City of Toronto   *
HomeContact UsHow Do I...? Advanced search Go
Living in TorontoDoing businessVisiting TorontoAccessing City Hall
 
Accessing City Hall
Mayor
Councillors
Meeting Schedules
   
   
  City of Toronto Council and Committees
  All Council and Committee documents are available from the City of Toronto Clerk's office. Please e-mail clerk@toronto.ca.
   

 

STAFF REPORT

September 3, 1999

To: North York Community Council

From: Wayne Green, Director, Quality Control & System Planning

Subject: Water Distribution System Analysis: Area within Ward 8 Bounded by Highway 401 to the south, Steeles Avenue to the north, Keele Street to the west, and Bathurst Street to the east

Purpose:

To respond to a resolution embodied in Report No. 15 of the North York Community Council, as adopted by Toronto City Council at its meeting of December 17 and 18, 1998 requesting a review of water pressure in the area bounded by Highway 401 on the south, Steeles Avenue on the north, Keele Street on the west and Bathurst Street on the east.

Financial Implications and Impact Statement:

Funding to address fire flow protection deficiencies identified in the analysis, in the amount of $3,320,000.00, will be requested in the 2000 Water and Wastewater Services Capital Works Program.

Recommendations:

That this report be received for information.

Background:

In June, 1998, Environmental Hydraulics Group, a consultant working for Canada Lands Corp., submitted a hydraulic analysis report to support the redevelopment of the Downsview Base Lands. These lands are substantially higher in elevation that the surrounding area in Pressure Zone 5 and would not receive adequate pressure from a conventional connection to the adjacent watermain network.

The consultant's recommended alternative was to extend Pressure Zone 6 approximately two kilometres to the south (Figure 7). Pressure Zone 6 can supply water at a significantly higher pressure to most of the proposed development. This alternative would also result in a substantial increase in pressure to the area immediately north of the Base Lands, which currently has substandard static pressure.

However, Pressure Zone 6 cannot provide sufficiency fire flow capacity to the Base Lands because of the friction losses over the extra distance from the Keele Pumping Station. Additional flow would have to be provided from Pressure Zone 5 using one-way check valves that only open under fire flow conditions. In order to more fully evaluate the impact of the consultant's proposal on the existing water distribution system, City staff began assembling a network analysis computer model for this area.

In December, 1998, City Council adopted the recommendation by North York Community Council that the City commission a review of water pressure in the area bounded by Highway 401 on the south, Steeles Avenue on the north, Keele Street on the west and Bathurst Street on the east. Most of this study area falls within Pressure Zone 5 West and Pressure Zone 6, shown in Figure 1.

A study was subsequently undertaken to address the following objectives:

- To evaluate a proposal submitted by Canada Lands for servicing the Downsview Base Lands;

- To address the concerns raised by North York Community Council regarding water pressure deficiencies in the area bounded by Highway 401 to the south, Steeles Avenue to the north, Keele Street to the west and Bathurst Street to the east; and

- To evaluate the general hydraulic capacity of the system within the western part of Pressure Zone 5.

Comments:

Residential Pressure Complaints

Internal flow tests (at the water meter inside the house) have indicated that a substantial number (greater than 5%) of the homes in the area bounded by Sheppard Ave., Dufferin St., Finch Ave. and Bathurst St. have inadequate internal flow capacity (less than 18 litres/minute) as defined by the City's new Residential Service Connection Repair Program. The average recorded internal flow capacity for homes with inadequate capacity is only 11 litres/minute. The public road allowance portion of the connections in these locations have been, or are in the process of being, replaced as part of the repair program.

In carrying hydrant flow tests for model calibration, a particularly dense grid of tests were carried out in the above area. These tests indicated that there is adequate flow capacity and pressure in the general watermain network in this area (a summary of the flow test reports is included in the Technical Report). The inadequate internal flow capacity is the result of older ½" diameter water service connections that have accumulated internal deposits that severely restrict their flow capacity.

Fire Flow Capacity

The hydrant flow tests did indicate that there are a number of other locations where fire flow capacity is inadequate or just barely adequate. These locations were generally in small sub-areas, where flow is only supplied in one direction from the major network, and where extensive rehabilitation has not been carried out. The most severely deficiency was found at the end of Timberlane Drive, which is a particularly long cul-de-sac.

