City of Toronto   *
HomeContact UsHow Do I...? Advanced search Go
Living in TorontoDoing businessVisiting TorontoAccessing City Hall
 
Accessing City Hall
Mayor
Councillors
Meeting Schedules
   
   
  City of Toronto Council and Committees
  All Council and Committee documents are available from the City of Toronto Clerk's office. Please e-mail clerk@toronto.ca.
   

 

STAFF REPORT

November 17, 1999

To: Policy and Finance Committee

From: Barry H. Gutteridge, Commissioner of Works and Emergency Services

Wanda Liczyk, Chief Financial Officer and Treasurer

Subject: Additional Expenditures for Work on Design-Build

Contract RFP No. 9155-99-01548 for Biosolids Truck Loading

and Odour Control Facilities

Purpose:

The purpose of this report is to advise of the requirement for additional expenditures in the amount of approximately $1.54 million, inclusive of GST, associated with the construction of biosolids truck loading and odour control facilities at the Ashbridges Bay Treatment Plant.

Financial Implications and Impact Statement:

Funding for this additional expenditure is currently not available in the approved 1999-2003 Capital Works program and was not forecasted in the preparation of our recently submitted proposed 2000-2004 Capital Works Program. Additional funding in the amount of approximately $1.48 million, after Municipal Goods and Services Tax Rebate, will be required over and above the amount currently included in our proposed 2000-2004 Capital Works Program submission as identified under Capital Account WP160-22000111, Ashbridges Bay Treatment Plant.

The Chief Financial Officer and Treasurer has reviewed this report and concurs with the financial impact statement.

Recommendation:

It is recommended that this report be received for information.

Background:

On September 24, 1997, the former Metropolitan Toronto Council adopted Clause No. 8 of Report No. 12 of the Environment and Public Space Committee, titled "Main Treatment Plant Environmental Assessment Implementation Plan", which endorsed the conclusions of the Main Treatment Plant Environmental Assessment (MTP EA), including the phased implementation of Biosolids Beneficial Use Program following the completion of four demonstration programs.

In January, 1998, the Works and Utilities Committee requested the Commissioner of Works and Emergency Services to report on the feasibility of accelerating the shutdown of incineration at the Plant. The Plant is now known as the Ashbridges Bay Treatment Plant (ABTP) as a result of the MTP EA Mediation Agreement approved by Council at its meeting of June 9, 10, and 11, 1999.

By adoption of Clause No. 2 of Report No. 6 of the Works and Utilities Committee, at its meeting of July 8, 9, and 10, 1998, City Council authorized the Commissioner of Works and Emergency Services to establish the Biosolids Multi-Stakeholder Committee (BMSC) and Independent Review Committee (IRC), retain consultants, and request proposals to allow for the shutdown of sewage sludge incinerators at the Ashbridges Bay Treatment Plant within a three-year period. This initiative is now known as the Toronto Biosolids Beneficial Use Program.

At its meeting of July 28, 1998, City Council adopted Clause No. 5 of Report No. 7 of the Works and Utilities Committee, which contained an accelerated timeline developed for planning purposes by the Committee for initial implementation of the Biosolids Beneficial Use Program. Subsequently, with input from the BMSC an aggressive timeline was set with the target date of December 31, 2000 for the end of sludge incineration at the Ashbridges Bay Treatment Plant.

By adoption of clauses embodied in Report No. 5 of the Strategic Policies and Priorities Committee at its meeting of March 2, 3, and 4, 1999, City Council authorized staff to negotiate Agreements for the beneficial use of the City's biosolids with Terratec Environmental Ltd. (Terratec) and USF Canada Inc. (USF).

The adoption of the above-noted report also authorized the use of a Request for Qualification (RFQ) followed by a Request for Proposal (RFP) as a methodology for the selection of firms to undertake design/build contracts for the necessary biosolids truck loading and odour control facilities and a plant wide heating system, as well as, authorized the shortlisting of respondents to the Request for Qualifications to receive the RFP.

At its meeting of July 27-29, 1999, City Council, by adoption of Clause No. 18 of Report No. 2 of the Works Committee approved the award of Contract RFP No. 9155-99-01548 to Icon Systems Limited (ICON) for the design, construction and commissioning of a biosolids truck loading and odour control facility at a lump sum price of $44,332,992.27, including full GST and based on the terms and conditions set out in that RFP, and otherwise on such terms and conditions satisfactory to the Commissioner of Works and Emergency Services and in a form satisfactory to the City Solicitor.

