|
Memorandum |
Urban Planning & Development Services |
Building Division
City of Toronto
Scarborough Civic Centre
150 Borough Drive
Toronto, Ontario M1P 4N7
|
Tel:(416) 396-7075
Fax:(416) 396-4266 |
Date:December 23, 1998
To:Scarborough Community Council
From:Steve Franklin, P. Eng.
Director and Deputy Chief Building Official
Subject:Derelict Building
North-east Corner of Brimley Road and Sheppard Avenue East
4430-4438 Sheppard Avenue East and 2095 Brimley Road
Ward 18 - Scarborough Malvern
Purpose:
To report on the condition of the derelict building at the above noted location, as directed by
Scarborough Community Council.
Recommendation:
That Scarborough Community Council receive this report for their information.
Background:
On February 22, 1995, Pacific Empire Developments Inc. (the original owners) filed an
application for building permit to construct a four storey reinforced concrete building, with
two levels of underground parking containing retail, office and restaurant uses, and having a
gross floor area of 11,445 square metres.
A foundation permit was issued on June 1, 1995 to allow construction to begin. On August 8,
1995, a superstructure permit was issued. Inspections were conducted on the project by all
City disciplines, along with professional design consultants until construction ceased at the
end of January, 1996 in the stage as it remains to date; namely, 3 storeys of exposed
reinforced concrete floor slabs and columns and partial erection of structural steel columns,
beam and joists that would form the roof. In addition, some plumbing and mechanical work
was completed in the underground parking levels.
The site is surrounded by a combination of 8 foot high fencing and hoarding. Sometime after
this, the project went into receivership and was assumed by the mortgagor, Bank of China.
During the winters of 1996 and 1997, the Building Division ordered Bank of China to provide
frost protection of the buildings foundations, as well as site safety measures which were
completed within our required time frame. To date, they are maintaining the requested frost
protection through installation of six electrical heat furnaces located in the lower parking level
as designed by a professional engineer.
In early 1997, Bank of China, at our request, retained a professional engineer design
consultant to assess the structural stability and condition of the partially-built structure. A
report was submitted to the Building Division with recommendations for repairs and/or
remedial action. At the end of March, 1997, Bank of China complied with all the
recommendations as outlined in that report.
In the summer of 1997, Bank of China was asked to assess the condition and security of the
hoarding/fencing erected around the site and make the necessary replacement and repairs as
required. Following this assessment, Bank of China hired a contractor to do the corrective
work. From the time the work on the project ceased, our Division has periodically inspected
the site in co-operation with Bank of China officials to ensure that safety measures were
maintained.
On September 16, 1997, the previous Scarborough Council approved an application to amend
the official plan and zoning by-law to add hotel uses. This was initiated by an interested
purchaser of the site. Unfortunately, in September 1998 we learned from Bank of China that
the purchase transaction was not finalized as indicated in the attached letter of September 22,
1998. However, Bank of China is currently negotiating with a potential purchaser as further
explained in the attached letter of December 16, 1998.
Conclusion:
The last consultant engineering assessment and report done in 1997 revealed that the building
as it stands was structurally sound. In addition, our recent inspection on December 17, 1998,
found the building has no serious structural items of concern, the two lower underground
parking levels free of standing water, the six electrical heating furnaces located in the lower
parking level that provide heat to protect the foundation from freezing operational, and the site
hoarding/fencing secure and tight.
Attached for your information is a letter that outlines what any new owner would have to
undergo to activate the existing permit and proceed with construction.
Any new building design would require new applications to be filed for building permit and
Site Plan Control.
Contact name:
Joe Debono, Manager
Inspections East District
Team 2
Tel: (416) 396-7316
Fax:(416) 396-4266
E-mail:debono@city.scarborough.on.ca
Respectfully submitted,
Steve Franklin, P. Eng.
Director and Deputy Chief Building Official
Building Division
Urban Planning and Development Services
/yk