City of Toronto   *
HomeContact UsHow Do I...? Advanced search Go
Living in TorontoDoing businessVisiting TorontoAccessing City Hall
 
Accessing City Hall
Mayor
Councillors
Meeting Schedules
   
   
  City of Toronto Council and Committees
  All Council and Committee documents are available from the City of Toronto Clerk's office. Please e-mail clerk@toronto.ca.
   

 

Transmittal of Evaluation of the

Leaside Neighbourhood Branch Library -

Capital Budget Project

The Strategic Policies and Priorities Committee recommends the adoption of the Recommendation of the Budget Committee embodied in the following communication (May26,1999) from the City Clerk:

Recommendation:

The Budget Committee on May 25, 1999, recommended to the Strategic Policies and Priorities Committee, and Council, the adoption of the report (May 10, 1999) from the City Librarian.

The Budget Committee reports, for the information of the Strategic Policies and Priorities Committee and Council, having requested the City Librarian to report back to the Budget Advisory Committee during the year 2000 Capital Budget process outlining cost savings due to efficiencies in staffing and maintenance.

Background:

The Budget Committee had before it a report (May 10, 1999) from the City Librarian advising that the Toronto Public Library Board on May 3, 1999, adopted the Leaside Neighbourhood Branch Library report from the City Librarian, wherein it is recommended that:

(1)the Board adopt Option (2) as outlined in the Parkin Group report as the preferred option and convey this to the Budget Committee in May 1999, as requested; and

(2)the Board proceed to working drawings for the new building in 1999, funded by expending the balance of the 1999 capital allotment for the Leaside project estimated at $240,000.00.

--------

(Report dated May 10, 1999, addressed to the

Budget Committee from the City Librarian)

Attached for consideration of the Budget Committee at its meeting on May 25, 1999, is the Leaside Neighbourhood Branch Library report (May 3, 1999) from the City Librarian, which was adopted by the Toronto Public Library Board at its meeting on May3, 1999, wherein it is recommended that:

(1)the Board adopt Option (2) as outlined in the Parkin Group report (April 26, 1999) as the preferred option and convey this to the Budget Committee in May 1999, as requested; and

(2)the Board proceed to working drawings for the new building in 1999, funded by expending the balance of the 1999 capital allotment for the Leaside project estimated at $240,000.00.

The report is provided in response to the Budget Committee's request for an overall evaluation of the Leaside Public Library facility.

Project Cost Estimates (GST is excluded from all amounts)

Option 1 - Upgrade Existing Building

-Renovations to existing building including$1,362,409.00

construction of new elevator, barrier free

washroom and enlarged main entrance

-Professional fees and associated costs (10 percent)136,000.00

-Furniture, fixtures and equipment175,000.00

-Building permit fees at $12.00 per square metre11,160.00

Total Project Cost Estimate (renovation)$1,684,569.00

Option 2 - New Building

-Construction of new 9,000 square feet library$1,477,211.00

including demolition of existing building

-Professional fees and associated costs (10 percent)147,720.00

-Furniture, fixtures and equipment175,000.00

-Building permit fees at $12.00 per square metre10,800.00

Total Project Cost Estimate$1,810,731.00

(new construction)

--------

(Report dated May 3, 1999, addressed to the

Toronto Public Library Board from the City Librarian)

Purpose:

To present the results of the Feasibility Study to determine whether to retrofit or reconstruct Leaside Neighbourhood Library.

Funding Sources, Financial Implications and Impact Statement:

Funding for the project was provided in the 1998 Capital Budget and further funds were approved pending the City Librarian's report to the Budget Committee on an overall evaluation of the Leaside Public Library facility.

Recommendations:

It is recommended that the Toronto Public Library Board:

(1)adopt Option (2) as outlined in the Parkin Group report as the preferred option and convey this to the Budget Committee in May 1999, as requested; and

(2)proceed to working drawings for the new building in 1999, funded by expending the balance of the 1999 capital allotment for the Leaside project estimated at $240,000.00.

Comments and/or Discussion and/or Justification:

In 1998, a capital budget of $235,000.00 was approved for the Leaside Neighbourhood Library to provide barrier-free access to the building (elevators, washroom, automatic doors). Upon undertaking the work for this project, difficulties associated with high water table escalated the cost to $600,000.00.

As a result of the 1999 capital budget discussions, Council directed that the increase in expenditures of $65,000.00 in 1999 and $300,000.00 in 2000 required for the Leaside Accessibility project be approved pending the City Librarian's report to the Budget Committee on an overall evaluation of the Leaside Public Library facility.

Overall concern was expressed about the $600,000.00 cost of providing barrier-free access when the whole facility could be completely replaced at two-to-three times the cost. The expenditure was considered not good value for money, particularly in view of the fact that other building deficiencies would remain.

The Parkin Group was employed by Toronto Public Library to undertake an overall evaluation of the Leaside Public Library.

The results of the Parkin Group study are two options, with costing provided for each. Option (1) is for renovating the existing facility at just under $1.7 million. Option (2), the recommended option, is for demolition of the existing facility and construction of a new facility at $1.8 million.

In assessing both options it is important to note that the renovation program to upgrade the existing facility in Option (1) does not address a number of significant deficiencies, and there is no guarantee as to the longevity of the building or equipment:

(a)An elevator is required in the retrofit option. In addition, the elevator doors will open directly into the auditorium; there is no space for a vestibule or lobby area on the lower level.

(b)While the circulation desk service area will be enhanced with a renovation, site lines into the adult and children's areas will remain problematic. It is anticipated that current staffing levels at Leaside will remain unchanged. For those times when it is not possible to staff the adult or children's desks, the circulation desk staff will continue to be responsible for service in those areas and will have difficulty monitoring these activities.

(c)The stairway to the lower level is very steep. An investigation was undertaken to rebuild the existing stairway that would see a decrease in the slope as well as eliminate the 90 degree turn at the landing. However, such a significant redesign of the existing facility would impact on space allocation (a minimum of eight feet would be lost in the auditorium), and increase costs significantly. In the retrofit option, there is no change to the existing stair.

(d)There will continue to be inefficient use of space. There is no opportunity to rationalize space allocation for collection and services; e.g., the proportion of adult and children's areas and the opportunity to respond to local needs such as the addition of a local history collections area.

(e)Energy efficiency of the building could be improved with the installation of insulation and a vapour barrier on perimeter walls, but this upgrade may cause deterioration of the exterior wall brickwork.

A significant investment of almost $1.7 million results in some important improvements to the Leaside Library. However, the Library Board is left with a facility built in 1950 where a number of deficiencies continue, and the life expectancy of the building and equipment remain uncertain.

Contact Names:

Ms. Ann Eddie, Director, Administration, 393-7091, Mr. Bruce Barnett, Senior Manager, Facilities, 395-5880.

(A copy of the Leaside Branch Feasibility Study referred to in the foregoing report was forwarded to each Member of Council with the agenda of the Budget Committee meeting of May 25, 1999, and a copy thereof is also on file in the office of the City Clerk.)

 

   
Please note that council and committee documents are provided electronically for information only and do not retain the exact structure of the original versions. For example, charts, images and tables may be difficult to read. As such, readers should verify information before acting on it. All council documents are available from the City Clerk's office. Please e-mail clerk@toronto.ca.

 

City maps | Get involved | Toronto links
© City of Toronto 1998-2005