March 4, 1999
TO:Works and Utilities Committee
FROM:Commissioner, Works & Emergency Services
SUBJECT:CONSULTING SERVICES - GENERAL ADMINISTRATION AND SITE
SUPERVISION FOR WESTERN BEACHES STORAGE TUNNEL PHASE II
Purpose:
To obtain Council authorization to amend the engineering consultant agreement with CH2M
Gore & Storrie Limited and MacViro Consultants Inc. to include detailed design services and
general administration and site supervision during construction of Phase II of the Western
Beaches Storage Tunnel.
Funding Services, Financial Implications and Impact Statement
Funds are available in the approved 1999-2003 Water and Wastewater Services Division,
Water Pollution Control Capital Account C-WP951, New District Sewers.
Recommendations:
It is recommended that:
authority be granted to amend the existing engineering services Agreement with the joint
consulting firms of CH2M Gore & Storrie Limited and MacViro Consultants Inc. for review
of detailed design calculations and drawings proposed by the design/build contractor, and
general administration and site services during construction for Phase II of the Western
Beaches Storage Tunnel, by an additional amount of $650,000.00 including the Goods and
Services Tax and including a contingency allowance of $120,000.00, to cover extended
services during construction for Phase I and Phase II, if necessary and as authorized by the
Commissioner of Works and Emergency Services, all in accordance with the terms of the
existing engineering agreement; and
the appropriate City officials be authorized to take the necessary action to give effect thereto.
Background
Council of the former City of Toronto, at its meeting of July 5, 1996, in considering
Communication No. 59 from the Board of Management, approved the engagement of CH2M
Gore & Storrie Limited and MacViro Consultants Inc. (CG&S/MacViro) to provide
engineering consulting services for the preliminary design, preparation of the design/build
proposal call and assistance in the pre-qualifications and tender process for the Western
Beaches Storage Tunnel (WBST) project in the amount of $727,229.20 including Goods and
Services Tax (GST).
Subsequently, the Board of Management of the former City of Toronto, at its meeting of
December 11, 1997 (Minute No. 2.6) approved amending the terms of reference of the
engineering assignment with CG&S/MacViro to increase the consulting fees by $84,630.00 to
$811,759.20 including GST, to allow for the preparation and evaluation of revised predesign
and design/build Request for Proposals.
By adoption of Clause No. 2 of Report No. 4 of the Works and Utilities Committee, City
Council, at its meeting of May 13, 14 and 15, 1998 approved amendment of the engineering
consulting agreement with CG&S/MacViro to include detailed design review and general
administration and site services during construction for Phase I of the WBST project, by an
amount of $970,000.00 thereby resulting in a total agreement amount of $1,781,759.20
including GST.
Comments and Justification:
Council of the former City of Toronto by adoption of Clause No. 6 of Report No. 1 of the
Community and Neighbourhoods Services Committee on February 4, 5 and 6, 1998, awarded
Phase I of the WBST to McNally-Frontier Joint Venture Inc. at a total contract price of
$31,500,000.00 including GST. See attached Appendix 'A' for summary of project costs.
City of Toronto Council adoption of Notice of Motion J(19) at its meeting on February 2, 3
and 4, 1999, awarded Phase II of the WBST to McNally-Frontier Joint Venture Inc. at a
contract price of $17,259,100.00 including GST. See attached Appendix 'A' for summary of
project costs.
The purpose of the WBST, following Lakeshore Boulevard West between Strachan Avenue
and Parkside Drive, is to intercept and store, during periods of rainfall, polluted sewer
discharges which otherwise would flow to Lake Ontario from the City's combined sewer
system for subsequent treatment before release to the Lake. Intercepting and treating the
polluted sewer discharges will improve the water quality along the western waterfront and
substantially reduce the frequency of beach postings during the summer seasons. As
previously advised, both phases of the WBST project have now been awarded and the
contractor has completed approximately 65 per cent of Phase I construction. The contractor is
currently mobilizing for Phase II construction with the establishment of the construction
compound at Cowan Shaft located on the south side of Lakeshore Boulevard in line with
Dunn Avenue.
