TORONTO TRANSIT COMMISSION
TO: Committee of the Whole
FROM: Richard C. Ducharme
MEETING DATE October 20, 1999
SUBJECT: Bessarion Station -
Reinstatement of Centre Left Turn Lane on Sheppard Avenue
(Bessarion Road)
RECOMMENDATION
It is recommended that the Committee of the Whole:
1. confirm the elimination of the left turn lane and due to the significant cost implications to the project not reinstate the
lane,
2. endorse the addition of street lighting, a flashing light highlighting the 40 kph speed limit, use of paid duty police
officers (during busy retail periods) and proper lane markings through the construction zone as the preferred solution to
address the perceived access and safety concerns, and
3. forward this report to the Works Committee for consideration at its meeting of November 3, 1999 in conjunction with
the motion made by Councillor Shiner at the September 8, 1999 Works Committee meeting to reinstate the centre left turn
lane on Sheppard Avenue.
INTRODUCTION
At the September 22, 1999 meeting of the Committee of the Whole, Sheppard Subway project staff outlined the cost, legal
and schedule implications that would result if the centre left turn lane at Bessarion Station was not removed on schedule.
The Committee of the Whole endorsed the removal of the left turn lane and the contractor completed the removal on
September 23, 1999.
The Committee of the Whole requested that staff "meet with the contractor to discuss options for the possible reinstatement
of the centre left turn lane and that a report be brought back as soon as possible on the results of these deliberations". This
report responds to that request.
DISCUSSION
TTC and City staff have met to discuss the lane configuration that would be necessary to reinstate storage for two vehicles
to turn left into Sheppard Square Plaza/Weall and Cullen (see Exhibit 1). A preliminary design for this lane configuration
(which reduces the impact on utilities and dewatering facilities to the extent possible) was communicated to the contractor
on September 24, 1999. The contractor's estimated cost to reinstate the centre left turn lane (submitted in writing) is as
follows:
Option 1 With extension of Milestone #3 from April 11 to May 19, 2000 the contractor's cost is $200,000, plus utility
costs of $35,000, plus $10,000 for other exclusions for a total cost of $245,000 (excluding GST).
Option 2 If Milestone #3 cannot extended from April 11, 2000 to May 19, 2000 the contractor's price is $500,000, plus
utility costs of $35,000, plus $10,000 for other exclusions for a total cost of $545,000 (excluding GST).
The reference to Milestone #3 is of significant concern as this milestone relates to the completion of the trainway to allow
the installation of rail and other systems equipment. An extension of Milestone #3 by five weeks is not acceptable due to
the impact of this extension on trackwork and other systems installation contracts that are on the critical path schedule. A
delay in completion of trackwork (i.e. Option 1) would result in an extension of the revenue service date for the project
with the associated significant impact on project costs. Consequently, the cost to reinstate the centre left turn lane must be
based on Option 2 (no schedule extension) at an estimated cost of $545,000.
Accordingly, staff recommend that the centre left turn lane not be reinstated for the following reasons and that the four lane
construction detour be retained for the balance of the contract (see Exhibit 2):
· The high cost of Option 2 ($545,000) cannot be justified and is not affordable without increasing the project budget.
· The current four lane configuration (no left turn lane) is functioning well.
· The current four lane design meets or exceeds all City of Toronto design standards for construction detours.
· With enforcement of the 40 kph speed limit and use of paid duty police officers, left turn access into the Sheppard Square
Plaza/Weall and Cullen during seasonal business peaks will be satisfactory.
· During the spring of 2000, a centre left turn lane with storage for two vehicles will not be sufficient and left turning traffic
will be backed up into the eastbound through lane. If this occurs, the benefit of the reinstatement of the centre left turn lane
will be negated making the cost to implement the reinstatement even more questionable.
Given the above, staff believe that the solution to the perceived safety problem of a four lane road through the Bessarion
Station construction zone rests on enforcement of the reduced speed limit, pay duty police as required, the implementation
of flashing 40 kph speed limit light and review and implementation of improved street lighting, if necessary, to improve
night time visibility of the construction detour. If necessary, these initiatives could be implemented for $15,000 - $20,000.
A meeting to discuss the contents of this report has been arranged with Councillors Shiner and King for October 14, 1999.
Staff will update the Commission on the results of this meeting at the October 20, 1999 Committee of the Whole meeting
which the Councillors will be invited to attend.
Chief General Manager
50-20-11
654331
Attachment: Exhibit 1 - Reinstatement of Centre Left Turn Lane
Exhibit 2 - Road Detour for Balance of Construction of Bessarion Station