Procurement Authorization - Supply and Installation of
Permanent Inspection Platforms
on the Prince Edward Viaduct
The Policy and Finance Committee reports having referred the following communication (September 3, 1999) from
the Interim General Secretary, Toronto Transit Commission to the Chief Financial Officer and Treasurer for
report thereon directly to Council for its meeting scheduled to be held on September 28, 1999, respecting the
availability of funds for this project:
At its meeting on Wednesday, September 1, 1999, the Commission considered the attached report entitled, "Procurement
Authorization - Supply And Installation Of Permanent Inspection Platforms On The Prince Edward Viaduct."
The Commission adopted the Recommendation embodied in the above report, as listed below:
"It is recommended that the Commission approve:
(1)acceptance of the tender submitted by Dundas Iron and Steel Limited in the amount of $959,400.00 for the supply and
installation of permanent inspection platforms on the Prince Edward Viaduct;
(2)proceeding with this work as a result of the City Works and Emergency Services Department's project to install a
suicide barrier on the Prince Edward Viaduct and holding the expenses in TTC accounts pending City Council approval;
and
(3)forwarding this report to City Council to confirm funding."
The foregoing is forwarded to City of Toronto Council for the purpose of confirming the availability of funding for this
project.
--------
Toronto Transit Commission
Report No. 20, entitled "Procurement Authorization -
Supply And Installation Of Permanent Inspection
Platforms On The Prince Edward Viaduct"
from its meeting of September 1, 1999.
Recommendation
It is recommended that the Commission approve:
(1)acceptance of the tender submitted by Dundas Iron & Steel Limited in the amount of $959,400.00 for the supply and
installation of permanent inspection platforms on the Prince Edward Viaduct;
(2)proceeding with this work as a result of the City Works and Emergency Services Department's project to install a
suicide barrier on the Prince Edward Viaduct and holding the expenses in TTC accounts pending City Council approval;
(3)forwarding this report to City Council to confirm funding.
Funding
No funds were budgeted for this expenditure in the 1999-2003 TTC Capital Program as approved by City Council on
March 2, 1999. At its meeting of May 11 and 12, 1999, City Council approved an $800,000.00 expenditure associated with
the purchase of a Bridgemaster unit which was required to allow TTC to continue to inspect the underside of the concrete
track and steel walkways. At that time, it was agreed that funding for the purchase would be determined as part of the
2000-2004 budget process.
The TTC has been unable to secure a suitable Bridgemaster unit and therefore have proceeded with a tender for the
installation of permanent inspection platforms. The platforms require additional funding of $159,400.00 which will be
included in the TTC 2000-2004 Capital Program. As before, the funding arrangements will be determined as part of the
budget process.
Background
At its meeting of March 23, 1999 the Commission approved in principle, the procurement of a specialized inspection
vehicle (modified Bridgemaster), in the estimated amount of $800,000.00. This estimated cost was based on preliminary
pricing received from a prospective supplier. This requirement was based on the need to allow TTC to continue to inspect
the underside of the TTC concrete track and steel walkway beams, as a result of the City's program to construct the suicide
prevention barrier on the Prince Edward Viaduct.
At its meetings of May 11 and 12, 1999, City Council approved an amount of $800,000.00 for the purchase of a modified
Bridgemaster vehicle to be included in the TTC's 2000 Capital Budget as a special item over and above the TTC's capital
funding needs and that these costs be recovered over 10 years by a yearly rental. The final arrangements for the funding
were to determined as part of the 2000-2004 Capital Program process.
Subsequently, staff prepared specifications for the procurement of a specialized inspection vehicle to ensure that the
Commission could continue to inspect the Prince Edward Viaduct structure every two years, in accordance with
recommendations from the National Bridge Inspection Standards and published MTO Standards - Ontario Structure
Inspection Manual. An advertisement was placed in the Daily Commercial News and a total of seven (7) companies
requested tenders, out of which one (1) submitted a tender which was technically non-compliant.
As a result of the formal tendering process, manufacturers have advised that a vehicle meeting inspection requirements
(extended reach) is not currently available on the market and that to produce one would require extensive research and
development. It should be understood that the preliminary pricing was based on an off-the-shelf vehicle and that a modified
vehicle would cost substantially more to design and manufacture than previously indicated.
The City's project schedule is to install the suicide prevention barrier by the end of December 1999, and due to its impact
on TTC inspections, staff proceeded to obtain tenders for a second option. This option was for the installation of permanent
inspection platforms on the Prince Edward Viaduct.
