July 7, 1998
To: North York Community Council
From: S. Bertoia, P. Eng., Director of Engineering
Subject: Final Payment Contract 971-03, Reconstruction of Beveridge Drive, Draycott Drive,
Mission Drive and Seneca Hill Drive, 1997 Supplementary Budget
Purpose:
The purpose of this report is to seek Council's authorization to finalize the contract.
Funding Sources, Financial Implications and Impact Statement:
Funding for the above project was provided in the 1997 Supplementary Budget.
Recommendations:
It is recommended that the Chief Financial Officer and Treasurer be authorized to finalize
payment in the amount of $1,101,184.20 to Fufari Construction Co. Ltd.
Background:
Contract No. 971-030 was awarded to Furfari Construction Co. Limited on September 3, 1997
for the tendered amount of $966,683.48.
This work was for the reconstruction of the above streets including sidewalk repair. The
design and contract administration of the project was assigned by the City to the consulting
firm of Proctor & Redfern Limited.
The total cost of all work associated with this project, including consultant fees, is
approximately $1,262.000.00. The breakdown is as follows:
Contract tender amount $1,101,184.20
Engineering Fee and Testing$ 160,828.15
There is sufficient funding available in the contract accounts for this project.
The final cost of the tendered items, as stated above, is $1,101,184.20 which exceeds the
tendered amount by $134,500.72 or 13.91%. The former City of North York's Council policy
required the Management Committee's approval for contract payments which exceeded the
tendered amount by more than 5%.
The cost overun in the value of the contract is attributed to the actual measured quantities
exceeding the estimated tendered quantities in the following areas:
repair of concrete sidewalks,
removal of existing asphalt surface by grinding,
excavation of poor sub-base in the roadway,
supply of crushed limestone aggregates for the poor sub-base areas of the roadway,
supply of engineering fabric in the areas of poor sub-base, and
supply of base and surface asphalt
Contact Name and Telephone Number.
Stan Bertoia, P.Eng.
Director of Engineering, North York District
Telephone: (416) 395-6235
Fax No. (416) 395-0349
E-Mail: sbertoia@city.north-york.on.ca
Respectfully submitted,
(Copies of attached maps, are on file in the office of the City Clerk.)