March 15, 1999
To:Urban Environment and Development Committee
From:Commissioner, Works and Emergency Services
Subject:Contract T-33-98
York Mills Road Bridge over Don River
East of Don Mills Road, Structure Rehabilitation
Contract T-01-97
Humber Bridges - Bridges 2 and 3
Purpose:
To obtain Council authority to increase the contract price of Contract No. T-33-98 for the necessary additional structural
rehabilitation work on the York Mills Road Bridge over Don River, and also for Contract T-01-97 for the necessary
additional work on the new Gardiner Expressway bridges over the Humber River.
Funding Source:
Funding for T-33-98 has previously been approved by Council and is available in Works and Emergency Services Capital
Account C-TR055, Bridge Reconstruction Programme. Funding for Contract T-01-97 has been previously approved by
Council and is available in Capital Account C-TR028 Replacement of Gardiner Humber Bridges. The Treasurer has
previously certified that financing can be provided under the updated Debt and Financial Obligation limit and that it falls
within corporate debt guidelines.
Recommendations:
It is recommended that:
1. the contract price for Contract No. T-33-98, Structure Rehabilitation on York Mills Road Bridge over Don River, be
increased by $59,543.87 to a total of $952,885.25 (GST inclusive) to cover the costs incurred for work done under this
Contract including additional repair work.
2.The contract price for Contract T-01-97 be increased by $1,788,558.50 to a total of $37,559,728.50 (GST inclusive) to
accommodate additional expenditures.
Background:
At its meeting on May 20, 1998, the Bid Committee approved (Bid Committee Meeting No. 5, Clause 28) the award of
Contract No. T-33-98 to Bridgecon Construction Ltd. and Bridgecon Holdings Ltd. at a contract price of $893,341.38 (GST
inclusive). In accordance with Metro Council Procedure By-law No. 129-94, the Planning and Transportation Committee at
its September 3, 1997 meeting authorized the award of Contract T-01-97 to Peter Kiewit Sons Co. Ltd. in the amount of
$35,771,170.00 including GST. Expenditures under these Contracts exceed their limits due to the additional work done.
On Contract T-33-98, the structure was in worse condition than originally anticipated and therefore the repair quantities
increased. Also, additional work had to be done to rectify unforeseen site conditions. For example, additional steel repairs
were required to the supporting deck girders. These girder repairs could only be identified and repaired cost effectively
during the contract while the ballast wall and expansion joint were removed as part of the Contract.
Since the start of Contract T-01-97 in September of 1997, conditions were identified requiring the performance of extra
work and additional expenditures by the Contractor, Peter Kiewit Sons Co. Ltd. For example, as approved by Council, to
accelerate the construction schedule, a bonus of $10,000.00 per day was offered for each day that the Contractor bettered
their schedule. Completion was 25 days early and therefore an additional expenditure of $250,000.00 was incurred. In
addition, design changes were initiated by the project team to improve the final product, and these changes had to be done
by Peter Kiewit Sons Co. Ltd. for continuity, warranty, liability and safety reasons. Also, unforseen site and foundation
conditions arose that required the Contractor to perform extra work to fulfill the intent of the work programme as originally
contained in the contract. Contract finalization has not occurred yet as discussions with the Contractor are still ongoing in
an attempt to resolve the value of some outstanding extra work items. As such we are recommending that an allowance of
5% of the original contract value, or $1,788,558.50, over and above the original contract value be set for all extra
expenditures under this Contract.
At the time that these Contracts were prepared, the Commissioner of the Department had the authority to approve
additional expenditures on a commitment up to an amount equal to ten per cent of the contract price in accordance with the
former Metro Financial By-law No.146-90, as amended. As such, under the former Metro By-law, a further ten percent of
the awarded contract amount or approximately $89,300.00 for Contract T -33-99, and $3,577,117.00 for T-01-97 existed
for extra work provided sufficient funds in the Accounts existed to cover the shortfall.
At its meeting on January 6, 1998, City Council enacted By-law No. 7-1998, Interim Financial Control By-law, which
repealed the former By-law No. 146-90. As the new By-law contains no provision to exceed the awarded contract amount,
the Department has effectively lost its ability to authorize the unforeseen and necessary additional work that may arise
during construction of capital projects. This is even more problematic for rehabilitation projects and foundation work.
Typically, in this type of work the existing conditions are difficult to determine and as a result the quantity of repairs may
increase significantly or the scope of the foundation work may change from what was originally allowed for in the
Contract.
Condition surveys on all structures are performed in accordance with the Structure Rehabilitation Manual issued by the
Ontario Ministry of Transportation and these are used to establish the scope of work to be covered in the contract. Surveys
include, core extractions from the deck for testing and exposure of different areas of deck for examination. However,
during construction, it is not unusual to discover that the deterioration is more extensive than originally indicated. For
foundation work even though borings will be taken during the pre-engineering phase to assist in the foundation design, the
soil and rock conditions during construction may vary. Also, only a limited number of borings are taken and therefore the
results are not totally representative of the actual conditions. During construction of the foundations, the design
assumptions have to be checked and the site conditions verified continuously, and the foundation design enhanced or
modified as required.
Conclusion:
The contract price for Contract No. T-33-98 be increased by $59,543.87 to a total of $952,885.25 (GST inclusive) to cover
the extra costs for additional work done, and Contract No. T-01-97 be increased by $1,788,558.50 to a total of
$37,559,728.50 (GST inclusive) for additional work.
Contact Name and Telephone Number:
M. Chung, P. Eng.
Manager of Structures
Metro Hall Office
Telephone: 392-8341
T. G. Denes, P. Eng.
Executive Director
Technical Services
Barry Gutteridge
Commissioner
Works and Emergency Services
DJM/jg