September 23, 1999
Ms. Novina Wong
City Clerk
City of Toronto
Toronto City Hall
100 Queen Street West
Toronto, Ontario
M5H 2N2
Dear Ms. Wong:
At its meeting on Wednesday, September 22, 1999, the Commission considered the attached report entitled, "Procurement
Authorization Traffic Barriers For Spadina LRT."
The Commission adopted the Recommendation contained in the above report, as listed below:
"It is recommended that the Commission:
1)Approve a previously unscheduled and unbudgeted expenditure of $1,500,000 for the provision of permanent traffic
barriers along the Spadina LRT Streetcar line from College Street to Front Street;
2)authorize the issuance of Purchase Orders to the City of Toronto in an aggregate amount not to exceed $1,400,000,
without further authorization, for the design, contract procurement, construction, supervision and project management of
the project;
3)authorize staff to proceed with project expenditures immediately as required to comply with City Council directives
adopted at its meeting of July 27, 28, 29 and 30, 1999;
4)forward this report to the City Policy and Finance Committee for their information."
The foregoing is forwarded to the City of Toronto Policy and Finance Committee for information.
Sincerely,
Vincent Rodo
General Secretary
1-16
Attachment
TORONTO TRANSIT COMMISSION
REPORT NO.
MEETING DATE:September 22, 1999
SUBJECT:PROCUREMENT AUTHORIZATION
TRAFFIC BARRIERS FOR SPADINA LRT
RECOMMENDATIONS
It is recommended that the Commission:
1)Approve a previously unscheduled and unbudgeted expenditure of $1,500,000 for the provision of permanent traffic
barriers along the Spadina LRT Streetcar line from College Street to Front Street;
2)authorize the issuance of Purchase Orders to the City of Toronto in an aggregate amount not to exceed $1,400,000,
without further authorization, for the design, contract procurement, construction, supervision and project management of
the project;
3)authorize staff to proceed with project expenditures immediately as required to comply with City Council directives
adopted at its meeting of July 27, 28, 29 and 30, 1999; and
4)forward this report to the City Policy and Finance Committee for their information.
FUNDING
As indicated in the attached memo of July 26, 1999 from the Interim Chief General Manager to the Commission, the
proposed project is unbudgeted in the TTC's approved 1999-2003 Capital Program. As a result of Council's direction, a
new budget item has been included in the proposed 2000-2004 Capital Program for this project. To comply with City
Council's July1999 directive that design work proceed immediately and that funding be provided by TTC, staff previously
prepared a Purchase Authorization to the City in the amount of $50,000.00 to provide immediate interim funding pending
consideration of this report by the Commission.
BACKGROUND
Since being placed in service in July 1997 the Spadina LRT Streetcar line has experienced an unacceptably high level of
car/streetcar accidents at unsignalized intersections.
In July 1998, City Council approved the installation of temporary bollards adjacent to the streetcar right-of-way until such
time as an appropriate permanent barrier design could be developed and implemented in consultation with the community.
At its meeting of July 27, 28, 29 and 30, 1999, City Council adopted the following recommendations contained in Clause
No. 1 of Report No.3 of the Policy and Finance Committee:
"It is recommended that:
(1) the following recommendation of the Planning and Transportation Committee embodied in the communication dated
July 20, 1999 from the City Clerk, be adopted:
'That the funding for the installation of permanent barriers on Spadina Avenue to be erected upon the removal of the
temporary barriers by December 1, 1999, be provided by the Toronto Transit Commission'; and
(2)in order to begin design and contract preparation for the Spadina Barrier immediately, staff be authorized to retain
urban design and engineering design consultants directly, without going through a Request for Proposals procurement
process, at a cost not to exceed $150,000.00."
DISCUSSION
In response to the above City Council directives, staff from the City's Planning and Urban Development Services and
Transportation and Technical Services divisions have already assumed responsibility for managing the design, contract
procurement and construction supervision of the project and have retained the services of urban and engineering design
consultants to commence preliminary design and prepare materials for the planned public consultation process all in
accordance with the following preliminary workplan and schedule prepared by City staff:
CAugust - September 1999-Retain consultants; refine conceptual designs; develop information for public meetings
CSeptember - October 1999-Hold two public meetings
CNovember 15, 1999-Detailed design and contract documents complete
CNovember 15 - December 15, 1999-Tender and award contract
CApril 2000-Start construction
The overall cost of the project has been estimated by City and TTC Staff to be in the order of $1,500,000 which is to be
provided by TTC according to Council's decision. Of this amount, $1,400,000 will be allocated for City of Toronto costs
and $100,000 for TTC costs.
TTC Engineering and Service Planning Staff are part of the project team and TTC is to have the opportunity to review and
approve all designs and proposed construction contracts produced by the City and/or their consultants in so far as they may
impact TTC Operations. TTC staff will also participate in the public consultation process as required. All City invoices for
their own staff time or consultant services will be submitted for review and approval by TTC staff.
JUSTIFICATION
The project must proceed as described in order to comply with City Council directives.
- - - - - - - - - - - -
August 24, 1999
80-31-30
607627
Attachment
TORONTO TRANSIT COMMISSION
REPORT NO.
