June 19, 1998
Ms. Novina Wong
Clerk
City of Toronto
Station 1071, 7th Floor
Metro Hall
55 John Street
Toronto, Ontario
M5V 3C6
Dear Ms. Wong:
At its meeting on Wednesday, June 17, 1998, the
Commission considered the attached report entitled, "Russell
Hill Subway Train Accident Of August 11, 1995 Due Diligence
Checklist Update."
The Commission received the updated Due
Diligence Checklist contained in this report, which provides a
status report on the progress toward closing the Coroners
Jury Recommendations and the TTCs Internal Team
Recommendations.
The foregoing is forwarded to the City of
Toronto, the Chief Coroner of Ontario and the Province of Ontario
for information.
Sincerely,
Vincent Rodo
General Secretary
1-64
Attachment
Copy: Dr. J. Young, Regional
Coroner for TorontoMs.
J. Rush, Deputy Minister, Ontario Ministry of
Transportation
TORONTO TRANSIT COMMISSION
REPORT NO.
MEETING DATE: June 17, 1998
SUBJECT: RUSSELL HILL SUBWAY TRAIN ACCIDENT OF
AUGUST 11, 1995
DUE DILIGENCE CHECKLIST UPDATE
RECOMMENDATION
It is recommended that the
Commission:
i) Receive for information
the updated Russell Hill Subway Train Accident of August 11,
1995 Due Diligence Checklist contained in this report, which
provides a status report on the progress toward closing the
Coroner's Jury Recommendations and the TTC's Internal Team
Recommendations.
ii) Forward this report to
the Chief Coroner of Ontario, the City of Toronto, and the
Province of Ontario for information.
BACKGROUND
Six previous Due Diligence
Checklist updates were submitted to the Commission at its
meetings of April 2, 1996, May 28, 1996, July 9, 1996, December
10, 1996, March 4, 1997 and December 16, 1997.
The following definitions have
been provided to staff to clarify their meaning within the Due
Diligence Checklists:
Closed means that
every aspect of the recommendation has been addressed and
completed. There is documentation supporting the closure. For
example: a signed-off written procedure is complete and currently
being followed, the equipment is purchased and in use, or a memo
is on file detailing the reason the TTC has non-concurred. The
person responsible has signed-off on the Due Diligence Sign-off
Report.
Closed by TTC means
that every possible step has been taken by the TTC, and the
completion of the recommendation rests with an outside agency.
This applies only to Coroner's Jury Recommendations. The person
responsible has signed-off on the Due Diligence Sign-Off Report.
Open indicates
that the implementation of the recommendation is underway.
SUMMARY OF JURY AND TTC
INTERNAL TEAMS RECOMMENDATIONS
The TTC has now closed a total
of 197 of the 236 recommendations from both the Coroner's Jury
Recommendations and the Internal Teams' Recommendations. Of the
remaining 39 recommendations, 18 are scheduled to close during
1998. The following table provides a summary of the current
status of recommendations, and the status of recommendations as
reported in the last update on December 16, 1997.
CATEGORY
|
December
16, 1997
|
June 17,
1998
|
TOTAL
|
|
OPEN
|
CLOSED
|
OPEN
|
CLOSED
|
|
Training |
8
|
42
|
5
|
45
|
50
|
Track |
6
|
25
|
5
|
26
|
31
|
Transit Control |
9
|
30
|
7
|
32
|
39
|
Vehicles |
3
|
29
|
3
|
29
|
32
|
Signals Design |
10
|
22
|
9
|
23
|
32
|
Signals Maintenance |
2
|
32
|
2
|
32
|
34
|
Coroner's Jury |
9
|
9
|
8
|
10
|
18
|
TOTAL |
47
|
189
|
39
|
197
|
236
|
Percentages |
20%
|
80%
|
16%
|
84%
|
|
ONGOING STEPS
The next updated Due Diligence
Checklist, which is scheduled to be presented at the Commission
Meeting on December 2, 1998, will also be forwarded to the Office
of the Chief Coroner for Ontario, to ensure that the Chief
Coroner is apprised of our progress with respect to the
resolution of all of the recommendations stemming from the
Russell Hill Subway Train Accident.
The status of the
recommendations are also summarized and reported in the
TTCs monthly Chief General Manager's report. The TTC will
continue to present publicly to the Commission twice per year
until completion, and will outline the status of all
recommendations and any outstanding issues or deficiencies.
- - - - - - - - - - - -
June 8, 1998
13.8.8
Attachment: Due Diligence
Checklist Update -
Russell Hill Subway Train
Accident of August 11, 1995