June 8, 1999

To:North York Community Council

From:Rob Dolan

Acting Director, Community Planning, North District

Subject:Final Report

Application for Part Lot Control Exemption

1165709 Ontario Limited

150 Bartley Drive

(At the north-east corner of Bartley Drive and Hobson Avenue)

Parts 1 to 24 inclusive, Plan 66R-18338

Parts 1 to 10 inclusive, Plan 66R-18337

Parts 1 to 15 inclusive, Plan 66R-18336

Parts 1 and 2, Plan 66R-18283 and

Parts 1 to 8 inclusive, Plan 66R-18339

Ward 11 - Don Parkway

UD54-99-04REL

Purpose:

The purpose of this application is to request exemption from part lot control in order that 36 townhouse units may be conveyed into separate ownership under Phase II and 60 townhouse units under Phase III of the development.

Recommendation(s):

It is recommended that:

(1)this application be approved;

(2)that the draft by-law attached as schedule "C" be enacted; and

(3)permission be given to the City Solicitor to submit a part lot control exemption by-law directly

to City Council for Phase III of the development.

Official Plan:(TMUA) Transitional Mixed Use Area

Zoning:RM5(10) - Exception to Multiple Family Dwelling Zone

Comments:

The lands were the subject of official plan and zoning amendment application UDOZ-96-25 which was approved by Council on May 14, 1997. Implementing By-law 33034, which was approved on July 9, 1997, permits the redevelopment of the lands subject to specific zoning regulations. The development is a mixed use subdivision consisting of townhouses, apartment condominiums with ground floor employment uses and a park. Phase II of this development consists of 36 townhouse units and Phase III will consists of 60 townhouse. Phase I of the development received part lot exemption by City Council on February 2, 3 and 4, 1999 under by-laws 13-1999, 14-1999, 15-1999, 16-1999 and 17-1999.

The release of part lot control would permit the conveyance of each townhouse unit and allow each unit to be held under separate ownership.

Conclusions:

This application is consistent with the city's part lot control exemption policy. The issues regarding this development have been reviewed and all matters of concern to the City, for development of the subject lands, are covered by the requirements of Zoning By-law 7625.

Contact Name:

Daniel Antonacci, Senior Planner

Phone: 395-7131

______________________________

Rob Dolan

Acting Director, Community Planning, North

Schedules:

A. Location Map

B. Site Plan

C. Draft By-law

 

   
Please note that council and committee documents are provided electronically for information only and do not retain the exact structure of the original versions. For example, charts, images and tables may be difficult to read. As such, readers should verify information before acting on it. All council documents are available from the City Clerk's office. Please e-mail clerk@toronto.ca.

 