 STAFF REPORT


March 6, 2000

To: Works Committee

From: Barry H. Gutteridge, Commissioner, Works and Emergency Services

Wanda Liczyk, Chief Financial Officer and Treasurer

Subject:F.G.Gardiner Expressway - Rees Street to York Street

Substructure Rehabilitation, Contract No. 00FS-02S, Tender Call No. 07-2000 (Downtown)

Purpose:

The purpose of this report is to advise the results of the Tender issued for substructure rehabilitation of the F. G. gardiner expressway - Rees Street to York Street, in accordance with specifications as required by the Works and Emergency Services Department, and to request the authority to issue a contract to the recommended bidder.

Financial Implications and Impact Statement:

Funds to cover the cost of this project, in the estimated amount of $1,715,550.26 have been included in the recommended Transportation Services 2000 Capital Works Programme which has been approved by City Council.

Recommendations

It is recommended that Contract No. 00FS-02S, Tender Call No. 07-2000 for substructure rehabilitation of the F.G.Gardiner Expressway - Rees Street to York Street be awarded to G. Tari Limited, in the total amount of $1,715,550.26 including all taxes and charges, being the lowest Tender received.

Background:

The Bid Committee at its meeting held on March 6, 2000 opened the following Tenders for Contract No. 00FS-02S, Tender Call No. 07-2000, for substructure rehabilitation of the F.G.Gardiner Expressway - Rees Street to York Street:

Price Complete

Including All

TendererCharges and Taxes

G. Tari Limited$1,715,550.26

Underground Services (1983) Ltd.$1,722,977.13

Comments:

The Tender documentation submitted by the recommended bidder has been reviewed by the Commissioner of Works and Emergency Services, and was found to be in conformance with the Tender requirements.

The Manager, Fair Wage and Labour Trades Office has reported favourably on the firm recommended.

Conclusions:

This report requests authority to issue a contract for substructure rehabilitation of the F.G.Gardiner Expressway - Rees Street to York Street , in accordance with specifications, to G. Tari Limited, being the lowest Tender received.

Contact:

W.G.Crowther, P. Eng.,L.A.Pagano, P. Eng.

Director, Works Facilities and StructuresDirector

Technical Services DivisionPurchasing & Materials

Tel. No. (416) 392-8256Management Division

Fax No. (416) 392-4594Tel. No. (416) 392-7312

E-mail: WCrowth@toronto.ca

  Tom G. Denes, P. Eng.,

Executive Director, Technical Services

  Barry H. GutteridgeWanda Liczyk

CommissionerChief Financial Officer and

Works and Emergency ServicesTreasurer

WGC/mc

  List of Attachments

No attachments

 

   
Please note that council and committee documents are provided electronically for information only and do not retain the exact structure of the original versions. For example, charts, images and tables may be difficult to read. As such, readers should verify information before acting on it. All council documents are available from the City Clerk's office. Please e-mail clerk@toronto.ca.

 

City maps | Get involved | Toronto links
© City of Toronto 1998-2005