STAFF REPORT
October 20, 1999
To: Works Committee
From: Barry H. Gutteridge, Commissioner, Works and Emergency Services
Subject: Prince Edward Viaduct - Don Section
Structure Modification, Contract No. T-71-99, Tender Call No. 222-1999
(Midtown - Don River)
Purpose:
The purpose of this report is to advise of the results of the Tender issued for the installation of a suicide prevention barrier
on the Prince Edward (Bloor Street) Viaduct, in accordance with specifications as required by the Works and Emergency
Services Department.
Financial Implications and Impact Statement:
Council has previously approved an expenditure of $2.5 million. Acceptance of the low bid would require an additional
expenditure in excess of $3.0 million, but no funds are allocated for the additional expenditure. Other options presented in
this report would be within the original approved amount of $2.5 million. The Chief Financial Officer and Treasurer has
reviewed this report and concurs with the financial impact statement.
Recommendations:
It is recommended that:
(1) Contract No. T-71-99, Tender Call No. 222-1999 for the installation of a safety fence on the Prince Edward Viaduct be
cancelled;
(2) the Commissioner of Works and Emergency Services be authorized to issue a new Request for Proposals with a
maximum budget of $2.5 million, to solicit new design concepts and full engineering services for this project, based on a
design/build concept, with the submission being evaluated by a similar Project Steering Committee comprised of
representatives from:
(a) the Schizophrenia Society of Ontario
(b) the Council on Suicide Preventions
(c) the Toronto Historical Board/Heritage Toronto
(d) Architecture and Civic Improvements, City Planning
(e) the Public Art Policy Advisory Committee; and
(f) the Technical Services Division, Works and Emergency Services Department;
(7) the appropriate City of Toronto officials be directed to take the necessary action to give effect thereto.
Council Reference:
The Bid Committee at its meeting held on October 6, 1999, opened the following tenders for Contract No. T-71-99, for the
structure modification and the installation of a safety fence on the Prince Edward Viaduct - Don Section:
Price Complete
Including all
Tenderer: Charges and Taxes
Bridgecon Construction Ltd. $5,558,405.92
Grascan Construction Ltd. $7,029,900.00
G. Tari Limited $8,325,873.84
The Tender submitted by G. Tari Limited contained minor errors in the extension of the unit prices. The revised figure is
shown above.
Background:
On July 8, 9 and 10, 1998, Council adopted Report No. 8 of the Urban Environment and Development Committee
(UEDC), Clause No. 2, and authorized the Works and Emergency Services Department (WES) to solicit proposals for
design concepts and full architectural services for the installation of safety barriers on the Viaduct with a budget set at $1.5
million. The amount of $1.5 million was included in the terms of reference informing competitors of the parameters of the
project.
On October 1 and 2, 1998, Council adopted Report No. 11 of UEDC, Clause No. 1, recommending the preferred design by
Dereck Revington Studios/Yolles Partnership be adopted and that they be retained to prepare the detailed design and tender
documents and to provide project management and site supervision services.
Subsequent to Council's endorsement of the design, it was apparent that the design as selected, could not be constructed
within the original budgeted amount of $1.5 million.
On May 11, 12 and 13, 1999, Council adopted the recommendation of the UEDC (Report No. 7, Clause No. 2) which
directed the WES to proceed with the design by Dereck Revington Studios/Yolles Partnership, to prepare the detailed
design and tender documents for the construction and to increase the funding for the project by $1.0 million to $2.5
million.
Comments:
On October 6, 1999, the Bid Committee opened the tenders, as stated previously in this report. The low bid price was
$5,558,405.92, more than three times the original budget of $1.5 million and more than double the revised budget of $2.5
million.
Dereck Revington Studios/Yolles Partnership and their cost consultant, Vermeulens, are of the opinion as stated in the
attached letter (Attachment No.1), that the tenders are too high for the value of the work indicated and reflect the high
levels of risk associated with the project and current market conditions, rather than the underlying cost and scope of work.
In the attached letter, the consultant outlined a proposed course of action. City staff are not in agreement with the proposal
mainly because it does not provide the assurances that the project would be completed within the available budget. Should
Council decide to proceed with the option of a "test panel", any procurement must be in accordance with the Purchasing
Department's procedures.
