At its meeting on Wednesday, June 17, 1998, the Commission considered the attached
report entitled, "Sheppard Subway Status Of Permits And Approvals."
The Commission received the foregoing report and requested that a copy be forwarded to
the North York Community Council for information.
Sincerely,
Vincent Rodo
1-64
Attachment
TORONTO TRANSIT COMMISSION
REPORT NO. 30
MEETING DATE:June 17, 1998
SUBJECT:SHEPPARD SUBWAY
STATUS OF PERMITS AND APPROVALS
RECOMMENDATION
It is recommended that the Commission receive this report for information.
FUNDING
Funds for this Sheppard Subway project expenditure are included in the TTC 1998-2002
Capital Program (as set out on pages 695-705 - Sheppard Subway Category) as approved by
City of Toronto Council on April 29, 1998. The project is currently forecast to over-run the
project budget.
BACKGROUND
At its meeting on May 20, 1998 the Commission received for information the report entitled
"Sheppard Subway Status of Permits and Approvals". That report indicated that TTC
requires site plan approval, foundation permits and building permits for each Sheppard
Subway construction contract. The aim is to have site plan approval and building permits
within six to eight weeks after award of each construction contract. To date, the schedule for
approval of the necessary permits has not been achieved due, in large part, to the
introduction of site plan conditions that are not within the scope of the project budget. Site
plan approval is normally required prior to the issuance of foundation and/or building
permits.
The Commission then approved that "staff report on the critical path for completion of the
Sheppard Subway including tenders, site plan approvals, building permits, design work,
tunnelling work and any other appropriate deadlines associated with the project." The
report herein is staff's response to that approval.
DISCUSSION
Exhibit 1 provides an overview of the project critical path, and Exhibit 2 tabulates the
current status of the necessary permits and approvals for the Sheppard Subway station
contracts. If any of the activities in the critical path sequence is delayed, the end date of the
sequence will also be delayed by the same amount. It is therefore essential that the major
permits and approvals required for each station construction contract are received in a timely
manner. To date, in the absence of such permits, staff have reluctantly been proceeding with
construction to avoid construction delays, schedule slippage and contractor claims.
However, staff should not be put in the position of having to do this to mitigate potential
impact on the project budget and schedule.
The critical path diagram shows a sequence of summary activities for the tunnels and
stations. Those on the project critical path are black, meaning there is little or no "float" in
each of them, i.e. a delay in any one will produce a like delay in project completion. The
critical path diagram shows the dates on which we currently expect to receive these permits.
Generally, site plan approval is assumed to be required six weeks after contract award, and
building permit approval two weeks later. Of particular note:
(a)the building permit for the Twin Tunnels Emergency Exit Buildings (EEB's), submitted
for approval in Feb/97, has not yet been approved;
(c)permits for Leslie and Don Mills Stations are overdue, as construction is well underway
at both sites (foundation permits have been received);
(b)permits for Yonge, Bayview and Bessarion Stations are all on the project critical path.
The critical permits and approvals that are still to be received (all except those for Bayview
Station have been submitted for approval), and the dates by which they are required are as
follows:
Yonge Station
(a)Site Plan Approval required by 16-Sep-98
(b)Building Permit required by 30-Sep-98
Bayview Station
(a)Tree Cutting Permit required immediately
(b)Site Plan Approval required 18-Nov-98
(c)Building Permit required 02-Dec-98 1
Bessarion Station
(a)Site Plan Approval required 26-Aug-98
(b)Building Permit required 09-Sep-98
Leslie Station
(a)Building Permit required immediately (construction is underway)
Don Mills Station
(a)Site Plan Approval required immediately (construction is underway)
(b)Building Permit required immediately (partial permit issued)
Twin Tunnels
(a)Building Permit for EEB's required immediately (construction is underway)
- - - - - - - - - - - -
May 29, 1998
50-16-CJE
A0801/239141
Attachment:Exhibit 1 - Sheppard Subway Critical Path/Permits and Approvals
Exhibit 2 - Status of Permits and Approvals for the Sheppard Subway Project
STAFF SUMMARY SHEET
ENGINEERING & CONSTRUCTION BRANCH |
PREPARED BY:C.J. EscottDEPARTMENT HEAD - A.G. Bertolo
EXTENSION:3511GENERAL MANAGER - J.A. Sepulis
USER ID:DATE REQUIRED BY THE ORIGINATOR: |
PURPOSE:COMMISSION REPORT RE:SHEPPARD SUBWAY
STATUS OF PERMITS AND APPROVALS
DISCUSSION:
ALTERNATIVES:
(If applicable)
FUNDING:
(If applicable)
RECOMMENDATIONS:
|
# |
ROUTING |
CONCUR |
NON-CONCUR |
DATE |
ATTACHMENT(S) |
2 |
GM - ENG & CONST |
|
|
|
Commission Report
- Exhibit 1
- Exhibit 2
|
3 |
GM - EXECUTIVE |
|
|
|
|
GM - OPERATIONS |
|
|
|
|
DEPUTY GM - SUBWAY |
|
|
|
|
DEPUTY GM - SURFACE |
|
|
|
|
DEPUTY GM - CORPORATE |
|
|
|
ACTION REQUIRED BY CHIEF GENERAL MANAGER |
|
GENERAL COUNSEL |
|
|
|
9SIGN AGREEMENT
9RECEIVE FOR INFORMATION
9APPROVE
:APPROVE FOR SUBMISSION TO COMMISSION
9APPROVE FOR SUBMISSION TO CHAIR
___________________________________________
SIGNATURE DATE |
|
CHIEF FINANCIAL OFFICER |
|
|
|
|
MGR - HUMAN RES |
|
|
|
|
MGR - M&P |
|
|
|
1 |
CHIEF PM - SHEP SUBWAY |
|
|
|
|
|
|
|
|
|
|
|
|
|
239141
EXHIBIT 2
Status of Permits and Approvals for the Sheppard Subway Project