Prince Edward (Bloor Street Viaduct) -
Measures to Deter Suicide Attempts
(Don River and Midtown - Wards 23 & 25)
The Committee recommends the adoption of Recommendations (3) and (4) of the report (March 18, 1999) from the
Commissioner, Works and Emergency Services.
The Committee reports, for the information of Council, having deferred consideration of Recommendations (1) and (2) of
the report (March 18, 1999) from the Commissioner, Works and Emergency Services and requested the Commissioner to
report further to the Committee for consideration at its April 19, 1999 or May 17, 1999 meeting.
The Urban Environment and Development Committee submits the following report (March 18, 1999) from the
Commissioner of Works and Emergency Services:
Purpose:
To provide a status report on the Prince Edward (Bloor Street) Viaduct - Measures to Deter Suicide Attempts project and to
outline, through a series of recommendations, a proposed course of action that will allow the project to proceed to a
satisfactory conclusion.
Recommendations:
It is recommended that:
1.Subject to approval by the Toronto Transit Commission, Council authorize the additional expenditure of $800,000.00
for the purchase of a modified Bridgemaster vehicle to be included within the TTC's 2000 capital budget estimates, and
that the vehicle be maintained, thereafter, in the TTC's ownership;
2.in view of the confirmation of Dereck Revington Studios/Yolles Partnership Inc. that it cannot complete the project
within $1.5 million, the amount prescribed in the terms of reference for the design competition, Council authorize not
proceeding with finalization of an agreement with Dereck Revington Studios/Yolles Partnership Inc. and, instead, authorize
the engagement of E.R.A. Architect Inc. to prepare detailed design and tender documents for the construction of the Prince
Edward Viaduct Suicide Deterrent Measures based on its design proposal with the prescribed funding amount, and on
terms and conditions satisfactory to the Commissioner of Works and Emergency Services and the City Solicitor;
3.temporary measures be put in place without further delay, including six telephones and appropriate signage, and that the
additional annual costs estimated to be $2,500.00 incurred by the Distress Centre, be accommodated through a slightly
increased yearly grant to the Centre; and
4.the Schizophrenia Society working with community groups establish patrols on the bridge, the details of which would
be reported to Council at a later date.
Background:
Subsequent to a design competition, Council at its meeting held on October lst and 2nd, 1998, approved Clause 1 of Report
No. 11 of the Urban Environment and Development Committee authorizing the engagement of Dereck Revington
Studios/Yolles Partnership Inc. to prepare the detailed design and tender documents for the construction of the Prince
Edward Viaduct Suicide Deterrent Measures. The Terms of Reference for the design competition was very specific in
establishing an upper limit for the costs at $1.5 million and those expenditures were authorized by Council for the
completion of the project.
During the preliminary design stage, the TTC expressed concern that following the installation of the barrier, they would no
longer be able to carry out periodic inspections of the subway support substructure of the viaduct using their current
methodology, consisting of a vehicle with a long flexible arm and a bucket called the Bridgemaster, that reaches over the
handrail and under the bridge.
It also became clear that the selected design (or any of the other designs submitted) would not easily lend itself to periodic
dismantling in order to facilitate access by the Bridgemaster.
In order to resolve the impasse, City staff have been working closely with TTC staff and have examined various
alternatives including:
-a modified inspection vehicle capable of reaching over the barrier (Bridgemaster with a longer arm)
-a track mounted inspection vehicle (Bridgemaster on a TTC work train)
-construction of permanent inspection platforms under the subway tracks; and
-Remote Access Technology involving the use of ropes, harnesses and video equipment.
Discussion on the TTC's Inspection Needs:
TTC staff have estimated the costs of the alternative inspection methods, both in terms of capital expenditures and yearly
operating costs and have presented the following summary:
Options |
Capital
Costs
($x1,000) |
Yearly
Operating
Costs |
1.Using the current method with no
barrier in place |
$0 |
$ 56.5 |
2.Permanent platforms under the
subway tracks (5 arches) |
$2,000.00 |
$ 42.2 |
3.Modified Bridgemaster with
longer arm |
$ 800.00 |
$ 67.9 |
4.Remote Access Technology using
video equipment |
$0 |
$150.0 |
5.Track Mounted Bridgemaster |
$ 800.00 |
$129.9 |
6.Temporary Swing Stages |
$0 |
$637.2 |
7.Permanent Platforms for 2 arches
and bucket truck from Bayview and
the DVP |
$1,600.00 |
$ 57.2 |
Option 1 is the current method used by the TTC in performing inspections since 1996 using the MTO Bridgemaster.
Option 2 assumes construction in 1999 and 2000 concurrently with the approved support beam replacement contract.
Option 3 will require a delivery time of two years, however, the TTC is currently awaiting quotations from other
manufacturers.
