City of Toronto  
HomeContact UsHow Do I...?Advanced search
Living in TorontoDoing businessVisiting TorontoAccessing City Hall
 
Accessing City Hall
Mayor
Councillors
Meeting Schedules
   
   
  City of Toronto Council and Committees
  All Council and Committee documents are available from the City of Toronto Clerk's office. Please e-mail clerk@city.toronto.on.ca.
   

 

Installation of Four Sludge Dewatering Centrifuges

at the Main Treatment Plant - Contract No. MW9803WP

(Ward: East Toronto)

The Works and Utilities Committee recommends the adoption of the joint report dated September 23, 1998, from the Commissioner of Works and Emergency Services and the Chief Financial Officer and Treasurer.

The Works and Utilities Committee reports, for the information of Council, having requested the Commissioner of Works and Emergency Services to submit a report directly to Council for its meeting on October 28, 1998, confirming that due diligence has been completed to ensure that the existing odour control equipment will be able to successfully manage the increased gas processing which will be required due to the installation of the centrifuges.

The Works and Utilities Committee submits the following joint report (September 23, 1998) from the Commissioner of Works and Emergency Services and the Chief Financial Officer and Treasurer:

Purpose:

The purpose of this report is to award Contract No. MW9803WP for installation of four sludge dewatering centrifuges and process related equipment at the Main Treatment Plant in accordance with specifications as required by the Works and Emergency Services Department, and to request the authorization to issue a contract to the recommended bidder.

Funding Sources:

Funds are available in the appropriate account for this project.

Recommendation:

It is recommended that Contract No. MW9803WP for the installation of four sludge dewatering centrifuges and process related equipment at the Main Treatment Plant be awarded to the lowest acceptable base tenderer, W.A. Stephenson Mechanical Contractors Limited, for the Total Lump Sum Price of $4,965,000.00 including all taxes and charges.

Background:

On September 9, 1998, the Bid Committee opened the following tenders for Contract No.MW9803WP for the installation of four sludge dewatering centrifuges and process related equipment at the Main Treatment Plant:

Tenderer

Total Lump

Sum Price

$

W.A. Stephenson Mechanical Contractors Limited

4,965,000.00

Ram Mechanical Contractors Limited

5,050,000.00

Bennett Mechanical Installations Limited

5,277,000.00

Carosi Construction Limited

6,680,000.00

Comments, Discussion and Justification:

The tender submitted by the second lowest tenderer, Ram Mechanical Contractors Limited (Ram), offered five credits totalling an amount of $110,000.00 in potential savings to the tendered Lump Sum Price, which, if accepted wholly by the City, would alter the ranking of the tenderers, making Ram the lowest bidder.

Ram provided, with the tender, minimal information, simply indicating the equipment item, the supplier's name, and the corresponding credit that would be given. The information provided at the time of tender closing was insufficient to perform a proper evaluation on the acceptance of the alternates. In discussions with Ram by staff of the Works and Emergency Services Department, Ram advised that it was their intent to further discuss and provide general information and technical data on the five alternates proposed after tender submission.

The contract specifications require the tenderer to submit detailed information on any proposed equivalent equipment or material together with any price savings at the time of tendering. In the absence of these details, we are unable to evaluate the acceptability of the alternatives in the form submitted. To evaluate and accept Ram's alternatives based on detailed information submitted after the bids are opened would, in effect, give Ram an unfair advantage by providing Ram with the opportunity to make specification changes to the alternatives in order to obtain a favourable recommendation and thereby overtake the otherwise low bidder in full knowledge of its relevant ranking to the other tenderers. Accordingly, it is recommended that Ram's alternatives not be considered so that there will be no impact on the ranking for contract award. The City Solicitor advises that such a course of action would be legally unobjectionable.

Representatives of the Works and Emergency Services Department and our consultants have reviewed the tender submitted by W.A. Stephenson Mechanical Contractors Limited (Stephenson), and discussed the tender with them. Staff of the Department are satisfied that this company fully understands the contractual requirements, and has the capability to carry out the work as specified. Stephenson has successfully carried out work for this Department in the past.

Stephenson has offered a credit alternative of $20,000.00 which does not impact on the ranking of the bidders. Accordingly, the credit will be reviewed in detail following award of contract and if found acceptable will reduce the tendered Lump Sum Price of the contract.

In order to accommodate the existing quantity of sludge treated at the Main Treatment Plant, and to facilitate ongoing maintenance requirements of the dewatering centrifuges, it has been determined that four additional centrifuges are needed, bringing the total installed to 12 machines.

Accordingly, at its meeting of August 13, 1997, by adoption of Clause No. 4 of Report No. 11 of TheEnvironment and Public Space Committee, Metropolitan Council awarded Contract No.WPC-3-97 in the amount of $3,928,610.00 for the supply of four high efficiency sludge dewatering centrifuges. These units have been delivered and are currently in storage awaiting to be installed under this current installation contract. The present Contract No. MW9803WP includes the construction of necessary building modifications, installation of the equipment to be furnished under Contract No. WPC-3-97, and the supply and installation of related sludge pumping, sludge transfer, and auxiliary equipment necessary to achieve the aforementioned sludge dewatering firm capacity.

The Manager, Fair Wage and Labour Trades Office, has reported favourably on the firm recommended.

Conclusion:

This report requests authority to issue a contract for installation of four sludge dewatering centrifuges and related sludge pumping, transfer and auxiliary equipment at the Main Treatment Plant in accordance with specifications to W.A. Stephenson Mechanical Contractors Limited, being the lowest acceptable base tender received.

Contact Name:Contact Name:

Mr. P.A. Bradley, P.Eng. Mr. L.A. Pagano, Director

Senior Project EngineerPurchasing and Materials Management

Technical Services DivisionPhone: (416) 392-7312.

Phone: (416) 392-8251

 

   
Please note that council and committee documents are provided electronically for information only and do not retain the exact structure of the original versions. For example, charts, images and tables may be difficult to read. As such, readers should verify information before acting on it. All council documents are available from the City Clerk's office. Please e-mail clerk@city.toronto.on.ca.

 

City maps | Get involved | Toronto links
© City of Toronto 1998-2001