November 18, 1999
To: Works Committee
From: Barry H. Gutteridge, Commissioner of Works and Emergency Services
Subject: Additional Expenditures for Extra Work on Capital Projects Currently in Progress
Purpose:
To obtain Council authorization to negotiate and authorize additional expenditures for the performance of necessary
additional work on contracts within the Water and Wastewater Services Division as outlined in this report.
Financial Implications and Impact Statement:
Funds are available in the approved 1999-2003 Water and Wastewater Services Division Capital Accounts for each
contract outlined in this report.
Recommendations:
It is recommended that:
(1) additional expenditures in the amount of $847,082.15 including Goods and Services Tax, be authorized for the
performance of necessary additional work on Water and Wastewater contracts, as described herein and in accordance with
the amounts listed in Appendix B attached; and
(2) the appropriate City Officials be authorized and directed to take the necessary action to give effect thereto.
Background:
At its meeting of January 6, 1998, City of Toronto Council enacted By-law No. 7-1998, Interim Financial Control By-law,
which repealed former Metro By-law No. 146-90. As the new By-law contains no provision to exceed the awarded contract
value, as confirmed by the City's Legal Division, the Department has effectively lost its ability to authorize the unforeseen
and necessary additional work that may arise during construction of capital projects. This is particularly problematic in
instances where the capital construction is tendered on a firm, lump sum basis. For contracts recently tendered, since
confirmation of the repeal of former Metro By-law No. 146-90, we have been providing, on an interim basis, a general
contingency allowance for possible extra work into the Schedule of Prices for Alterations, Extras, and Deductions for
incorporation into the total lump sum tender price. However, in the case of contracts identified herein, Contract WPC-5-97,
Construction of Digester Gas Control Building and Contract WPC-6-97, Construction of the Anaerobic Digestion Tanks
Nos. 19-22 at the Ashbridges Bay Treatment Plant, no such general contingency was added, as we believed it was still
available through former Metro By-law No. 146-90.
At the time of award, in accordance with former Metro By-law No. 146-90, as amended, a Department Head had authority
to approve additional expenditures on a commitment in accordance with the By-law up to an amount equal to ten percent
of the commitment. As such, under the former Metro By-law a further ten percent of the awarded contract amount for each
of the contracts identified herein would have been available for required extra work on each contract.
Comments:
Shown in Appendix A are the above-noted contracts, which require the performance and/or payment of approved extra
work.
Appendix B identifies the extra work necessary to be performed for both of the contracts described in Appendix A along
with their corresponding costs.
At its meetings of October 28, 1998 and December 16, 1998, City of Toronto Council adopted Clause No. 4 of Report No.
7, and Clause No. 3 of Report No. 11, of the Works and Utilities Committee authorizing additional expenditures in the
amounts of $1,078,836.93 and $1,393,444.44 including Goods and Services Tax for the performance of necessary
additional work on ContractsWPC-5-97 and WPC-6-97 respectively.
Since the above mentioned request to City Council for authorization of additional expenditures for Contracts WPC-5-97
and WPC-6-97, more recent issues have been identified as requiring the performance of extra work. In some cases,
additional information and unexpected circumstances have arisen during construction, which have necessitated changes to
the original tendered scope of work. To ensure continuity with respect to liability and warranty issues under the contract,
these changes must be implemented by the issuance of extra work orders.
Some of the extra work is required to be performed to conform to recently changed regulatory code requirements or
operating procedures, and should be implemented to ensure construction of the best possible finished product. In other
cases, the advancement of technology in the period between the completion of design (1995) and current construction
phase dictated replacement/upgrade of the specified equipment or an addition to the equipment at extra cost. Examples of
this are as follows: (a) level sensing pipes in existing Digester Tanks Nos. 1 & 3 to provide accurate monitoring of sludge
levels; (b) provision of Programmable Logic Controllers control panels instead of microprocessors to provide better control
and monitoring of the operation of the dryers; and (c) thickened waste activated sludge flowmetering to existing Digester
Tanks Nos. 13 to 16 and new Digester Tanks Nos. 19 to 22 to provide total control of the sludge distribution to Digester
Tanks.
Furthermore, the installation of latest technology gas monitoring devices is required to be performed during the current
contract work due to the unreliability of aged and inaccurate existing gas sensors. Also, due to safety concerns, expressed
by plant personnel, control panels were removed from explosion to non-explosion proof area to eliminate reliance on the
performance, by plant personnel, of mandatory safety protocols (which over time may inadvertently be forgotten to be
performed) for each and every time routine maintenance or repair work is carried out.
Under this request for extra work expenditures we are also seeking funds required to cover the cost of the heating,
ventilation and air conditioning needed to complete the new control room building for the existing Anaerobic Digester
Tanks 5 to 12. The previous request covered the cost only of the construction of the previously designed control room
building. The heating and cooling components of the work were left to be completed at a later date.
The total value of the estimated extra work required to-date, as a percentage of the overall cost of contracts WPC-5-97 and
WPC-6-97 is equivalent to 5.8 and 6.3 percent respectively.
Conclusions:
The additional expenditures for extra work in the amount of $847,082.15, including GST are summarized in Appendix B
attached. This additional work is necessary to either meet regulatory code requirements and/or ensure construction of the
best possible product.
Contact:
P. Jancic, P.Eng.
Senior Project Engineer
Engineering Services - Works Facilities & Structures
Technical Services Division
Tel: (416) 392-8251
Fax: (416) 392-4514
E-mail: peter_jancic@metrodesk.metrotor.on.ca
Tom G. Denes, P.Eng. Barry H. Gutteridge
Executive Director Commissioner
Technical Services Division Works and Emergency Services
Attachments:
Appendices A & B