BU56.2 

ACTION

Adopted 

 

Ward:All 

Capital Variance Report for the Five-Month Period Ended May 30, 2014
Committee Decision

The Budget Committee recommends to the Executive Committee that:

 

1.         City Council approve the following adjustments to the 2014 Approved Capital Budget and 2015-2023 Capital Plan for Shelter, Support and Housing Administration to ensure proper funding is in place to tender and award a contract to hire a project manager to complete the feasibility analysis for the Shelter Development / Redevelopment Project:

           

a.         adjust the 2014 Approved Capital Budget for Shelter, Support and Housing Administration by reallocating $0.651 million gross and debt, with cash flow in 2014, from the Capital Repairs/ Replacement City Project to the Shelter Development/Redevelopment project; and

 

b.         amend the 2015-2023 Capital Plan for the Shelter Development/ Redevelopment project by approving a 2015 cash flow commitment of $1.000 million which is currently approved in 2015 as a future year plan estimate.

 

2.         City Council request the Toronto Transit Commission to identify either scope reductions or reallocations from other projects to ensure cash flow for Toronto Rocket Yard and Storage Tract Accommodation and Leslie Barns LRT Maintenance and Storage Facility do not exceed the 2014 Approved Capital Budget and report back prior to year-end with any changes that require City Council authority.

 

3.         City Council approve in-year budget adjustments to the 2014-2023 Approved Capital Budget and Plan detailed in Appendix 2 to the report (July 21, 2014) from the Deputy City Manager and Chief Financial Officer with no incremental impact on debt funding.

 

4.         City Council receive for information Appendix 3 to the report (July 21, 2014) from the Deputy City Manager and Chief Financial Officer which lists one (1) capital project for Court Services that has been cancelled and will be closed.

 

5.         City Council authorize and direct the appropriate City Officials to take the necessary action to give effect thereto.

Origin
(July 21, 2014) Report from the Deputy City Manager and Chief Financial Officer
Summary

The purpose of this report is to provide Council with the 2014 Capital Variance Report for the five month period ended May 31, 2014 as well as projected actual expenditures to December 31, 2014.  Furthermore, the report seeks Council’s approval for 2014 in-year budget adjustments.

 

This report also provides for information the cancellation of one capital project for Courts Services that will be closed, with funding of $0.140 million to be returned to Court Services Stabilization Reserve.

 

Capital expenditures for the five months ended May 31, 2014 totalled $628.339 million or 14.8 percent of the 2014 Approved Capital Budget of $4.258 billion (see Table 1 below). This spending pattern is consistent with prior years as the City's capital activities tend to accelerate in the second part of the year. As detailed by City Program and Agency in Appendix 1 to the report (July 21, 2014) from the Deputy City Manager and Chief Financial Officer, actual expenditures to year-end are expected to reach $3.248 billion or 76.3 percent of the total 2014 Approved Capital Budget; 24 of 33 City Programs and Agencies are projecting spending in excess of 70 percent by year-end: Tax Supported Programs project a spending rate of 75.9 percent to year-end; while Rate Supported Programs project year-end spending rate of 78.1 percent.

 

Table 1

Corporate Capital Variance Summary

for the Period  Ended May 31, 2014

($000s)

 

2014
Approved Budget

Actual Expenditures - January 1 to May 31, 2014

Projected Actual Expenditure
at Year-End

$000s

%

 

%

 

 

 

 

City Operations

1,343,121

164,514

12.2

995,257

74.1

Agencies

2,126,386

323,676

15.2

1,636,848

77.0

Sub Total - Tax Supported

3,469,506

488,190

14.1

2,632,106

75.9

Rate Supported Programs

788,464

140,149

17.8

615,979

78.1

TOTAL

4,257,970

628,339

14.8

3,248,084

76.3

 

The rate of spending in the first five months was driven largely by expropriation process delays for the acquisition of various sites, poor weather conditions, longer than planned timelines to obtain necessary approvals or required permits; delays in securing funds from cost-sharing partners; design issues and difficulty in securing necessary resources for project delivery.

Background Information
(July 21, 2014) Report from the Deputy City Manager and the Chief Financial Officer on Capital Variance Report for the Five-Month Period Ended May 30, 2014
(http://www.toronto.ca/legdocs/mmis/2014/bu/bgrd/backgroundfile-72331.pdf)

(July 21, 2014) Appendix 1 - 2014 Consolidated Capital Variance Report for the Five months Ended May 31, 2014
(http://www.toronto.ca/legdocs/mmis/2014/bu/bgrd/backgroundfile-72332.pdf)

(July 21, 2014) Appendix 2 - In-Year Adjustments for the Five months Ended May 31, 2014
(http://www.toronto.ca/legdocs/mmis/2014/bu/bgrd/backgroundfile-72333.pdf)

(July 21, 2014) Appendix 3 - Capital Project to be Closed
(http://www.toronto.ca/legdocs/mmis/2014/bu/bgrd/backgroundfile-72334.pdf)

(July 21, 2014) Appendix 4 - Capital Variance Explanation - Programs and Agencies
(http://www.toronto.ca/legdocs/mmis/2014/bu/bgrd/backgroundfile-72335.pdf)