The WBST project is a design/build contract and during its entire construction period the City
must review and approve detailed engineering design calculations and design/shop drawings
proposed by the contractor, as well as carry out general project administration and site
supervision during construction, to ensure that the constructed work meets specified and
approved standards, performance specifications, and design drawings. The City must also
review and approve progress payments and change orders. To assist in carrying out these
tasks, the City engaged the consulting services of the joint consulting firms of
CG&S/MacViro for Phase I of the WBST project.
During construction of Phase II of this project, continuation of the same above-noted services
by the same two engineering consulting firms is recommended as being most beneficial to the
City of Toronto. These consultants undertook the preliminary design, preparation of the
design/build RFP and evaluation of contractor proposals, and their initial involvement gives
them detailed knowledge of the WBST project enabling them to competently review the
detailed design calculations and drawings being prepared by the general contractor. Both
consulting firms also have experience and expertise in deep tunnel and shaft construction. The
cost of the consulting firms' services for Phase II of the WBST project has been estimated at
$650,000.00 including GST and including a contingency allowance of $120,000.00 to cover
extended services during construction for Phase I and Phase II, if necessary. The consultants'
services will be paid on a time basis plus allowable disbursements, all in accordance with the
terms of the existing engineering agreement.
Conclusion:
The consulting firms of CH2M Gore & Storrie Limited and MacViro Consultants Inc. had
been selected by the City to undertake the preliminary design and preparation of design/build
tender documents for the WBST project and to provide general administration and site
supervision during Phase I construction. Accordingly, these consultants will provide
continuity of engineering services for the project and are therefore best suited to undertake the
detailed design services and the construction supervision and administration for Phase II of
the WBST project.
Contact Name and Telephone Number:
Pagnanelli, P.Eng.
Manager, Plant & Facility Construction
Engineering Services - Works Facilities and Structures
Technical Services Division
Telephone No. (416) 392-8245
T.G. Denes, P.Eng. B.H. Gutteridge
Executive DirectorCommissioner of Works and Emergency Services
Technical Services Division
AP/cr
APPENDIX "A"
WESTERN BEACHES STORAGE TUNNEL CONSULTING AND CONTRACTUAL
COSTS
CG&S/MacVIRO ENGINEERING CONSULTING FEES
AUTHORITY |
|
APPROVED FEES |
|
CUMULATIVE FEES |
|
SCOPE |
|
|
|
|
|
|
|
Council (Former City of
Toronto) July 5,1996
Board of Management
Communication No.59 |
|
$727,229.20 |
|
$727,229.20 |
|
1st RFP |
Board of Management
(Former City of Toronto)
Dec.11,1997,
Minute No.2.6 |
|
+$84,630.00 |
|
$811,759.20 |
|
2nd version of 1st RFP |
Council May
13,14,15,1998, WUC
Rep.4, Cl.2 |
|
+$970,000.00 |
|
$1,781,759.20 |
|
Phase 1 Design-Build |
PROPOSED
Council April
13,14,15,1999, WUC of
March 24,1999 |
|
+650,000.00 |
|
$2,431,759.20 |
|
Phase 2 Design-Build |
AWARDED CONTRACTUAL SUMS TO MACNALLY-FRONTIER JOINT VENTURE INC.
AUTHORITY |
|
TOTAL LUMP
SUM |
|
CUMULATIVE
TLS |
|
DESCRIPTION |
|
|
|
|
|
|
|
Council Feb.4,5,6,1998,
C&NSC Rep.1, Cl.6 |
|
-$31,500,000.00 |
|
$31,500,000.00 |
|
Awarded Phase 1 with
Alternative B (Battery Park
instead of Coronation Park
main shaft) |
Council Feb.2,3,4, 1999,
Notice of Motion J(19) |
|
+$17,259,100.00 |
|
$48,759,100.00 |
|
Phase 2 Design-Build |
|
|
|
|
|
|
|
All above amounts include the Goods and Services Tax
These costs are included in the approved 1999-2003 Capital Works Program, Capital Account
WP951, New District Sewers.