Option 4in the TTC's opinion, poses a safety risk on one hand, and insufficient control over inspections on the other and,
therefore, has been rejected by them. City staff disagree. Remote access technology is a well accepted method of bridge
inspections and was last used in Ontario by the Ministry of Transportation - Ontario for substructure inspections of the
Garden City Skyway in the Niagara Region in 1998.
Option 5allows for limited inspection windows of less than two hours a day.
Option 6was the TTC's practice prior to 1996.
Option 7is a combination of Option 2 above and the use of a "cherry picker" truck from the ground for part of the
structure. This option would result in frequent road closures on both the Don Valley Parkway and the Bayview Extension.
TTC staff, having considered the implications of the alternatives, are prepared to recommend Option 3 in their report to the
Commission.
Discussion on the City's Inspection Needs:
During a meeting held on March 9, 1999, involving the Chair of the UEDC and some of the area Councillors, City staff
were requested to provide information, including costs involved in the inspection of the rest of the structure.
The deck of the Prince Edward Viaduct was last repaired in 1989. The recoating of the structural steel substructure
followed shortly after. In April 1999, we expect City Council to award the last recoating contract for Span No. 3.
Since the rehabilitation contract, former Metro Transportation and now the City staff have performed regular routine
inspections of this bridge. In general, inspection has been performed in accordance with the Structure Inspection Manual
issued by the Ontario Ministry of Transportation. Staff have used different methods for inspection on different components.
For example, staff would request special permission to enter into the TTC subway right-of-ways with the aid of flaggers to
visually inspect the underside of the bridge deck. For the substructure, more detailed inspection has been performed in
utilizing the falsework installed for the recoating contracts. Furthermore, visual inspection was also performed from the
ground with the aid of binoculars.
When preparing the recoating contracts for Span No. 2 (the Don Valley Parkway span) and Span No. 5 (the Bayview
Extension span) "man lifts" or a "cherry picker" bucket truck was used to inspect the steel work. For Spans Nos. 3 and 4
(the Don River span) an inspection engineer with safety harnesses climbed up the structural steel from ground. Steel cable
lifelines were also installed to assist the inspection from a safety standpoint. This bridge is currently in good condition,
therefore, inspection costs for the City only include staff time and the accessory cost is minimal.
Discussion on Cost Estimates provided by Dereck Revington Studios:
The Terms of Reference for the design competition specified the amount of $1.5 million as the maximum amount within
which the project had to be completed. Dereck Revington Studios/Yolles Partnership Inc. won the competition based on
those Terms of Reference and Council authorized the engagement of these companies at its meeting held on October lst and
2nd, 1998. In early March 1999, following some quantity estimates by City staff, Mr. Revington was requested to provide
assurance, in writing, that the cost of the project would not exceed $1.5 million. In his response dated March 14,1999, he
indicates that he can no longer stand by his original estimate and, in fact, the project will cost substantially more than
specified in the Terms of Reference. His current estimate is $2.14 million.
City staff have approached E.R.A. Architect Inc., the runner-up in the design competition, and they have indicated in a
letter dated March l7, 1999, that they stand behind their original estimates.
Under the circumstances, it would be appropriate for Council to withdraw its previous approval relating to the engagement
of Dereck Revington Studios/Yolles Partnership Inc. and to instruct the Commissioner of Works and Emergency Services
to enter into an agreement with E.R.A. Architect Inc. to prepare the detailed design and tender documents. The City
Solicitor is in agreement with this recommendation.
Heritage Toronto, who played a key role in the selection of the successful design alternatives, are also in agreement with
the recommendation.
Discussion on Temporary Measures:
If Council authorized commencement of the project at its upcoming meeting, it would be completed by the late fall of 1999
at the earliest. In the meantime, immediate short term measures should be considered. These measures include the
installation of telephones and community patrols on the bridge. Both of these proposals were discussed by the Steering
Committee during the preliminary design phase.
Telephones:
Dedicated telephone lines may prove useful for individuals in need of professional advice. Such telephone lines have been
employed in other jurisdictions with a great degree of success. A total of six telephones would be connected directly to the
Distress Centre where qualified personnel would deal with individual situations.
The following is the estimate of costs:
-Initial cost of installation |
|
$16,000 |
-Operating cost for telephone lines |
|
$ 2,700 per annum |
-Additional costs incurred by the
Distress Centre: |
Initial
Operating |
$ 5,000
$ 2,500 per annum |
Patrols:
The patrols can either be from the police or from community groups such as the Schizophrenia Society. In view of the
restraint on the police budget, it may be difficult to have their commitment. As for the community groups, this service
would be provided on a voluntary basis. It is uncertain, at this time, what level of patrolling is necessary, thus an estimated
cost cannot be made until the unknowns are realized.