Remedial Alternatives for Fire Flow Capacity Improvement

The assembled network analysis computer model was calibrated using field measured test data and then used to evaluate the capacity of the network and to test remedial works alternatives. The flow tests were used to calibrate the computer model, and the model was used to evaluate the existing capacity of various parts of the network and to test remedial works alternatives. A comprehensive review of watermain break history data was also undertaken to determine whether the remedial works should consist of replacements or cleaning and lining. A summary of recommended works is shown in Figure 2 to 6 and provided in the following:

RECOMMENDED WORKS ESTIMATED COST
Watermain replacement the watermain on Timberland Dr. (Fig. 2) $300,000
Watermain replacement works in the Armour Blvd. Area (Fig. 2) $625,000
Watermain cleaning and lining works in the Armour Blvd. Area (Fig. 2) $575,000
Watermain replacement works on Maple Leaf Dr. (Fig. 3) $450,000
Watermain replacement works in the Exbury Area (Fig. 4) $245,000
Watermain cleaning and lining works in the Exbury Area (Fig. 4) $205,000
Watermain Replacement works in the Firgrove Cr. Area (Fig. 5) $350,000
Watermain cleaning and lining works in the Strathallan Wood Area (Fig. 6) $570,000
TOTAL: $3,320,000

Review of Base Lands Servicing Proposal

The network model was also applied to assess the consultant's recommended servicing alternative for the Base Lands (Fig. 7). The analysis indicates that the consultant's alternative will generally function as predicted. The additional draw from Zone 5 under fire flow conditions will not result in an unacceptable drop in pressure in the neighbouring area. However, the modelling indicated that the dead-ends created through the proposed closure of gate valves on Ashwarren Dr. and Steeprock Dr. will result in some local flow deficiencies. Instead of the closed gate valves, there is a need for two additional check valves in these locations.

Improving Residential Flow Capacity

Some consideration was given to evaluating a further modification of the pressure zone boundaries to increase static pressures in the complaint area mentioned above. However, as previously discussed, the average flow capacity in substantial locations was found to be only 11 litres/minute. It is estimated that the static pressure would have to be raised to ~ 790 kpa in order to force an adequate amount of flow (18 litres/minute) through these connections. This level of pressure is not practical and could not be supplied even if the complaint area was supplied through Pressure Zone 6.

The only practical alternative for improving residential flow capacity is to replace the service connections in those locations with substandard flow capacity. In June, 1999 Council adopted a Harmonized Residential Water Service Connection Repair Program. As part of this Program, the City has committed to replacing the portion of service connections within the road allowance in locations where the flow capacity measured at the house meter is less than 18 litres/minute (which is an enhancement over the former City of North York criteria of 15 litres/minute). While there is sufficient capacity in the local watermain network to provide more than 18 litres/minute to the homes, the full potential of the improvement is realized if the homeowner also arranges for the replacement of the portion of the service connection on private property.

Conclusions:

The remedial works recommended as a result of this study will improve the water distribution system's ability to provide adequate flow capacity under fire conditions. Funding to address fire flow prevention deficiencies identified in the analysis, in the amount of $3,320,000, will be requested in the 2000 Water and Wastewater Services Capital Works Program.

Resident complaints regarding inadequate internal flow pressure can best be addressed through the City's new Harmonized Residential Water Service Connection Repair Program. It is estimated that $12 million will be budgeted for this program City-wide in the 2000 Water and Wastewater Services Capital Budget.

Contact:

Eric Arm, P. Eng.

Team Lead,

Water Distribution Asset Management & Modelling

Telephone (416) 395-6234

Wayne Green, P. Eng.

Director of Quality Control and System Planning

Water & Wastewater Services

Works & Emergency Services

EA/car

 

   
Please note that council and committee documents are provided electronically for information only and do not retain the exact structure of the original versions. For example, charts, images and tables may be difficult to read. As such, readers should verify information before acting on it. All council documents are available from the City Clerk's office. Please e-mail clerk@toronto.ca.

 

City maps | Get involved | Toronto links
© City of Toronto 1998-2005