Integration of Works Construction Contract Documents -
Harmonized General Conditions of Contracts
The Works Committee:
(1) submits the following report (January 4, 2000) from the
Commissioner of Works and Emergency Services to Council
without recommendation; and
(2) reports having requested the Commissioner of Works and
Emergency Services to submit a report directly to Council for its
meeting on February 1, 2000, on the issues raised in the
communication dated January 11, 2000, from the Greater Toronto
Sewer and Watermain Contractors Association:
Purpose:
The purpose of this report is to seek Council approval of the proposed,
harmonized Works and Emergency Services General Conditions of
Contracts document for construction contracts.
Financial Implications and Impact Statement:
There are no direct funding implications arising from this report.
Recommendations:
It is recommended that:
(1) Council approve the use of the General Conditions of Contracts
document proposed in this report for inclusion in all future tender
documents issued on or after February 1, 2000, for all Works
construction contracts; and
(2) the Commissioner of Works and Emergency Services be
authorized to make such amendments to the General Conditions
of Contracts document as deemed appropriate by the
Commissioner from time to time, provided such amendments are
in a form satisfactory to the City Solicitors and consistent with the
objectives set out in the body of this report.
Background:
As the result of amalgamation in 1997, the Department inherited several
different General Conditions of Contracts (GC) documents from the
former municipalities. These documents are inconsistent with each
other, out of date and have not kept up with changing government
legislation and Works and business practices. The Department has
been using these versions in various districts until it had developed a
consolidated and harmonized document to replace the existing ones.
Recognizing the importance of an integrated GC document, the
Department in March 1998 chartered an interim staff work group to
review and harmonize existing versions of GC documents. This group
began with the task of working towards the creation of a draft document
using the Ontario Provincial Standard (OPS) GC as the base document.
Utilization of the OPS as the base document for Works and Emergency
Services contracts had previously been reported to and approved by
Council.
Because of departmental restructuring, the function of integration,
development and maintenance of design and construction standards
has become the activity of the Department's Technical Services Division.
In November 1998, a new Works Standards Technical Advisory Group
represented by selected managers from Technical, Solid Waste
Management, Transportation and Water and Wastewater Services,
chartered by the Senior Management Team of the Department, replaced
the former interim staff work group. The new group, with the assistance
of Works staff from Standards, Policies and Quality Assurance branch,
continued with the task of harmonizing the existing General Conditions
of Contracts documents.
Between November 1998 and June 1999, extensive consultation took
place in meetings, discussions, and written communications with
various internal stakeholders. Stakeholders included staff of Insurance
and Risk Management and Purchasing and Materials Management of the
Finance Department, and Legal, Occupational Health, Safety and
Workers' Compensation and Facilities and Real Estate of the Corporate
Services Department. Concurrently, staff held meetings and
discussions with key representatives of contractors' associations to
understand their interests and concerns. Inputs from these
stakeholders have helped the staff reshape the work of the earlier group.
On June 17, 1999, staff completed the first draft of the integrated
General Conditions of Contracts document that harmonizes practices of
the seven former municipalities, and began to solicit external comments.
External stakeholders receiving the draft document include nine
associations and agencies representing consulting engineers,
contractors, utility companies and the TTC. A list is included at
Appendix A.
There were approximately 50 issues of concern (Appendix B) raised by
these stakeholders, most of which came from the Grater Toronto Sewer
and Watermain Contractors Association (GTSWCA), Metropolitan
Toronto Road Builders Association (MTRBA), and Ontario Association
of Foundation Specialists (OAFS). After further discussions and
consultation with internal and external stakeholders, staff completed a
revised, second draft of the document on November 9, 1999. Staff were
able to resolve approximately 80 percent of these issues in the second
draft.
On December 22, 1999, staff again met with representatives of GTSWCA
and MTRBA to discuss and resolve any outstanding issues of concerns
that these associations might still have. Consequently, staff has revised
and finalized the proposed General Conditions of Contracts document
(Appendix C) such that it addresses almost all of the issues raised by
the participating stakeholders.
Comments:
The Department has based its proposed new General Conditions of
Contracts (GC) on the OPS parent document because municipalities and
construction industries in Ontario generally accept the OPS document
as a reliable source. The Ontario Ministry of Transportation is currently
the steward of OPS. Selected representatives from the Municipal
Engineers Association and associations of related construction
industries across Ontario are joint authors of various parts of OPS.