MEETING DATE:September 22, 1999
SUBJECT:PROCUREMENT AUTHORIZATION
TRAFFIC BARRIERS FOR SPADINA LRT
RECOMMENDATIONS
It is recommended that the Commission:
1)Approve a previously unscheduled and unbudgeted expenditure of $1,500,000 for the provision of permanent traffic
barriers along the Spadina LRT Streetcar line from College Street to Front Street;
2)authorize the issuance of Purchase Orders to the City of Toronto in an aggregate amount not to exceed $1,400,000,
without further authorization, for the design, contract procurement, construction, supervision and project management of
the project;
3)authorize staff to proceed with project expenditures immediately as required to comply with City Council directives
adopted at its meeting of July 27, 28, 29 and 30, 1999; and
4)forward this report to the City Policy and Finance Committee for their information.
FUNDING
As indicated in the attached memo of July 26, 1999 from the Interim Chief General Manager to the Commission, the
proposed project is unbudgeted in the TTC's approved 1999-2003 Capital Program. As a result of Council's direction, a
new budget item has been included in the proposed 2000-2004 Capital Program for this project. To comply with City
Council's July1999 directive that design work proceed immediately and that funding be provided by TTC, staff previously
prepared a Purchase Authorization to the City in the amount of $50,000.00 to provide immediate interim funding pending
consideration of this report by the Commission.
BACKGROUND
Since being placed in service in July 1997 the Spadina LRT Streetcar line has experienced an unacceptably high level of
car/streetcar accidents at unsignalized intersections.
In July 1998, City Council approved the installation of temporary bollards adjacent to the streetcar right-of-way until such
time as an appropriate permanent barrier design could be developed and implemented in consultation with the community.
At its meeting of July 27, 28, 29 and 30, 1999, City Council adopted the following recommendations contained in Clause
No. 1 of Report No.3 of the Policy and Finance Committee:
"It is recommended that:
(1) the following recommendation of the Planning and Transportation Committee embodied in the communication dated
July 20, 1999 from the City Clerk, be adopted:
'That the funding for the installation of permanent barriers on Spadina Avenue to be erected upon the removal of the
temporary barriers by December 1, 1999, be provided by the Toronto Transit Commission'; and
(2)in order to begin design and contract preparation for the Spadina Barrier immediately, staff be authorized to retain
urban design and engineering design consultants directly, without going through a Request for Proposals procurement
process, at a cost not to exceed $150,000.00."
DISCUSSION
In response to the above City Council directives, staff from the City's Planning and Urban Development Services and
Transportation and Technical Services divisions have already assumed responsibility for managing the design, contract
procurement and construction supervision of the project and have retained the services of urban and engineering design
consultants to commence preliminary design and prepare materials for the planned public consultation process all in
accordance with the following preliminary workplan and schedule prepared by City staff:
August - September 1999-Retain consultants; refine conceptual designs; develop information for public meetings
CSeptember - October 1999-Hold two public meetings
CNovember 15, 1999-Detailed design and contract documents complete
CNovember 15 - December 15, 1999-Tender and award contract
CApril 2000-Start construction
The overall cost of the project has been estimated by City and TTC Staff to be in the order of $1,500,000 which is to be
provided by TTC according to Council's decision. Of this amount, $1,400,000 will be allocated for City of Toronto costs
and $100,000 for TTC costs.
TTC Engineering and Service Planning Staff are part of the project team and TTC is to have the opportunity to review and
approve all designs and proposed construction contracts produced by the City and/or their consultants in so far as they may
impact TTC Operations. TTC staff will also participate in the public consultation process as required. All City invoices for
their own staff time or consultant services will be submitted for review and approval by TTC staff.
JUSTIFICATION
The project must proceed as described in order to comply with City Council directives.
- - - - - - - - - - - -
August 24, 1999
80-31-30
607627
Attachment
STAFF SUMMARY SHEET
ENGINEERING & CONSTRUCTION BRANCH |
PREPARED BY:D.A. TrudeauDEPARTMENT HEAD - T.G. Middlebrook
EXTENSION:3894GENERAL MANAGER - J.A. Sepulis
USER ID:DTRUDEAUDATE REQUIRED BY THE ORIGINATOR: |
PURPOSE:COMMISSION REPORT:PROCUREMENT AUTHORIZATION
TRAFFIC BARRIERS FOR SPADINA LRT
DISCUSSION:
ALTERNATIVES:
(If applicable)
FUNDING:
(If applicable)
RECOMMENDATIONS:
|
# |
ROUTING |
CONCUR |
NON-CONCUR |
DATE |
ATTACHMENT(S) |
4 |
GM - ENG & CONST |
|
|
|
- Commission Report
|
7 |
GM - EXECUTIVE |
|
|
|
6 |
GM - OPERATIONS |
|
|
|
|
DEPUTY GM -
SUBWAY |
|
|
|
|
DEPUTY GM -
SURFACE |
|
|
|
|
DEPUTY GM -
CORPORATE |
|
|
|
ACTION REQUIRED BY CHIEF GENERAL MANAGER |
|
GENERAL COUNSEL |
|
|
|
9SIGN AGREEMENT
9RECEIVE FOR INFORMATION
9APPROVE
:APPROVE FOR SUBMISSION TO COMMISSION
9APPROVE FOR SUBMISSION TO CHAIR
___________________________________________
SIGNATURE DATE |
5 |
CHIEF FINANCIAL
OFFICER |
|
|
|
|
MGR - HUMAN RES |
|
|
|
2 |
MGR - M&P |
|
|
|
1 |
CHIEF ENGINEER |
|
|
|
3 |
Manager -
Service Planning |
|
|
|
|
|
|
|
|
|