Seaton House Renovations

The Community Services Committee recommends the adoption of the following reports:

(Report dated June 21, 1999, addressed to the

Community Services Committee from the

Commissioner of Community and Neighbourhood Services)

Purpose:

To approve capital budget financing and to award a construction contract for Seaton House capital renovations.

Funding Sources, Financial Implications and Impact Statement:

Funds for the capital renovations are included in the 1997-2001 Capital Works Program totalling

$4 million, as previously approved by Council.

Previous approvals: Clause No. 8 of Report No. 9 of the Human Services Committee of the former Metropolitan Toronto Corporation ($0.8 million gross) and Clause No. 23 of Report No. 6 of the Strategic Policies and Priorities Committee ($3.2 million gross).

The Ontario Ministry of Community and Social Services has verbally approved 50 percent cost-sharing towards total project expenditure of up to $7.0 million. Written confirmation of the cost-sharing has been requested.

Recommendations:

It is recommended that:

(1)a construction contract be awarded for Seaton House renovations, as per the staff report available July 10, 1999;

(2)financing in the amount of $4.0 million net, and debentured if necessary for a term up to but not exceeding 10 years, be approved; and

(3)the appropriate City officials be authorized and directed to take the necessary action to give effect thereto.

Council Reference/Background/History:

On January 29, 1997, the Council of the former Municipality of Metropolitan Toronto adopted a report which initiated the Seaton House restructuring process, and established a panel to assist the Commissioner in implementing the changes recommended in that report. On July 3, 1997, Council received and approved a report on the consultation regarding the redesign of programs and major renovations at Seaton House. A progress report was received by Council in October 1998.

Comments and/or Discussion and/or Justification:

Tenders from contractors will be received on June 30, 1999. A staff report recommending the award of the construction contract will be ready for Committee by July 10, 1999. It is important for Committee to approve the recommendation at its July meeting so that construction can begin in August 1999.

While Seaton House is relocating close to half of its current residents during the construction period, it will remain partially occupied for that period of time. Major portions of the heating system will be replaced as part of the construction contract. Therefore, it is important to award the contract as soon as possible so that work can be completed before the upcoming winter season.

A delay in the approval process will delay construction start-up time and therefore pose potential health and safety risks to residents and staff remaining on site.

Conclusion:

Approval of this report will permit the project to proceed to the construction phase.

Contact Name:

John Jagt

Director of Hostel Services

Tel: 392-5358

(Joint report dated July 12, 1999, addressed to the

Community Services Committee from the

Commissioner of Community and Neighbourhood Services and

the Chief Financial Officer and Treasurer)

Purpose:

The purpose of this report is to advise the results of the tender issued for Seaton House renovations, 319-339 George Street, in accordance with specifications as required by the Community and Neighbourhood Services Department, and to request the authority to issue a contract to the recommended bidder.

Source of Funds:

Funds are available in the Capital Works Program.

Recommendation:

It is recommended that Tender Call No. 129-1999 for Seaton House renovations, 319-339 George Street, be awarded to Ross Clair/Division of ROM Contractors Inc., in the total amount of $5,715,000.00 including all taxes and charges, being the lowest tender received.

Council Reference/Background/History:

The Bid Committee at its meeting held on June 30, 1999, opened the following tender for Seaton House renovations, 319-339 George Street:

TendererTender Price

Ross Clair/Division of ROM Contractors Inc.$5,715,000.00

M. J. Dixon Construction Ltd.$5,800,000.00

The Atlas Corportation$5,920,000.00

Richard & B.A. Ryan Ltd.$6,351,433.00

Jasper Construction Group$6,472.000.00

Comments and/or Discussion and/or Justification:

The Tender Documentation submitted by the recommended bidder has been reviewed by the Commissioner of Community and Neighbourhood Services and was found to be in conformance with the tender requirements.

The Manager, Fair Wage and Labour Trades Office, has reported favourably on the firm recommended.

Conclusion:

This report requests authority to issue a contract for Seaton House renovations, 319-339 George Street, in accordance with specifications, to Ross Clair/Division of ROM Contractors Inc., being the lowest tender received.

Contact Name:

John Jagt

Director Hostel Services

Tel: 392-5358

 

   
Please note that council and committee documents are provided electronically for information only and do not retain the exact structure of the original versions. For example, charts, images and tables may be difficult to read. As such, readers should verify information before acting on it. All council documents are available from the City Clerk's office. Please e-mail clerk@toronto.ca.

 

City maps | Get involved | Toronto links
© City of Toronto 1998-2005