These documents are broad based, generic and generally cater to the
needs of smaller municipalities, especially those that have limited staff
and financial resources. This Department is managing an extremely
large Capital Works Program. To protect these large investments it is
important for the Department to ensure that the City is completely
satisfied and confident in implementing its new GC document. This
includes, where necessary, making amendments to the OPS document
to remove any ambiguities or inconsistencies with Works and
Emergency Services best practices and relevant corporate policies. To
this effect, the proposed new document has incorporated over 120
amendments to the OPS base document.
Some highlights of the differences between the proposed General
Conditions of Contracts document and the existing City and OPS GC
documents are discussed in the following paragraphs.
Alternative Dispute Resolution (ADR):
When disputes arise, litigation helps define legal and factual issues, for
appropriate resolutions. However, unnecessary lawsuits can result in
higher construction costs to both parties and undermine a constructive
continuing relationship between owner and contractor.
The proposed GC document now has an ADR mechanism that includes
access to mediation and binding arbitration through mutual agreement
or consent of both parties. The mediation procedure is the same as OPS
GC 3.14. However, the proposed document is fundamentally different
from OPS GC 3.15 in terms of access to arbitration. OPS GC 3.15
stipulated unilateral access to arbitration whereby either party may force
the other party into binding arbitration proceedings, whether or not the
party being forced to arbitration believes it to be the best route given the
legal issues involved and the need to retain appeal rights on those
issues. The proposed document allows arbitration through mutual
agreement or consent, thereby providing the needed flexibility for the
parties, and particularly the City, to choose between arbitration and
litigation.
Discussions with staff of the Ministry of Transportation (MTO)
responsible for contract dispute resolution indicate that the Ministry in
its own experience is not in favour of unilateral access to mediation and
arbitration and that MTO construction contracts have a section called
Issue Resolution (Appendix D) that replaces OPS GC 3.14 and 3.15. The
section describes a three-level, bottom up two-party negotiation
protocol, failing which there are provisions for access, through mutual
agreement, to a third party referee or advisor and failing resolution, by
mutual agreement again, to binding arbitration.
Other generally accepted standard documents (published by Canadian
Construction Document Committee) for building contracts involving
owner, contractor, architects and consultants are CCDC2(1994) for
Stipulated Price Contract (lump sum contract), and CCDC4(1982) for Unit
Price Contract. CCDC2 has provisions for mediation by mutual
agreement and unilateral access to binding arbitration. CCDC4 has no
provision for mediation but mutual agreement to arbitration. CCDC4 for
Unit Price Contracts has not changed since 1982.
Typically, there is little need for mediation in case of unit price contracts
as the use of unit price items can quantify the items in dispute. The cost
of items due to unforeseen factors such as change in subsurface or soil
conditions, can be clearly determined as is done in the proposed GC
document. A majority of Works construction contracts, particularly
sewers, watermains and roads, are of unit price nature and mediation
and arbitration have rarely, if ever, been used by any former
municipalities.
The Department has recently conducted a random survey of current
practices by 16 municipalities in Ontario (Appendix E). The population
of these municipalities ranges from 30,000 to 830,000.
The results of the survey lead to the following conclusions:
(a) The mediation process has very little use or has rarely been used
in municipal construction contracts. The objective of a mediator
is to reach a settlement in middle ground which will likely result in
some monetary settlement in favor of the plaintiff. Since a
municipality is usually the defendant and not the plaintiff, it is
understandable that in most cases a municipality will be reluctant
to use mediation.
(b) Unilateral access to mediation does not appear to exist in
municipal construction contracts in large and medium size
municipalities.
(c) Only a very small number of municipalities have some limited
experience in binding arbitration. Despite having provisions for
unilateral access to binding arbitration, very few municipalities
have actually used it in the past.
(d) Arbitration does not appear to be faster than litigation.
Statistics regarding mediation proceedings in Canada reveal a drop in
success rate from 75 percent to 40 percent if the process is mandatory.
This translates into a 60 percent failure rate for any unilateral mediation.
This drop is perhaps understandable because the other unwilling party
is probably less prepared and consequently, more likely to reject the
outcome. The result is often a poor use of money, resources and time.
Mandatory mediation is soon to become a preliminary procedural
requirement in Ontario civil actions, in which event any pre-court
mediation such as that provided in GC documents may be seen to be a
duplication.
Based on the above discussions, staff is of the opinion that mediation
and binding arbitration should be discretionary or mutually agreeable to
both parties. While there are merits to both mediation and arbitration,
the decision on implementing those mechanisms should allow the City
to determine the appropriateness of the relevant mechanism depending
on the nature and magnitude of the issues involved in any given
situation.
