Contract No. T-38-98:
Road and Track Allowance
Reconstruction at Four Locations.
The Urban Environment and Development Committee recommends the adoption of the following report (May 14,
1998) from the Interim Functional Lead, Transportation:
Purpose:
To award a contract for the road and track allowance reconstruction at four locations.
Funding Source:
The total project cost is estimated to be $1,473,813.41 and all costs are recoverable from the Toronto Transit Commission.
The cost is summarized as follows:
(1)Bid Price Amount $1,313,813.41
(2)Other costs (estimate):160,000.00
(a) quality control testing (b) traffic signage
(c) temporary traffic control signal
____________
Total project cost $1,473,813.41
Funding for this project has been approved by Council and is available in the Toronto Transit Commission=s Track
Reconstruction Program. The Treasurer certifies that financing can be provided under the updated Debt and Financial
Obligation limit and that it falls within corporate debt guidelines.
Recommendations:
It is recommended that:
(1)Contract No. T-38-98, for the road and track allowance construction at four locations, be awarded to Crownwood
Construction Ltd. who submitted the lowest price bid in the amount of $1,313,813.41; and
(2)the appropriate City of Toronto officials be directed to take the necessary action to give effect thereto.
Comments:
On May 13, 1998 The Bid Committee opened tenders for:
Contract No.T-38-98Road and Track Allowance Reconstruction at Four Locations
NumberName $ Amount
5Crownwood Construction Ltd.1,313,813.41
4Dufferin Construction Company,
a division of St. Lawrence Cement Inc.1,396,307.20
1Pave-Al Limited and Orlando Corporation1,404,035.92
2Grascan Construction Ltd. and Torbridge Construction Ltd.1,483,555.00
6Brennan Paving and Construction Ltd.1,577,977.15
3Gazzola Paving Limited1,627,640.18
The award is subject to receipt of a favourable report from the Fair Wage and Labour Trades Office regarding working
conditions and wages of the recommended contractor and his sub-contractors, and also from the Chief Financial Officer
and Treasurer regarding the surety company who issued the Bid Bond and Agreement to Bond.
Scope of Work:
The work in this contract includes the reconstruction of the streetcar track allowance at the following locations:
(1)Lake Shore Boulevard West, between Symons Street and Royal York Road;
(2)Lake Shore Boulevard West, between Kipling Avenue and 23rd Street;
(3)Dundas Street East at Parliament Street; and
(4)Dundas Street East at Sherbourne Street.
Conclusion:
Contract No. T-38-98 should be awarded to Crownwood Construction Ltd. who submitted the lowest price bid for this
Contract.
Contact Name and Telephone Number:
Mr. B. I. Craig, Manager of Roads, Metro Hall Office, 392-8312.