to $9.856 million, as detailed in the table below:
2013 Capital Budget In-Year Adjustments ($000s)
There is no impact on the Council approved annual debt levels. As a result of these adjustments, the Toronto Public Library’s 2014 gross capital budget increases from $24.665 million to $25.724 million.
Cash Flow Reallocations
The Mount Dennis renovation project was slightly ahead of schedule in 2012, requiring the acceleration of $0.220 million cash flow available in 2013. To offset this cash flow advance, a cash flow deferral of $0.220 million from 2012 to 2013 from cash flow under-expenditures in the Multibranch SOGR project is required, as shown in the table below.
March 2013 Capital Budget In-Year Adjustments ($000s)
The Director, Finance and Treasurer has reviewed this financial impact statement and is in agreement with it. |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Background Information |
(April 10, 2013) Report from the City Librarian on Toronto Public Library on Capital Budget Adjustments (http://www.toronto.ca/legdocs/mmis/2013/bu/bgrd/backgroundfile-57667.pdf) (April 10, 2013) Attachment 1 - Memo dated January 29, 2013 from Ray David Director, Community Planning, Scarborough Centre Branch Library Project - 150 Borough Drive Funding Sources for Enhancements (http://www.toronto.ca/legdocs/mmis/2013/bu/bgrd/backgroundfile-57668.pdf) |