City of Toronto  
HomeContact UsHow Do I...?Advanced search
Living in TorontoDoing businessVisiting TorontoAccessing City Hall
 
Accessing City Hall
Mayor
Councillors
Meeting Schedules
   
   
  City of Toronto Council and Committees
  All Council and Committee documents are available from the City of Toronto Clerk's office. Please e-mail clerk@city.toronto.on.ca.
   

 

Date:August 5, 1998

To:Urban Environment and Development Committee

From:Commissioner, Works and Emergency Services Department

Subject: Contract No. T-47-98

F. G. Gardiner Expressway - Saulter Street to Leslie Street

Substructure Repairs

Don River; Councillors Jack Layton, Pam McConnell

Purpose:

To increase the contract price for Contract No. T-47-98, F.G. Gardiner Expressway - Saulter Street to Leslie Street, Substructure Repairs so that additional emergency work can be carried out.

Funding Sources:

Funding for this project has previously been approved by Council and is available in Capital Account No. C-TR026, F.G. Gardiner Repairs - Parkway to Leslie Street. The Treasurer has previously certified that financing can be provided under the updated Debt and Financial Obligation Limit and that it falls within corporate debt guidelines. There are sufficient funds available in Capital Account No. C-TR026 to accommodate the extension of this Contract.

Recommendation:

It is recommended that the contract price for Contract No. T-47-98, F.G. Gardiner Expressway - Saulter Street to Leslie Street, Substructure Repairs be increased by $250,000.00 net to a total of $1,036,920.80 to accommodate the additional emergency work.

Background:

At its meeting on May 20, 1998, the Bid Committee awarded Contract No. T-47-98, F.G. Gardiner Expressway - Saulter Street to Leslie Street, Substructure Repairs to Grascan Construction Ltd. and Torbridge Construction Ltd. at a contract price of $786,920.80 (GST included).

Discussion:

The former Metropolitan Toronto Council had authorised the dismantling of the section of the F. G. Gardiner Expressway between Don Valley Parkway and Leslie Street. A report recommending the award of a contract for the railway relocation (Contract No. T-54-98) along Lake Shore Boulevard from the Don Valley Parkway to Leslie Street was presented to the Urban Environment and Development Committee on July 13, 1998. At the meeting, the Urban Environment and Development Committee deferred the consideration of the award of the contract until its meeting scheduled to be held on October 5, 1998. The physical demolition of this section of the Expressway, if Council directs, will take place some time in the future (likely in year 2000) following the completion of all required preliminary works.

This section of the Expressway has not been rehabilitated since it was built in 1964. The deterioration of this portion of the Expressway has accelerated to such a critical level that emergency repairs to the substructure must be undertaken in order to keep the Expressway in service until dismantling.

At the design stage, staff performed detailed visual inspections on the substructure in accordance with the Structure Rehabilitation Manual issued by the Ontario Ministry of Transportation. The required emergency repairs to the south cantilevers and bearing seats were identified.

During the actual repair work, a more thorough limited delamination survey was conducted to assess the general conditions of the bent cap beams. It was found that there were numerous large areas of delamination on both the vertical faces and soffit of the cap beams. These areas are directly over the westbound lanes of Lake Shore Boulevard. The delaminations will eventually spall as a result of continued corrosion of the reinforcing steel as well as vibrations from traffic on the Expressway above. Consequently, this will pose a potential threat to motorists currently using the Lake Shore Boulevard Westbound.

It is therefore recommended that, as a safety measure, this delaminated concrete be removed as soon as possible.

Conclusion:

The contract price for Contract No. T-47-98 should be increased by $250,000.00 to a total of $1,036,920.80 so that the additional emergency work can be carried out.

Contact Name and Telephone Number:

M. Chung, Manager of Structures

392-8341

T. DenesW. A. Liczyk

Executive Director, Technical ServicesChief Financial Officer and Treasurer

Barry Gutteridge

Commissioner, Works and Emergency Services Department

MC/sc/bm

 

   
Please note that council and committee documents are provided electronically for information only and do not retain the exact structure of the original versions. For example, charts, images and tables may be difficult to read. As such, readers should verify information before acting on it. All council documents are available from the City Clerk's office. Please e-mail clerk@city.toronto.on.ca.

 

City maps | Get involved | Toronto links
© City of Toronto 1998-2001