The work entails fabricating and installing small steel platforms at the end of each row of beams, which would be
accessible from track level to carry out inspections. There would be an added benefit that during the annual replacement
program for track beams, the contracting out of the erection and dismantling of temporary wooden stages and work
platforms would not be required. By enabling TTC to carry out its inspections and work on its own, permanent platforms
would reduce lane closures and disruptions both on Bloor Street across the Prince Edward Viaduct and on the roadways
beneath the bridge. The tender indicated that the temporary suspended scaffolds on the Don Valley Parkway and Bayview
Avenue would remain in place to enable this installation. A window of opportunity exists to utilize these temporary
suspended scaffolds, currently in place for replacement of the walkway beams on the Prince Edward Viaduct, to install the
permanent platforms. However, some scaffolds are scheduled to be removed this fall and it is essential that this
procurement proceed now, otherwise the cost and complexity of the work would increase substantially.
The order of magnitude for the permanent platform option is comparable to the procurement of the specialized inspection
vehicle previously approved by City Council at its meetings of May 11 and 12, 1999. Also, there will be a reduction of
approximately $100,000.00 in the annual procurement of temporary work platforms. Staff consider the permanent
platforms as a preferable option which avoids the complications of using a specialized vehicle for a brief annual period,
rental payments and vehicle maintenance. The TTC will be able to minimize road closures on the Don Valley Parkway and
Bayview Avenue in the future as a result of the installation.
The TTC is currently scheduled for a weekend closure of the Don Valley Parkway on the weekend of October 15, 1999 to
remove the temporary suspended scaffold platforms. To accommodate this procurement, it will be necessary to defer this
closure to November.
Discussion
Specifications and drawings were prepared for the above noted contract and a request for tender was issued with a closing
date of August 9, 1999. An advertisement was placed in the Daily Commercial News and a total of seventeen (17)
companies requested tenders, out of which seven (7) submitted tenders. All responses are summarized in Appendix "A".
The lowest tender was submitted by Canron Construction Corporation East in the amount of $877,688.00. However their
tender included the following exceptions which are considered unacceptable: Canron could not meet the scheduled
completion unless they received notification of award immediately after the tender closing; Canron took exception to the
specified terms of payment as their tender was based on monthly progress payments in lieu of payment following
completion of each span of the platforms; and Canron's tender was based on the TTC being responsible for re-routing all
hydro, telephone and other utilities rather than the contractor as specified in the tender documents. Based on the above, the
tender submitted by Canron Construction Corporation East is considered commercially unacceptable.
The second lowest tender, which meets all contract requirements and contains no exceptions or qualifications, was
submitted by Dundas Iron & Steel Limited in the amount of $959,400.00. Dundas Iron & Steel has satisfactorily completed
work for the Commission as a sub-contractor. Reference checks were completed which indicated they have satisfactorily
performed work of a similar size and nature in the past. Their tender is considered commercially and technically compliant.
The Agreement to Bond submitted by Dundas Iron & Steel Limited covers both a Labour and Material Payment Bond and
a performance Bond and was submitted by a Surety Company licensed to transact business in Ontario.
Justification
It is necessary to proceed with the foregoing procurement expenditure in order to meet published safety recommendations
for bridge inspection. Given the City's program to construct a suicide barrier, the installation of permanent inspection
platforms are necessary to inspect the underside of the TTC concrete track and steel walkway beams, thus ensuring the
safety and integrity of the subway system on the Prince Edward Viaduct and the safety of human and vehicular traffic on
the roadways and pathways located beneath.
August 10, 1999
6-123-124
Attachments
Appendix "A"
Supply, Installation Of Permanent Inspection Platforms
On The Prince Edward Viaduct
Tender no. T31W9807
FirmsTotal Tendered Price
Canron Construction Corporation East$ 877,688.00*
Dundas Iron & Steel Ltd.$ 959,040.00
Autogene Industries North Bay Inc.
O/A Central Welding & Iron Works$1,292,832.00
Consolidated Canadian Contractors
(1031695 Ontario Inc.)$1,316,000.00
M & G Steel Ltd.$1,355,000.00
E.S. Fox Ltd.$1,402,971.70
Lorvin Steel Ltd.$1,643,200.00
Engineer's Estimate-$1,300,000.00
*Commercially Non-compliant.