The Ledbury Park Building improvements are complete and the building and outdoor ice rink is open to the public. Minor site work to the pool area will be completed in spring 2023.

The City is improving the building in Ledbury Park as part of a state-of-good-repair program to upgrade the facility’s roof and exterior, mechanical and refrigeration systems, and improve accessibility.

  • August 2021: Detailed design
  • January 2022: Hiring a construction team
  • March 2022: Construction starts
  • December 2022: Construction complete
  • Spring 2023: Minor site work to pool area

The timeline is subject to change.

January 2023

Construction Complete

A majority of construction is complete and the building and outdoor ice rink open to the public. Minor site work to the pool area will be completed in spring 2023. Additional information will be shared on this page when available.

December 2022

Construction Update

Construction is near completion and the building is anticipated to open to the public in early January. The outdoor rink is currently closed as it is being prepared for the winter season. The public is asked to stay off the rink surface until is it open.

September 2022

Construction Update

Construction continues on the washrooms, change rooms, mechanical, electrical and refrigeration systems. Work is near completion for the upgrades to the roof and building’s exterior. All work is anticipated to be complete in December 2022.

There will continue to be no access to the entire facility during construction.

June 2022

Building and Pool Closure

Construction is underway on the building’s roof and exterior. As a result of this work, the building and pool are closed to the public.

Image shows the work being completed on the exterior of the Ledbury Park building. Construction material and equipment are present the pool deck, with scaffolding covering the building's exterior.
Construction is in progress on the Ledbury Park building exterior.

Due to work stoppage, unforeseen site conditions and ongoing supply chain issues, construction will not be complete in time for the 2022 pool season. Ledbury’s leisure swims have been added to Lawrence Height’s programming schedule. The pool will reopen for the 2023 season.

Alternatively, the nearest outdoor pools are:

The building in Ledbury Park houses the pool change rooms, public washrooms, pavilion, as well as mechanical and refrigeration systems to support the park’s artificial ice rink and outdoor pool.

The building is undergoing improvements to:

  • upgrade the public washrooms and pool change rooms
  • upgrade the mechanical, HVAC, electrical and refrigeration systems
  • upgrade the roof and the building’s exterior
  • add a universal washroom and elevator

Due to the impact this work will have on the building, the pool change rooms and the adjacent pool area, the entire facility and pool will be closed for the duration of the project.