July 6, 1998
To:Toronto Community Council
From:Commissioner of Urban Planning and Development Services, upon application by
St. Michael's Hospital on behalf of the Sisters of St. Joseph for the Diocese of Toronto, 30
Bond Street, Toronto, Ontario M5B 1W8
Subject:Preliminary Report, Rezoning Application No. 198011, St. Michael's Hospital, 30
Bond Street, to permit a 4-phased expansion of the existing hospital. (Ward 24: Downtown)
Purpose:
To introduce Rezoning Application No. 198011 to Community Council to permit a
4-phased expansion of the existing St. Michael's Hospital, 30 Bond Street, upon application
by St. Michael's Hospital on behalf of the Sisters of St. Joseph for the Diocese of Toronto,
30 Bond Street, Toronto, Ontario M5B 1W8.
Funding Sources:
Not applicable.
Recommendations:
- That I be requested to hold a public meeting in the community to discuss the application,
and to notify owners and tenants within 300 metres of the site, the Toronto East
Downtown Residents Association, and the Ward Councillors.
- That the owner submit to the Commissioner of Urban Planning and Development
Services the following additional information and plans:
- Revised plans for the desired Site Plan Approvals for the Queen Street renovations
and the 5-storey addition to Wing C on Victoria Street, containing floor plans and
more detailed elevations; and
- As required by the Official Plan, a statement from the agency primarily responsible for
approving the construction of the expansion, indicating the need for, and authorizing the
planning or construction of, the expansion.
- That the applicant be advised that, prior to final Council approval of this project, the
applicant may be required to submit a Noise Impact Statement and a Material Recovery
and Waste Reduction Plan, and if necessary for the development, a Transportation
Demand Management Plan, in accordance with City Council's requirements. The
applicant will be further advised of these requirements, as they relate to this project, by
the Commissioner of Works and Emergency Services.
Background:
In 1977, a site-specific zoning by-law (By-law No. 755-77) was adopted to permit a major
expansion and renovation of St. Michael's Hospital, with a minor revision in 1978. Those
expansion plans called for a major new wing on Victoria Street (Wing C), and the
demolition of Wing D in the northeast corner of the block. Loading facilities and common
outdoor space were required by the by-law to be constructed in the northeast corner of the
block, and common outdoor space was also required in the southwest corner of the block.
The 11-storey Wing C has recently been completed, but the demolition of Wing D has never
been carried out, and the southwest corner of the block is still used for surface parking. The
existing complex is thus not in compliance with the site-specific zoning by-law.
Comments:
Location:
The 13,260 m2 site comprises the entire city block bounded by Queen, Victoria, Shuter and
Bond Streets, and currently contains the main St. Michael's Hospital complex.
Development Proposal:
With the recent amalgamation with Wellesley Hospital, St. Michael's Hospital is again
planning for future expansion, in a 4-phased program. The first phase involves
improvements to the grade-related facade and main entrance on Queen Street East. The
proposed improvements include an improved entrance lobby and an improved relationship
to the street. Another phase involves the expansion of the existing emergency facilities in the
northwest corner of the hospital into the existing Wing D to the east. This will be an internal
renovation. A third phase involves adding 5 more floors (24.4 m), including a mechanical
floor, to the existing, newly constructed 11-storey Wing C on Victoria Street, and a
long-term future phase involves the replacement of the existing 9-storey Wing D with a
9-storey building. This last phase will include the consolidation of loading and garbage
handling facilities and a 3-level below-grade parking garage (138 spaces) in the new Wing
D, and will include new landscaped open spaces in the southwest corner of the block as well
as on either side of the existing Bond Street pedestrian entrance.
The 5-storey addition to Wing C will add 14,820 m2 of gross floor area to the existing
77,343 m2 of floor area in the hospital, and the replacement of Wing D will result in a
further net increase of 9,424 m2. This translates in total to a density increase from the
existing 5.8 times the lot area to 7.7 times the lot area, according to the applicant's figures.
The height of Wing C will be increasing from approximately 47 m to approximately 71.4 m.
Planning Controls:
The Official Plan Part I designates the block as a "Hospital Area". The general Zoning
By-law designates the block as "Q T6.0", which permits the hospital uses at a maximum
density of 6.0 times the lot area. Site-specific Zoning By-law 755-77, as amended by By-law
358-78, permits a maximum gross floor area of 78,036 m2, a maximum height of 54.9 m
excluding mechanical penthouses, establishes a building footprint, and includes various
requirements for the location, size and/or quantity of loading and parking spaces, common
outdoor space, vehicular access ramps, ambulance bays, landscaping, and provision for a
future pedestrian tunnel under Victoria Street. A Development Agreement is registered on
title.
Amendments to Planning Controls:
Amendments are required to the Zoning By-law to permit the increases in density and
height, to alter the building footprint, to permit the phasing of the various additions and
renovations, and to alter the specifications and location of various loading, parking,
vehicular access and common outdoor space requirements. Amendments are also required to
the existing Development Agreement.
