November 19, 1999
Ms. Novina Wong
City Clerk
City of Toronto
Toronto City Hall
100 Queen Street West
Toronto, Ontario
M5H 2N2
Dear Ms. Wong:
At its meeting on Wednesday, November 17, 1999, the Commission considered the attached report entitled, "Project
Approval - Fibre Optics and Subway Radio Communication Project."
The Commission approved the Recommendation contained in the above report, as listed below:
"It is recommended that the Commission approve:
(i) forwarding this report to the City of Toronto Council, requesting increased project approval of $2,334,000 (gross and
net) for City Project #231 as the expenditure for this will be required in advance of receiving approval from the City for the
2000-2004 Capital Program; and
(ii) the holding of funds in TTC accounts until additional funds are approved."
The Commission also reports having requested that a copy of this report be forwarded to the City Telecommunications
Steering Committee for information.
The foregoing is forwarded to City of Toronto Council through the Budget Advisory Committee for consideration and
approval of the Commission's request for increased project approval of $2,334,000 for City Project #231, as well as, the
City Telecommunications Steering Committee for information.
Sincerely,
Vincent Rodo
General Secretary
1-16 - Attachment
Copy: Administrator, City of Toronto Telecommunications Steering Committee
TORONTO TRANSIT COMMISSION
REPORT NO.
MEETING DATE: November 17, 1999
SUBJECT: PROJECT APPROVAL - FIBRE OPTICS AND SUBWAY RADIO COMMUNICATION PROJECT
RECOMMENDATION
It is recommended that the Commission approve:
(i) forwarding this report to the City of Toronto Council, requesting increased project approval of $2,334,000 (gross and
net) for City Project #231 as the expenditure for this will be required in advance of receiving approval from the City for the
2000-2004 Capital Program; and
(ii) the holding of funds in TTC accounts until additional funds are approved.
FUNDING
Sufficient funds have been included in the 2000-2004 Capital Program under Project No. 2.3 - Communications, Fibre
Optics and Subway Radio Communications, (as set out on pages 195 to 203 of the State of Good Repair Category) as
approved by the Commission on November 3, 1999.
BACKGROUND
The Fibre Optics and Subway Radio Communication Project consists of two major contracts:
(i) Alcatel Canada Inc., for the design, supply and installation of a radio antenna system that will enable communication
between Transit Control and subway trains, and will also allow Emergency Response Agencies and TTC staff to
communicate from street level, into the subway system; and
(ii) Midland International Corporation (Trak Com Wireless Inc.), for the design and supply of subway car radios, wayside
radio and Transit Control equipment. This contract was originally awarded to Midland, but in late 1998, Midland's parent
company experienced financial difficulties and began to liquidate assets. As a result, staff agreed to allow Midland to
transfer responsibility for completion of the work to Trak Com, who had retained Midland's technical experts, with
Midland continuing to provide the financial security.
At its meeting of April 8, 1998, the Commission received a status report on the Fibre Optics and Subway Radio
Communication Project for information. The report contained the following budget and schedule information.
Schedule
Based on the recovery schedules supplied by the two Contractors, the following revised milestone dates were provided for
the project:
· Antenna System In-service (B-D) - November 30, 1998
· Base (fixed) Radio System Operational (B-D) - December 24, 1998
· All B-D Trains Equipped with Radios - April 15, 1999
· Antenna and Base Radio System Operational (Y-U-S) - April 12, 1999
· All Y-U-S Trains Equipped with Radios - September 30, 1999
Budget
The approved 1998-2002 budget for the project was $38,699,000. During the 1999-2003 budget process, the estimated cost
was revised to $40,314,000, for a total increase of $1,615,000. This increase was based on the above-noted schedule dates.
It was noted that there was still uncertainty as to the final cost of the two contracts, based on outstanding contract changes
and claims.
DISCUSSION
Since the last report to the Commission and in spite of staff's best efforts, the project has experienced continued delays.
The primary reason for these delays is a result of the technical complexity of both contracts, which has resulted in delays in
the development, installation and debugging of both systems. In addition, and as noted above, the work on the Subway Car
Radio Contract was transferred to Trak Com in November 1998. Prior to this change, Midland had not been performing
satisfactorily which, combined with the change, resulted in considerable delays. It is noted that since this change, the
performance on this contract has improved dramatically.
Impact of Delays
As a result of the noted delays, additional TTC engineering and contract support resources have been required to support
the longer installation time and to perform additional testing of these systems.
Special provisions have also been necessary to accommodate the newly acquired T-1 subway cars, which began arriving in
1996. The T-1's were originally purchased on the basis that the new subway radio system would be operational. This not
being the case, existing radios had to be removed from the subway cars being retired by the T-1's, to enable the T-1's to
enter service. As the T-1's were not designed for the existing radios, modifications were required to accommodate these
radios. This required a considerable effort by TTC staff, which resulted in additional costs. To date, 208 T-1's have been
retrofitted.
Increased Costs
In light of the additional work noted above, and also to address some unforeseen technical issues, additional funds in the
amount of $2,334,000 are required to complete the project, bringing the total cost of the project to $42,648,000. It is noted
that there are pending claim issues, for which a limited allowance has been made in this increase.
Current Status
The current status of the project is very promising. The antenna system has been operational for testing purposes since May
and during the week of September 13, all trains on the Bloor/Danforth subway line were equipped with new radios. While
there have been a few problems, the performance of the system has been satisfactory and both engineering and user staff
are pleased with the operation.
Testing of the Yonge/University subway line is currently underway and based on successful results, installation of new
radios should begin in late November. On this basis, the entire fleet should be operational on the new system by early
December.
Testing of the system with the City of Toronto Emergency Response Agencies (ERA) has also recently begun and the
ERA's who have tested the system to this point have been pleased with the results. In addition, the ERA's that participated
in the October 3, 1999, Emergency Simulation (Fire, Police and Ambulance) reported good results.
JUSTIFICATION
Additional funds are required in order to complete the Fibre Optics and Subway Radio Communication Project.
- - - - - - - - - - - -
October 21, 1999
6-138-220