Nevertheless, staff also recognise the need for a team-building, issue
resolution protocol or process that creates mutual trust and respect for
both parties respective roles in the construction process and recognizes
the risks inherent with those roles. The proposed ADR mechanism in
the GC document will be much more effective if it is complemented by
a team-building process that develops/nurtures harmonious
relationships at jobsites. The Department will be developing a dispute
resolution protocol in the near future.
Changed Subsurface Conditions and Changed Soil Conditions:
These two common areas lead to frequent claims, because relevant
sections of current City GC documents were too onerous and
unreasonable, therefore resulting in contractual disputes, escalated
construction costs and in some instances unnecessarily high bids. The
new GC document sets out a clear and equitable way of sharing the
contractual responsibility between the contractor and the City.
Construction Lien Act and Occupational Health and Safety Act:
Current City GC documents did not keep up with changes in the
Construction Lien Act and the Occupational Health and Safety Act.
Legal and Occupational Health and Safety staff have reviewed and made
major amendments to the proposed GC document with respect to these
statues.
Insurance, Protection and Damage:
Risk and Insurance and Legal staff have amended and rewritten the
Insurance Liability, and Indemnification clauses in the proposed GC
document to reflect current corporate policies and ensure quality and
consistency.
Owner's Responsibilities and Rights:
Major revisions to OPS GC documents have been made to further clarify
Owner's Responsibilities and Rights. They include sections under
Management and Disposition of Materials, Default by the Contractor,
Owner's Right to Correct Default or Terminate the Contract, Final
Payment to Contractor and Continuation of Contractor's Obligations.
Warranty:
The standard warranty period has been increased from 12 months to 24
months from the date of substantial performance of the work.
Contractor's Responsibility for Drainage:
This clause has been added to ensure contractors exercise due
diligence and are responsible for damages caused to properties as a
result of the contractor's construction activities, such as flooding or
other rainwater related problems.
Interest:
All references to interest due to the contractor have been removed.
Staff believe it is not necessary to set rates and rules as the City has no
real history of delay in making payments to contractors and does not
foresee any change in the future. Deleting these clauses from the GC
document will provide flexibility for both parties to negotiate and settle
a claim or a dispute equitably and based on the real cost of doing
business.
Conclusions:
Staff has completed the harmonization of General Conditions of
Contracts for Works construction projects. The new set of General
Conditions of Contracts document, using OPS as a base, is ready for
implementation in new Works Construction Contracts in the year 2000.
The new document sets out a clear understanding between the City and
contractors with respect to their general administrative and legal
obligations.
The foundation of successful construction projects depends on healthy
and true partnership where each member has a clear understanding of
their roles and responsibilities and work as part of an effective team.
The recommended document fosters quality and cost effective
construction through commitment, equity, trust, and timely
responsiveness of both the City and contractors. The Department is
also committed to develop a team-building, issue resolution protocol
that fosters harmonious relationships at jobsites, to complement the
new GC document. Accordingly, it is the Department's belief that
implementation of the recommended General Conditions of Contracts
document will promote the spirit of partnership and will have a long
term cost saving effect on the Department's construction projects.
The proposed General Conditions of Contracts is a live document and
will be subject to periodic review and improvement.
Contact:
Samson Yao, P.Eng., Manger
Standards, Policies and Quality Assurance, Works Facilities and
Structures
Tel. No. (416) 392-8389; Fax No. (416) 392-4594
E-mail: SYao@toronto.ca
List of Attachments:
Appendix A - List of External Stakeholders
Appendix B - List of Issues Raised by External Stakeholders
Appendix C - City of Toronto, WES, General Conditions of
Contract
Appendix D- Extract from Ontario Ministry of Transportation
Amendments to OPS General Conditions of Contract,
August, 1990
_________
The Works Committee reports, for the information of Council, having
also had before it during consideration of the foregoing matter a
communication (January 11, 2000) from Mr. Salvatore Morra, P.Eng.,
Executive Director, Greater Toronto Sewer and Watermain Contractors
Association, regarding the harmonization of the General Conditions of
Contracts, and advising that the most important item to the Association,
Unilateral Access to Mediation and Arbitration, remains unresolved.
(A copy of Attachments A, B, C and D, referred to in the foregoing report
has been forwarded to all Members of Council, and a copy thereof is on
file in the office of the City Clerk.)