Planning Issues:
The following planning issues will require review and resolution prior to final reporting:
- Submission of more detailed plans for the Site Plan Approvals sought for the Queen
Street renovations and the 5-storey addition to Wing C. The plans submitted with the
application are concept plans only, and floor plans and more detailed elevations are
required.
- Compliance with Official Plan section 11.15, which requires a statement from the agency
primarily responsible for approving the construction of the expansion, indicating the need
for expansion at that location, and indicating whether the agency is prepared to authorize
the planning or construction of such expansion.
- Shadow impact of the 5-storey addition to Wing C on the public pedestrian environment.
This may not be a significant issue given the higher buildings in the financial core to the
west and southwest. I am prepared to carry out a shadow impact analysis in-house.
- Parking and loading, and related vehicular access, in terms of location, type, design
and/or quantity, as applicable.
- Verification of the existing gross floor area, and thus the total gross floor area after
expansion. Past submissions have indicated a higher existing gross floor area than
indicated in the current application. The City's own records indicate a higher existing
floor area.
- Other issues have also arisen, which do not necessarily need resolution prior to final
reporting. In a preliminary briefing by the proponent for the Toronto East Downtown
Residents Association (TEDRA), prior to submission of the application, TEDRA
members raised concerns about the safety and security of the proposed landscaped open
spaces on Bond and Queen Streets. While a legitimate concern, the applicant is not
currently seeking Site Plan Approval for these areas. When such approval is sought in the
future Phase 4, design elements to mitigate such concerns will then be considered.
The applicant has advised that a construction start for the Queen Street renovations is
desired for the Fall of 1998. While it should be possible to complete the rezoning this Fall,
the Site Plan Approval, and thus the issuance of a building permit for these alterations, is not
likely to precede the adoption of a new site-specific Zoning By-law, given the current state
of non-compliance of the hospital complex with the existing site-specific Zoning By-law, as
discussed above. The applicant has expressed a desire to proceed with such a Site Plan
Approval in advance of the rezoning, and that may not be possible. I will be reviewing this
matter in greater detail.
Conclusions:
The application should proceed to a community public meeting, after which, subject to
resolution of the relevant concerns outlined above and any other concerns which may arise
in response to the circulation of plans and public comment, a final report will be prepared.
Contact Name:
Peter Langdon
City Planning Division, East Section
Tel: 416-392-7617
Fax: 416-392-1330
Email: plangdon@city.toronto.on.ca
Beate Bowron
Acting Director, City Planning
Toronto Community
(p:\1998\ug\uds\pln\to981655.pln)-tm
APPLICATION DATA SHEET
Site Plan Approval: |
Y |
|
Application Number: |
198011 |
Rezoning: |
Y |
|
Application Date: |
June 12, 1998 |
O. P. A.: |
N |
|
Date of Revision: |
|
Confirmed Municipal Address:30 Bond Street
Nearest Intersection: |
Block bounded by Queen/Victoria/Shuter/Bond Streets. |
|
|
Project Description: |
St. Michael's Hospital expansion. |
Applicant:
St. Michael's Hospital
30 Bond Street
864-5840 |
Agent:
|
Architect:
A. J. Diamond, Donald
Schmitt & Co.
2 Berkeley Street
862-8800 |
PLANNING CONTROLS (For verification refer to Chief Building Official)
Official Plan
Designation: |
Hospital Area |
Site Specific
Provision: |
755-77; 358-78 |
Zoning District: |
Q T6.0 |
Historical Status: |
Listed |
Height Limit (m): |
46.0 |
Site Plan Control: |
Yes |
PROJECT INFORMATION
Site Area: |
13260.0
m2 |
|
Height: |
Storeys: |
15 + Mech. Pent |
Frontage: |
|
|
|
Metres: |
76.40 |
Depth: |
|
|
|
|
|
|
|
|
|
Indoor |
Outdoor |
|
|
Ground Floor: |
|
|
Parking
Spaces: |
138 |
|
|
|
Residential
GFA: |
|
|
Loading
Docks: |
1 |
A |
|
|
|
|
Non-Residential GFA: |
102093.0
m2 |
|
(number,
type) |
5 |
B |
|
|
|
|
Total GFA: |
102093.0
m2 |
|
|
2 |
C |
|
|
|
|
|
|
FLOOR AREA BREAKDOWN |
|
|
|
|
|
Land Use |
Above
Grade |
Below
Grade |
|
|
|
|
|
Existing |
77849.0 m2 |
|
|
|
|
|
|
To Be Demolished |
9111.0
m2 |
|
|
|
|
|
|
Addition |
33355.0 m2 |
|
PROPOSED DENSITY |
|
|
Residential Density: |
Non-Residential Density: 7.70 |
Total Density: 7.70 |