May 21, 1998
Ms. Novina Wong
Clerk
City of Toronto
Station 1071, 7th Floor
Metro Hall
55 John Street
Toronto, Ontario
M5V 3C6
Dear Ms. Wong:
At its meeting on Wednesday, May 20, 1998, the Commission considered the attached
report entitled, "Sheppard Subway Status Of Permits And Approvals."
The Commission received the subject report for information and approved the following:
1.That staff report on the critical path for completion of the Sheppard Subway, including
tenders, site plan approvals, building permits, design work, tunnelling work and any other
appropriate deadlines associated with the project; and further
2.That any site plan approval conditions which add costs beyond the approved budget for
the Sheppard Subway project be forwarded to the City of Budget Committee and City
Council for additional project and funding approval.
The foregoing is forwarded for the information of City of Toronto Council.
Sincerely,
Vincent Rodo
General Secretary
1-64
Attachment
TORONTO TRANSIT COMMISSION
REPORT NO.
MEETING DATE:May 20, 1998
SUBJECT:SHEPPARD SUBWAY
STATUS OF PERMITS AND APPROVALS
RECOMMENDATION
It is recommended that the Commission receive this report for information (an update of this
report will be submitted to future Commission Meetings).
FUNDING
Funds for this Sheppard Subway project expenditure are included in the TTC 1998-2002
Capital Program (as set out on pages 695-705 - Sheppard Subway Category) as approved by
City of Toronto Council on April 29, 1998. This project is in jeopardy of overrunning.
BACKGROUND
As the Commission is aware, the TTC requires site plan approval, foundation permits and
building permits for each Sheppard Subway construction contract. The aim is to have site
plan approval and building permits within six to eight weeks of award of the construction
contract. To date, the schedule for approval of the necessary permits has not been achieved
due, in large part, to the introduction of site plan conditions that are not within the scope of
the project budget. Site plan approval is normally required prior to the issuance of
foundation and/or building permits.
Delays in obtaining the necessary permits and approvals prior to the start of construction
could lead to additional project costs of approximately $2 million per month.
DISCUSSION
Exhibit 1 outlines the current status of the necessary permits and approvals for the Sheppard
Subway project. The major permits and approvals which are required for each station
construction contract have the potential to delay the construction if not received on schedule.
In the absence of such permits, staff are reluctantly proceeding with construction to avoid
construction delays, schedule slippage and contractor claims with the resulting negative
impact on the project budget and schedule. Ultimately this will cause a delay to revenue
service.
Bayview Station
The necessary tree cutting permit to implement the west side location of the Hydro vaults
(opposite Mallingham Court) was considered by City Council on May 13. The overall
Dangreen property agreement (allows for Hydro vaults to be placed on Dangreen property)
will be considered by Council on June 3. Regardless of which option is implemented, the
delay in proceeding with the Hydro work has resulted in unbudgeted project costs of
$47,500 to design the west side option and to condense construction time following the
June3 Council meeting.
Don Mills Station
Of particular concern is the lack of site plan approval for Don Mills Station and the lack of a
full building permit for construction. Only a partial foundation permit has been received to
date and the site plan approval is still not resolved. Staff from North York and TTC are
discussing the issue of the covered walkway (and alternative solutions to a covered
walkway) taking into account the budget constraints.
Leslie Station
Also of concern is the lack of a foundation and/or building permit for Leslie Station. The
construction of Leslie Station is currently 15% complete. Likewise, TTC staff are
dialoguing with City staff to confirm that all issues are resolved and these permit approvals
are granted at an early date.
Bessarion
The following applications have been made:
-Site Plan Application (May 6)
-Building Permit (April 30)
Yonge
The following application has been made:
-Building Permit (May 6)
- - - - - - - - - - - -
May 8, 1998
50-20-11
A08-01/237440
Attachment:Exhibit 1 - Status of Permits and Approvals for the Sheppard Subway Project
STAFF SUMMARY SHEET
ENGINEERING & CONSTRUCTION BRANCH |
PREPARED BY:C. WheelerDEPARTMENT HEAD - A.G. Bertolo
EXTENSION:6536GENERAL MANAGER - J.A. Sepulis
USER ID:WheeleDATE REQUIRED BY THE ORIGINATOR: |
PURPOSE:COMMISSION REPORT RE:SHEPPARD SUBWAY
STATUS OF PERMITS AND APPROVALS
DISCUSSION:
ALTERNATIVES:
(If applicable)
FUNDING:
(If applicable)
RECOMMENDATIONS:
|
# |
ROUTING |
CONCUR |
NON-CONCUR |
DATE |
ATTACHMENT(S) |
2 |
GM - ENG & CONST |
|
|
|
Commission Report
- Exhibit 1
|
3 |
GM - EXECUTIVE |
|
|
|
|
GM - OPERATIONS |
|
|
|
|
DEPUTY GM - SUBWAY |
|
|
|
|
DEPUTY GM - SURFACE |
|
|
|
|
DEPUTY GM - CORPORATE |
|
|
|
ACTION REQUIRED BY CHIEF GENERAL MANAGER |
|
GENERAL COUNSEL |
|
|
|
9SIGN AGREEMENT
9RECEIVE FOR INFORMATION
9APPROVE
:APPROVE FOR SUBMISSION TO COMMISSION
9APPROVE FOR SUBMISSION TO CHAIR
___________________________________________
SIGNATURE DATE |
|
CHIEF FINANCIAL OFFICER |
|
|
|
|
MGR - HUMAN RES |
|
|
|
|
MGR - M&P |
|
|
|
1 |
CHIEF PM - SHEP SUBWAY |
|
|
|
|
|
|
|
|
|
|
|
|
|
237440
EXHIBIT 1
Status of Permits and Approvals for the Sheppard Subway Project
STATION |
CONSTRUCTION STARTED |
SITE PLAN APPLICATION |
BUILDING PERMIT |
OTHER PERMITS
APPROVALS |
AFFECTING
PROJECT
SCHEDULE |
COMMENTS |
SUBMITTED |
APPROVED |
SUBMITTED |
RECEIVED |
SUBMITTED |
RECEIVED |
Yonge |
Out to
Tender |
Yes
(Feb. 27/98) |
No |
Yes
(May 6/98) |
No |
NA |
NA |
No |
-site plan
approval required
by Sept.7/98 |
Bayview |
Station - No
Utility
Relocation -
Yes |
No |
No |
No |
No |
Tree cutting permit
deferred to the May 13/98
Council Meeting |
No |
Possibly |
-Hydro work
delayed by one
month
-redesign and
acceleration costs
resulting from
delay incurs costs
of $47,500 |
Bessarion |
Out to
Tender |
Yes
(May 6/98) |
No |
Yes
(April 30 /98) |
No |
NA |
NA |
No |
-- |
Leslie |
Yes (Aug.
13/97) |
Yes (Nov.15/95) |
Yes
(Jun18/97) |
Yes (May26/97) |
No |
NA |
NA |
Possibly |
-building permit
required ASAP |
Don
Mills |
Yes (Jan.
5/98) |
Yes (Nov.15/97) |
No |
Yes (Oct.28/97) |
Partial
Permit
only |
NA |
NA |
Possibly |
-full building
permit
required ASAP
-site plan
approval/public
meeting required
ASAP
|
Foundation permit for Phase 1 of parking structure only. No foundation and/or building
permit for station, bus terminal or Phase 2 of the Parking Structure.
|