City of Toronto  
HomeContact UsHow Do I...?Advanced search
Living in TorontoDoing businessVisiting TorontoAccessing City Hall
 
Accessing City Hall
Mayor
Councillors
Meeting Schedules
   
   
  City of Toronto Council and Committees
  All Council and Committee documents are available from the City of Toronto Clerk's office. Please e-mail clerk@city.toronto.on.ca.
   

 

Basement Flooding in the

Stag Hill Drive Area

The East York Community Council recommends the adoption of the following report (October14, 1998) from the Director of Quality Control and System Planning:

Purpose:

This report is to the East York Community Council for its meeting of October 14, 1998. It responds to a request for a report on the modifications/improvements to the existing sewer system required to solve the basement flooding problem in the Stag Hill Drive area, and an estimate of the associated cost.

Financial Implications:

The two alternatives to solve the basement flooding problems in the Stag Hill Drive area, and the estimated financial implications of each are as follows:

Option 1Modification/improvement to the sewer system

Cost: $1,375,000.00

Option 2Installation of back-flow valves with access chambers at the two basement flooding impacted houses.

Cost: $15,000.00

Annual maintenance cost: $200.00

Recommendations:

It is recommended that:

(1)the City use back-flow valves to solve the basement flooding in the Stag Hill Drive area; and

(2)the City enter into an agreement with the two residents experiencing basement flooding to allow the City to install and maintain back-flow valves at their residences.

Council Reference/Background/History:

Community Council at its September 16, 1998 meeting requested a report on the cost to solve the basement flooding problems in the Stag Hill Drive area by improvement to the existing sewer system.

Comments and/or Discussion and/or Justification:

Basement flooding in the Stag Hill Drive area, in the block between Leander Court and Hale Court, first surfaced during a storm on July 10, 1975. To ameliorate/solve the problem, the existing relief storm sewer along Stag Hill Drive was extended westward to encompass the problem area.

Despite the relief sewer extension, basement flooding persisted. A further review of the problem carried out by Gore and Storrie (1980) revealed that 'The extent of the flooding in the Stag Hill Drive area appears to have worsened since the construction of the relief sewer'. The continuing problem was believed to have been caused by the lack of transmission capacities to accommodate the flow from the relief sewer in both the Glenwood Crescent trunk storm sewer and its outfall to MasseyCreek. The Stag Hill Drive relief sewer exits to the Glenwood trunk storm sewer. The respective capacities were calculated to be 1.47 m3/sec for the Glenwood Crescent trunk sewer and 1.98 m3/sec for the outfall, versus 4.44 m3/sec required to handle the runoff from the currently used five-year design storm.

It should be noted that in the last five years, complaints/reports of basement flooding in the subject area were received from only two residences.

To solve the storm sewer surcharging in the Stag Hill Drive area, and thus the basement flooding problems, it will be necessary to build a relief trunk storm sewer and an outfall parallel to the existing Glenwood Crescent trunk storm sewer and its outfall to Massey Creek. The new sewer and outfall will have capacities of about 3 m3/sec. Furthermore, the drainage from the area upstream of the new sewer must be serviced by a common structure to split the flows. The existing Stag Hill Drive relief sewer will have to be enlarged and new storm sewers will be installed along Leander Court, HaleCourt and Glen Gannon Drive.

A precise cost of the required works will be derived during the design stage. In the interim, preliminary cost estimates of the project components are as follows:

Relief trunk storm sewer from

St. Clair Avenue, East to Glenwood Terrace$ 725,000.00

Outfall from Glenwood Crescent to

Massey Creek$ 245,000.00

Enlargement to the existing Stag Hill

relief storm sewer$ 265,000.00

Installation of storm sewers along Leander Court,

Hale Court and Glen Gannon Drive$ 140,000.00

Total Project Cost $1,375,000.00

The foregoing project had not been included in the current and past capital works programs because of the high cost and the low number of homes reporting basement flooding.

Two alterative solutions to the basement flooding problems in the subject area, discussed previously, are as follows:

Disconnecting downspouts at homes in the vicinity, advocated and encouraged during the construction and expansion of the Stag Hill Drive relief sewer, will relieve local sewer surcharging and should still be encouraged. However, this will not solve local basement flooding, because flows from the Stag Hill relief sewer will not be able to enter the Glenwood Crescent trunk storm sewer when it surcharges during heavy storms. On the contrary, the Stag Hill Drive relief sewer will likely act as a relief sewer to the Glenwood Crescent trunk storm sewer during heavy storms. This is the probable reason for the previously mentioned statement by Gore and Storrie about the worsening basement flooding problem.

The Stag Hill Drive area could be a candidate area, should the City decide to extend the former Cityof Toronto's free downspout disconnection program city-wide.

In response to inquiries or proposals to use back-flow valves to prevent basement flooding, the then Commissioner of Works (1987) advised that the former Borough would not encourage or discourage their use because of problems encountered by other former local municipalities. It is staff's opinion that the foregoing should not preclude their use. Experience since reveals that despite the possibility of failure/problems, their use in instances where the alternative is very expensive is appropriate.

Staff have estimated the costs to install and maintain a back-flow valve as follows:

Cost of valve, installation, including

access chamber $ 7,500.00

Annual maintenance cost$ 100.00

Conclusions:

It is much more economically feasible to use back-flow valves to solve the basement flooding problems in the Stag Hill Drive area then it is to modify/improve the local sewer system.

Contact Name:

Kim Choo-Ying

Environmental Engineer

East York Civic Centre

Tel. No.: (416)778-2218

Fax No.: (416)466-9877

 

   
Please note that council and committee documents are provided electronically for information only and do not retain the exact structure of the original versions. For example, charts, images and tables may be difficult to read. As such, readers should verify information before acting on it. All council documents are available from the City Clerk's office. Please e-mail clerk@city.toronto.on.ca.

 

City maps | Get involved | Toronto links
© City of Toronto 1998-2001