September 20, 1999
TO:Works Committee
FROM:Commissioner, Works & Emergency Services
SUBJECT:Engineering Services to Complete the Replacement of Sludge Dewatering
Centrifuges Contract at the Highland Creek Treatment Plant
Purpose:
To authorize additional engineering fees for general administration and site supervision services related to Contract
WPC-8-97, "Replacement of Centrifuges for the Sludge Treatment Building at the Highland Creek Treatment Plant".
Funding Sources:
Funding is available in the approved 1999-2003 Water and Wastewater Services Division Capital Works Program, Water
Pollution Control, Highland Creek Treatment Plant, Equipment Replacement Account C-WP050.
Recommendations:
It is recommended that authority be granted to extend the previously engaged services of the engineering firm of Proctor &
Redfern Limited for general administration and site services during construction of the Replacement of Sludge Dewatering
Centrifuges project at the Highland Creek Treatment Plant, for a fee not exceeding $72,000.00, including all applicable
taxes and disbursements, based on the previously authorized contingency unit rate of $4,500.00 per week.
Background:
Metropolitan Council on August 10, 1994, by adoption of Works Committee Report No. 14, Clause 16, authorized the
engagement of the firm of Proctor & Redfern Limited (P&R) to provide engineering design services in connection with this
project, composed of two contracts, one for the supply, delivery, supervision of installation and commissioning of two
centrifuges (WPC-1-96) and the other for the installation of centrifuges, including provision for sludge feed and polymer
systems and commissioning of the replaced sludge dewatering system, (WPC-8-97).
With the report for the award of the equipment supply contract in the amount of $1,693,000.00, Metropolitan Council on
August 14, 1996, by adoption of the Environment and Public Space Committee Report No. 13, Clause No. 10, authorized
the extension of P&R's services to include contract administration services for the supply contract in the amount of
$9,700.00 including taxes.
As the procurement of the centrifuge equipment was secured, the installation contract was awarded on September 24, 1997,
by Metropolitan Council in the amount of $1,645,000.00 by adoption of Environment and Public Space Committee Clause
No. 14, Report No.12. The Report also authorized the extension of P&R's services to include general administration and
site services during construction of the Centrifuges Installation Contract in the amount of $320,000.00, including taxes,
based on an anticipated tendered construction period of 52 weeks, with the provision for further extension at a contingency
rate of $4,500.00 per week for continuation of services beyond the 52 weeks, if necessary and as authorized by the
Commissioner of Works, all under the terms of the existing engineering services agreement.
The new sludge dewatering centrifuge system has been operating since February 9, 1999, with only a partial automated
control system due to unexpected problems encountered during the integration with the existing control system.
Investigation of the control system and upgrading of some of the existing computer hardware by companies having
expertise in communications and software systems, was necessary to allow resumption of contractual site activities and
completion of the new control system integration with the existing.
Contractual completion is now expected by the end of September 1999, with no delay claims, as this Department, with the
assistance of our consultants, reached an agreement with the contractor involved, allowing a control system audit and
upgrade by a third party to proceed with the contractor's commitment of no delay claim submissions. Therefore, the
completion date of contract WPC-8-97, originally tendered as November 16, 1998, will now be extended to the end of
September 1999, or an extension of 46 weeks, due to unexpected site conditions.
During the extended construction period, the City's consultant, Proctor & Redfern Limited, have been involved only on as
needed basis with the project and are requesting additional fees in the amount of $72,000.00, including taxes and
disbursements, equating to a time period of 16 weeks at the unit rate of $4,500.00 per week, previously authorized for such
extensions of services. The additional fees will bring the total of contract administration and site supervision engineering
services to an amount of $401,700.00, including taxes and disbursements, on a total awarded contract amount of
$3,338,000.00, including both the equipment supply and installation contracts.
Conclusions:
In view of the unexpected site conditions encountered in the integrating the new control system with the existing system,
requiring a third party investigation and a limited upgrade of the existing system, Contract WPC-8-97 was unavoidably
prolonged by 46 weeks, extending the requirements of contract administration and site supervision on an as needed basis
by 16 weeks.
Accordingly, the engineering fees for Proctor & Redfern Limited should be increased by $72,000.00, including applicable
taxes and disbursements.
Contact Name and Telephone Number:
Adrian Piccolo, P.Eng.
Senior Project Engineer
Plant & Facility Construction
416-392-8853
T.G. Denes, P.Eng.B.H. Gutteridge
Executive DirectorCommissioner of Works & Emergency Services
Technical Services Division
AFP/ph
Attachment
File 1020.50-1-2