At present, an amount of $1.5 million is included in the approved WES 1999 Capital Works Programme under Capital
Account TR029, Don Valley Parkway Rehabilitation. The source of the additional funding is yet to be identified.
There are five possible alternatives for this project:
(1) proceed with the construction of the suicide prevention barrier in the amount of $5,558,405.92;
(2) retain the design by Dereck Revington Studios/Yolles Partnership and retender the construction utilizing a modified
procurement process, including the erection of a "test" section to refine cost projections, prior to proceeding with the
balance of construction. Expenditures in excess of $2.5 million would still require further allocation of funds.
(3) as an interim measure, install a chain link fence at a cost of approximately $800,000.00,until such time as the final
barrier is installed;
(4) terminate work on the design by Dereck Revington Studios/Yolles Partnership and initiate a new design competition,
based on the design/build concept; or
(5) terminate work on the design by Dereck Revington Studios/Yolles Partnership and construct a basic barrier at a cost of
approximately $2.0 million.
Option 3 could be implemented by late winter/early spring of 2000. The timelines for Options 1, 2, 4 and 5 are all of a
similar duration and would result in scheduled completion in late summer/early fall of 2000.
This matter was discussed with the Project Steering Committee at a meeting on October 19, 1999. The Committee is
strongly in favour of Option 2 and has reached a consensus as follows:
(1) we do not recommend a second design competition;
(2) we accept the analysis of the tenders provided by Vermeulens Cost Consultants, that market conditions,
overhead/access costs and perceived risk have inflated the bids;
(3) we recommend immediate installation of a temporary barrier and 4 payphones with appropriate Distress Centre
signage;
(4) we recommend staff and Revington/Yolles negotiate with the lowest bidder to reduce the bid;
(5) we recommend a sample bay (approximately 6.4 metres) of the winning Revington/Yolles barrier be constructed to
determine more accurately the cost and reduce the perceived risk;
(6) the Project Steering Committee supports a "design build" process to reduce costs and perceived risk of the winning
design; and
(7) we recommend the City seek private sector sponsorships to offset increased costs of construction and complete the
Revington/Yolles barrier.
Should the recommendation to proceed with a new Request for Proposal (RFP) be adopted, WES will proceed immediately
to reorganize the Project Steering Committee to fast-track the process. Such process will follow closely in line with the
previous RFP procedure with a strong emphasis on the budget amount of $2.5 million. In order to ensure the budget is not
exceeded, the work would be tendered as a design/build assignment.
As directed by Council in the May 11, 1998 UEDC, Report No. 7, Clause No. 2, WES staff have had several discussions
with Bell Canada and Toronto Hydro regarding the installation of 4 payphones on the approaches of the bridge. Cost
estimates from Bell and Toronto Hydro to install the two telephone lines and power supply at the southeast and southwest
corners of the bridge are in the order of $15,000.00. A work order for this work has already been issued and we expect
completion of the work within 4-6 weeks. Installation of the telephone lines at the northeast and northwest corners of the
bridge is more problematic and they are currently assessing the feasibility and cost to install these lines. As the cost of the
installation of these two telephones is expected to be substantially higher, we will report to the Works Committee again
once the investigation is completed.
On September 8, 1999, a meeting of the telephone sub-committee was held on the site to discuss and finalize the locations
and proposed signage to complement the telephones. The signage shall include the telephone numbers of the Distress
Centre.
Conclusions:
This report requests authority to cancel Contract No. T-71-99, Tender Call No. 222-1999, for the installation of a safety
fence on the Prince Edward Viaduct and also to issue a new RFP for a new design concept for the project.
Contact:
W. (Bill) G. Crowther, P.Eng.
Director, Works Facilities and Structures
Technical Services Division
Tel. (416)392-8256
Fax (416)392-4594
E-mail: william_g._crowther@metrodesk.metrotor.on.ca
Tom G. Denes, P.Eng.
Executive Director, Technical Services
Barry H. Gutteridge
Commissioner, Works and Emergency Services
WC/fh
List of Attachments:
No. 1 Vermeulens letter dated October 20, 1999