June 19, 1998
Ms. Novina Wong
Clerk
City of Toronto
Station 1071, 7th Floor
Metro Hall
55 John Street
Toronto, Ontario
M5V 3C6
Dear Ms. Wong:
At its meeting on Wednesday, June 17, 1998, the
Commission considered the attached report entitled, "1998
Wheel-Trans Budget Update."
The Commission approved the Recommendation
contained in the above report, as listed below:
"It is recommended that the Commission
approve:
1. Increasing the 1998 Wheel-Trans Operating
Budget of $38.2M by up to $625,000, and the workforce complement
from 380 to 383, as set out below:
a) Increasing the Sedan Taxi service by up to
$400,000 to accommodate unbudgeted costs associated with
increased trip demand;
b) Increasing the Wheel-Trans maintenance costs
by $75,000 as a result of decreasing Orion bus reliability and
thereby delaying the planned reduction of the Wheel-Trans
Maintenance workforce; and
c) Allocating the legal costs associated with
the current Canadian Charter of Rights and Freedoms Challenge of
the Wheel-Trans application process and eligibility criteria, in
the amount of $150,000 to the 1998 Wheel-Trans Operating Budget;
and
2. Increasing the current purchase order upset
limits of the Sedan Taxi Contracts by up to $400,000 in order to
provide for these additional trips;
3. Forward this report to the City of Toronto
requesting City Council approval, through the City Budget
Committee, of a draw from the Corporate Contingency Account in
the amount of $625,000, bringing the 1998 Budget to $38.8."
The foregoing is forwarded to City of Toronto
Council for the necessary approval, as detailed in the report.
Sincerely,
Vincent Rodo
General Secretary
1-64
Attachment
TORONTO TRANSIT COMMISSION
REPORT NO.
MEETING DATE:
June 17, 1998
SUBJECT:
1998 WHEEL-TRANS BUDGET UPDATE
RECOMMENDATION
It is recommended that the
Commission approve:
1. Increasing the 1998
Wheel-Trans Operating Budget of $38.2M by up to $625,000, and the
workforce complement from 380 to 383, as set out below:
a) Increasing the Sedan Taxi
service by up to $400,000 to accommodate unbudgeted costs
associated with increased trip demand;
b) Increasing the Wheel-Trans
maintenance costs by $75,000 as a result of decreasing Orion bus
reliability and thereby delaying the planned reduction of the
Wheel-Trans Maintenance workforce; and
c) Allocating the legal costs
associated with the current Canadian Charter of Rights and
Freedoms Challenge of the Wheel-Trans application process and
eligibility criteria, in the amount of $150,000 to the 1998
Wheel-Trans Operating Budget; and
2. Increasing the current
purchase order upset limits of the Sedan Taxi Contracts by up to
$400,000 in order to provide for these additional trips;
3. Forward this report to the
City of Toronto requesting City Council approval, through the
City Budget Committee, of a draw from the Corporate Contingency
Account in the amount of $625,000, bringing the 1998 Budget to
$38.2 million.
FUNDING
The 1998 Wheel-Trans Operating
Budget did not provide sufficient funds to accommodate the
increased demand, accelerated decline of Orion fleet reliability,
and costs associated with the Challenge under the Canadian
Charter of Rights and Freedoms. Therefore, the additional funding
of up to $625,000 is an unbudgeted expense.
BACKGROUND
Demand
The 1998 Wheel-Trans Operating
Budget provided for a trip demand of 1,415,000. The TTC
Accessible Transit Services Plan 1998-2002, which utilized Metro
Planning Department demographic studies as well as actual
Wheel-Trans experience during 1997, and the Transit Accessibility
Needs Study prepared for the Metro Council Advisory Committee to
the TTC Task Force on Accessible Transit, predicted Wheel-Trans
demand would increase by about 3% per annum. However, the 1998
Wheel-Trans trip demand was increased by approximately 6% in
order to reflect full year impact of the significant registrant
growth throughout 1997 combined with an additional 2% projected
registrant growth in 1998 and a trip utilization rate increase of
1%.
Experience in the first half of
1998 indicates the increase in trip demand by year-end will be in
the order of 2% to 3% above the 1998 budget estimates. This
translates into an additional 40,000 trips requested. In order to
achieve the goal of a 2% unaccommodated rate for the remainder of
1998, the Wheel-Trans Operating Budget would have to be increased
by up to $400,000. The additional trips would be provided by
sedan taxi contractors because the available accessible taxi
fleet will be used to capacity and the unreliability of the aging
Orion fleet means they cannot accommodate the added demand.
