The City is planning improvements to the building in Ledbury Park as part of a state-of-good-repair program to upgrade the facility’s mechanical and refrigeration systems, roof, exterior building system and improve accessibility to the washrooms, change rooms and elevator.

Project Timeline

  • August 2021: Detailed design
  • January 2022: Hiring a construction team
  • March 2022: Construction starts
  • December 2022: Construction finishes

The timeline is subject to change.

About the Project

Ledbury Park is located at 160 Ledbury St. near Bathurst Street and Lawrence Avenue in North York. The building is located within the park and includes change rooms and washrooms.

The building is being improved as part of a state-of-good-repair program being delivered in multiple phases and includes the following improvements:

  • Public washrooms and changing rooms upgrades
  • Mechanical, HVAC, electrical and refrigeration systems upgrades
  • Roof and exterior building upgrades (“building envelope”)
  • Accessibility improvements including accessible change room, washroom and elevator

Phase 1: Outdoor Pool Area

Construction for this phase is scheduled for March to June 2022 and includes upgrades to the pool change rooms, roofing and building envelope. During this phase, there will be no access to these spaces and the outdoor pool.

Phase 2: Artificial Ice Rink

Construction for this phase is scheduled for July to September 2022 and includes upgrades to the washrooms, roofing and building envelope, mechanical and electrical rooms. During this phase, there will be no access to these spaces.

Phase 3: Artificial Ice Rink and Elevator

Construction for this phase is scheduled for September to December 2022 and includes upgrades to the mechanical, electrical and HVAC systems and elevator installation. During this phase, there will be no access to the artificial ice rink.