At the same meeting, City Council also approved Contract RFP No. 9155-99-01547 for the design, construction and commissioning of a plant wide heating system to Thorburn Penny Limited and amendment of the existing Agreement with Terratec Environmental Ltd., to include increased quantities of ABTP biosolids for land application.

Comments:

The scope of work included in the biosolids loading and odour control facilities contract included the following main elements:

1. The construction of a new biosolids loading and sludge storage facilities to allow for unrestricted removal of biosolids from the Plant by the land application contractor(s).

2. Provision of new odour control facilities to treat odorous air from the existing dewatering building, the existing loading facility, the new biosolids storage facility, and the new loading facility to replace the odour control currently provided by the incineration process.

3. Demolition of three existing sludge incinerators to provide space for construction of the three sludge storage silos.

As part of the Request for Proposals process for the work, an asbestos survey was undertaken by an independent consultant, selected in accordance with approved corporate policy, to identify the extent of asbestos substances within the three incinerators and components slated for demolition.

An Asbestos Survey is a part of a Designated Substance Survey, which is required under the Ontario Occupational Health and Safety Act (OH&S Act) to identify substances to contractors and subtrades prior to the tendering of construction work. The asbestos survey performed by Shaheen & Peaker Limited identified asbestos-containing materials in a number of locations, most commonly in insulating cement as well as insulation of pipes, pipe fittings and in pipe and duct gaskets. This information was documented and made available to bidders through issuance of an addendum to the original RFP document.

However, upon commencement of the actual demolition of the incinerators, additional and unanticipated quantities of asbestos-containing materials were encountered by the design/build contractor, ICON. The contractor has had the situation investigated by their own independent experts and has advised that a substantial amount of hazardous Amosite Asbestos insulation has been unexpectedly discovered between the refractory and steel shell of the three incinerators to be demolished for the construction of the sludge storage silos. This has been confirmed by the City's independent testing.

In order for the work to proceed, the asbestos-containing material must be removed using Type 3 procedures as required under the provisions of the Ontario Occupational Health and Safety Act. Type 3 operations are the most restrictive and require the following extensive measures to be undertaken: full body protective clothing from head to feet, including the use of a respirator; enclosure of work area using polyethylene sheeting from ceiling to floor and barricading area from rest of workplace; decontamination of area including change rooms and showers; and encapsulating ("glueing") the material prior to its disposal.

The additional work including the disposal of the contaminated brick and asbestos material at a licensed landfill site could extend the overall project duration by up to twenty weeks. In order to minimize the delay, the contractor will be working on a double shift basis reducing the delay to approximately five weeks. The additional cost to do the work has been estimated at $1.54 million, inclusive of GST. This asbestos abatement cost has been reviewed by City staff and our engineering consultants for the project, R.V. Anderson Associates Limited, and found to be fair and reasonable.

In order to expedite matters and to limit our liability for any delay claims, we have instructed the contractor to proceed with the necessary extra work. However, to accommodate this additional expenditure, additional financing in the amount of $1.54 million, inclusive of GST, will be required. As this extra work was not anticipated in the preparation of our proposed 2000-2004 Capital Works Program, it will be necessary to increase both the Gross Estimated Cost and the associated funding requirement for this project by an amount of $1.54 million, inclusive of GST. Accordingly, the gross estimated cost for the Biosolids Truck Loading and Odour Control Facilities (SAP No. 22000111) should be increased from $45,238,000.00 to $46,778,000.00, inclusive of GST. Appropriate amendments to our proposed 2000 Capital Budget submission will be tabled by the Department during the Capital Budget review process.

As the project is presently in its initial phase, there are sufficient funds available as per the approved 1999-2003 Capital Budget to finance the work and until the additional funds are required.

Conclusions:

In order to expedite progress on this project, to comply as closely as possible to Council's targeted completion date as well as to limit our liability for any possible delay claims, staff have authorized the Contractor to undertake the extra work at an additional cost of $1.54 million, inclusive of GST.

Contact:

William G. Crowther, P.Eng.

Director, Works Facilities & Structures

Technical Services Division

Tel. No. 392-8256

Fax. No. 392-4594

Tom G. Denes, P.Eng. Barry H. Gutteridge Wanda Liczyk

Executive Director Commissioner Chief Financial Officer

Technical Services Works and Emergency Services and Treasurer

WGC/mtro

Biosolids

 

   
Please note that council and committee documents are provided electronically for information only and do not retain the exact structure of the original versions. For example, charts, images and tables may be difficult to read. As such, readers should verify information before acting on it. All council documents are available from the City Clerk's office. Please e-mail clerk@toronto.ca.

 

City maps | Get involved | Toronto links
© City of Toronto 1998-2005