Legal Costs
Legal costs associated with the
Canadian Charter of Rights and Freedoms Challenge regarding the
Wheel-Trans eligibility criteria and application process are
anticipated to be $150,000 for 1998. This Challenge was forwarded
to the Commission in March, 1998 and therefore was not provided
for in the 1998 Wheel-Trans Operating Budget.
Orion Maintenance Costs
The declining reliability of our
Orion bus fleet results in both customer inconvenience when trips
are interrupted and additional cost to achieve Wheel-Trans
budgeted service levels. In order to maintain the Orion service
levels for the remainder of 1998, the planned maintenance
workforce reduction will not be possible. Funding in the amount
of $75,000 is required to provide for additional maintenance
resources for the balance of 1998.
DISCUSSION
The 1998 Wheel-Trans Operating
Budget of $38.2M is comprised of $36.2M for service and $2.0M to
begin replacement of the aging Orion fleet scheduled to take
place over the next five years. This Orion replacement plan was
approved by the Commission in August, 1997 when the report of the
TTC Task Force on Accessible Transit and Five Year Accessible
Transit Services Plan were presented.
In 1998, staff have taken action
in order to maximize service within the funding available.
Wheel-Trans has improved scheduling efficiency and productivity
is up. New Zone Service has been introduced and consideration is
currently being given to expanding this Zone service in early
1999 rather than later as originally planned. With the
introduction of a new Cancellation Policy in 1997, the
cancellation rate initially decreased to 9%, however, the rate
has increased to 12% during 1998. This increase has had a
negative impact on our ability to provide additional trips within
the funds available. A report will be submitted later this year
recommending changes to this policy in order to bring the rate of
cancellations to an acceptable level.
The increased 1998 Wheel-Trans
demand is due to a combination of an expanding registrant base
(currently 15% or 1,800 higher than the 1998 year-end target
level of 11,600) and increased trip utilization by these
registrants. The milder winter weather, improved quality of
service, and positive response to the new Downtown Zone Service
have all contributed to this increased utilization of the service
and an overall increase in our trip demand. As a result of this
increased demand, the unaccommodated rate has risen from 2% to
4%.
Alternatives were considered to
address this additional demand. One involves maintaining service
with current funding ($36.2M) which will result in an increased
unaccommodated rate of 6.5-7.5% for the last six months of this
year (overall 5.5% for 1998). This is not an acceptable option as
it means the quality of service will continue to deteriorate to
an unacceptable level.
An alternative to use part of
the $2 million dedicated in the 1998 budget for Orion bus
replacement is not an option. This is not recommended as it will
delay the replacement of the Orion fleet, a key component of the
approved Five Year Accessible Transit Services Plan, required to
reduce operating and maintenance costs and to improve service.
Proposals for replacing the Orion Bus fleet will be tendered in
July with the approval to award a contract anticipated in August,
1998.
The recommended option is to
maintain the 2% unaccommodated rate for the remainder of 1998
(currently 4%), by maximizing the level of service available from
Orions and accessible taxis, and increasing funding by up to
$400,000 to accommodate additional taxi trips to year- end. This
additional funding would be drawn on as needed by adjusting
contracted taxi purchase orders.
In order to respond to the
reliability problems with the Orions and maintain current levels
of service, an increase of $75,000 is required for maintenance
staff in 1998. It was anticipated in the 1998 budget that a
reduction in maintenance costs could be accomplished, however,
the reliability problems experienced to-date suggest cost
reductions in this area are not realistic and could contribute to
being unable to provide service at the levels required. Our peak
hour vehicle allocation is now down to 115 vehicles while in 1997
it was still possible to schedule 117 vehicles for peak service.
With regard to the legal costs
for the challenge under the Charter of Rights and Freedoms, this
item was not foreseen in the 1998 Operating Budget and, given the
situation outlined above, this cost cannot be accommodated in the
remainder of 1998. As such, a separate allocation should be
established as part of the Wheel-Trans funding.
JUSTIFICATION
It is appropriate for the
Commission to authorize up to an additional $625,000 for the
Wheel-Trans budget to address higher than budgetted demand, the
inability to reduce our maintenance costs and the funds necessary
for the legal costs associated with the Charter challenge.
- - - - - - - - - - - -
June 8, 1998
18-52-65