Conclusion:
The project has suffered significant delays due to the need to accommodate the TTC's ongoing bridge inspection needs. It
would now appear that the TTC requirements can be satisfied at an additional cost of $800,0000. If Council agrees to the
continued engagement of Dereck Revington Studios/Yolles Partnership Inc. at a cost which is $0.85 million higher than the
original submission including contingencies, the project will proceed immediately upon approval and, barring further
delays, it stands a good chance of being completed by the end of 1999. In the meantime, temporary measures in the form of
telephones, signs and community patrols should be instituted without further delay.
Contact Name & Telephone No.
Mike Chung, P.Eng.
Manager, Structures & Expressways
Design Construction and Inspection
Technical Services Division
Tel. 392-8341
The Urban Environment and Development Committee also submits the following report (March 24, 1999) from the
General Manager, Toronto Transit Commission:
At its meeting on Tuesday, March 23, 1999, the Commission considered the attached report entitled, "Prince Edward
Viaduct - Suicide Barrier and TTC Structural Inspection Options."
The Commission approved the Recommendation contained in the above report, as listed below:
"It is recommended that the Commission approve:
1.Receipt of this report for information noting that:
-the proposed Prince Edward Viaduct suicide barrier prevents the TTC from using current methods for inspecting the
portion of the bridge structure for which TTC is responsible, and
-City staff are reluctant to consider an alternative barrier design which would accommodate TTC's inspection needs, and
-as a result, it will be necessary to procure an inspection vehicle (estimated to cost $800,000) to allow our inspections to
continue, and
-alternatively, a removable fence (see attached drawing #3) could be considered as a suicide barrier (estimated at
$650,000)which would allow TTC's current cost effective inspections to continue.
2.Forwarding this report to City of Toronto Council to request City funding of the required larger inspection vehicle."
The foregoing is forwarded to the Urban Environment and Development Committee and City of Toronto Council for
consideration of the Commission's request that funding for the design and procurement of the larger inspection vehicle be
incorporated in the City of Toronto's Capital Program, as noted above.
--------
The Urban Environment and Development Committee also had before it the following communications and copies thereof
are on file in the office of the City Clerk:
-(March 24, 1999) from the General Secretary, Toronto Transit Commission forwarding their Report No. 22 to City of
Toronto Council and requesting City funding for the required larger inspection vehicle.
-(March 16, 1999) from Alan L. Berman, Executive Director, American Association of Suicidology, supporting the effort
to create anti-suicide barriers at the Bloor Viaduct.
-(February 12, 1999) from David Lester, Ph.D., Professor of Psychology, Past President of the International Association
for Suicide Prevention, supporting the fencing in of the Bloor Street West Viaduct to prevent people jumping from it in an
effort to commit suicide.
-(March 25, 1999) from Councillor Ila Bossons requesting the Provincial Government to provide financial assistance for
the Bloor Viaduct suicide barrier.
-(March 29, 1999) from Dr. Chris Cantor, Senior Research Psychiatrist, Australian Institute for Suicide Research and
Prevention, urging all interested parties to negotiate a solution which permits a very worthwhile suicide prevention project
to proceed.
-(March 26, 1999) from Robin R. Richards, Head, Division of Orthopaedics, St. Michael's Hospital, informing the
Committee of the number of patients who have fallen from the Bloor Viaduct and survived with usually massive disabling
and permanent injuries.
-(March 26, 1999) from Geoffrey Thun, Dereck Revington Studio, forwarding three letters of recommendation regarding
measures to deter suicide on the Bloor Street Viaduct.
-(February 12, 1999) from David Lester, Professor of Psychology, The Richard Stockton College of New Jersey, urging
that fences be placed on the Bloor Viaduct.
-(March 16, 1999) from Alan L. Berman, Executive Director, American Association of Suicidology, supporting the effort
to create anti-suicide barriers at the Bloor Viaduct.
-(March 26, 1999) from E.H. Zeidler, Zeidler Roberts Partnership/Architects, commenting on the intent of the Committee
to employ the services of another architect.
-(March 29, 1999) from Dereck Revington, Dereck Revington Studio, forwarding documents relating to the Bloor
Viaduct - Preventive Measures.
-(March 29, 1999) from Claude Prevost, Regie Regionale De La Sante Et Des Services Sociaux, confirming that the
installation of a safety fence would be the most appropriate measure.
The following persons appeared before the Urban Environment and Development Committee in connection with the
foregoing matter:
-Ellis Galea Kirkland, Juror, Bloor Viaduct Barrier Design Selection Committee, Urban Planning and Development
Services, City of Toronto;
-Derek Revington, Derek Revington Studios;
-Morden Yolles, Yolles Engineering Inc.;
-Richard Vermeulen, Vermeulen Cost Consultants;
-Dr. Isaac Sakinofsky, Clarke Institute;
-J.A. (Al) Birney, Past President of East York Chapter and Bridge Committee Chairman, Schizophrenia Society of
Ontario; and
-Michael McCamus, Bridge Committee Spokesperson, Schizophrenia Society of Ontario and Member of Bloor Viaduct
Project Steering Committee.