April 30, 1998
To:Urban Environment and Development Committee
From:Interim Functional Lead, Transportation
Subject:Improvements to Bicycle and Pedestrian Trails in the vicinity of the Humber Bridges Project.
Lakeshore - Queensway; Councillors Irene Jones, Blake Kinahan
Purpose:
To report on options for improving bicycle and pedestrian trails in the vicinity of the Humber Bridges Project.
Funding Sources:
The funds associated with the proposed feasibility study can be provided under the Transportation Department=s
Approved Capital Programme for 1998. The estimated cost is $30,000.00 for the feasibility study. Funds for the
construction of the proposed improvement are not currently provided for under the Humber Bridges Project.
Recommendation:
It is recommended that this report be received for information.
Background;
At the February 25, 1998 meeting of the Task Force on the Lakeshore Gardiner Corridor, transportation staff were
requested to give a presentation on the current status and future scenario and schedule of the Humber Bridges Project
(HBP). Questions arose about the trail networks around the project and in particular focused on the perceived need for an
underpass of the railway embankment (key number 22, circled on the attached drawing). This is to allow an improved
connection, where none presently exists, from the Lake Shore Trail, the riverside promenade adjacent to the Palace Pier and
Palace Place Condominiums and the Humber River Pedestrian/Bicycle Bridge to the Tommy Thomson Trail, along the
west-side of the Humber River.
Discussion:
A design principle from the start of the Humber Bridges Project has been to ensure that sufficient clearance would be
provided under the new Humber Bridges to comfortably accommodate pathway links on both banks of the river.
During discussions which ultimately led to the design of the Humber River Pedestrian/Bicycle Bridge, project staff of the
former Metropolitan Toronto Transportation Department invited the involvement of representatives of a wide range of
special interest groups, other former Metropolitan Toronto departments, departments of the former cities of Toronto and
Etobicoke, Provincial Government Departments and the Waterfront Regeneration Trust. This group was known as the
Inter-Agency Review Group (IARG).
The IARG established the layout of a network of parkland trail links in the vicinity of the Humber Bridges. The alignments
of these links are shown on the attached drawing. This design of the trail network, which best served the area and which
satisfied the concerns of the IARG members, identified the need for a new underpass of the CN Railway embankment on
the west side of the Humber River. This was to accommodate a future link from the lakeshore parks to the existing Tommy
Thompson Trail up the west side of the Humber River.
This important railway underpass link has never fallen within the mandate and funding of the Humber Bridges Project and
we anticipate that the cost of such a structure may be relatively high compared to the costs of the pathways themselves.
On the east side of the river there is no need for a new underpass of the railway embankment since the pathway will turn to
the east after passing under the road bridges to join the trail along the existing South Kingsway underpass of the railway.
This will be a relatively inexpensive link. Furthermore, there is no existing trail system along the east bank of the Humber
River north of the Queensway to justify the cost of any substantial additional work. We can easily include the pathways on
the east side of the Humber River in the construction of the Humber Bridges Project.
We anticipate that the pathway work on the east side of the river will be included in a supplementary contract to the
Humber Bridges Project, following the completion and opening to traffic of the final three bridges in the complex. This
supplementary contract is expected to include restoration of construction staging areas and park areas, landscaping, slope
paving under the bridges, as well as the pathway links on the east bank of the river and any necessary lighting associated
with them.
With respect to the west side pathways under our bridges, our position has been that for safety reasons they should not be
built unless and until a future underpass of the railway is in place. Furthermore, because of the urgency of completing the
Humber Bridges Project, construction of this railway underpass for the trail system should not take place until all of the six
road bridges in the Humber Bridges Project have been completed and opened to traffic.
Nevertheless, it makes practical sense to consider this railway underpass in the overall urban design context of the Humber
Bridges Project. Our Department has initiated preliminary inquiries with railway staff on this matter during our extensive
and ongoing discussions with them over the Humber Bridges Project, and we did some initial feasibility study work on the
underpass during discussions with the IARG. We are therefore well placed because of our working relationship with
engineering staff of the railway and our familiarity with this important location to play a lead role in pursuing this feature as
an addendum to the Humber Bridges Project.
Accordingly we will undertake a study to determine the feasibility of this railway underpass. The cost of the study can be
accommodated within the 1998 capital budget.
Conclusion:
Transportation staff will undertake a feasibility study, in consultation with the CN Railway, to investigate the options for a
structure to carry a future trail link under the railway embankment on the west side of the Humber River. We will report
back on the findings of the study, the preferred scheme(s) and the costs to build the underpass structure.
Contact Name and Telephone Number:
Barry Craig, Manager
Road Construction
(416) 392-8312
D. P. Floyd
Interim Functional Lead, Transportation
Reviewed by Barry Gutteridge
Commissioner, Works & Emergency Services
BC/bc;fc