The City is improving Norseman Community School and Pool as part of a state-of-good-repair program to upgrade the pool’s ventilation systems, change rooms, washrooms, swimming pool, lighting and repair the interior and exterior of the building.

  • September 2022: Construction starts
  • December 2023: Construction complete
  • Mid-March 2024: Pool reopens

The timeline is subject to change. The pool reopening is dependent on Toronto Public Health approval.

February 2024

Construction Update

Pending Toronto Public Health sign-off, drop-in programs inclusive of lane swim, leisure swim, aquatic fitness and permits will return in mid-March 2024.

November 2023

Construction Update

Construction is now expected to be completed in December 2023.

September 2023

Construction Update

Construction for the pool improvements continues and is anticipated to be completed in October/November 2023.

March 2023

Construction Update

Construction for the pool improvements continues as planned and on schedule.

September 2022

Construction starts

Construction for the building improvements starts and the facility closes to the public.