The City is making improvements to Warden Hilltop Community Centre as part of a state-of-good-repair project to address water leak and drainage issues. The community centre will remain open during construction.
The timeline is subject to change.
Additional repairs to the south side of the community centre (offices and multi-purpose rooms) were completed.
Additional areas requiring waterproofing repairs were found during construction. The scope of the project is planned to include additional repairs to the green roof.
The following repairs to the community centre were completed.
Foundation waterproofing repairs and site drainage improvements at the gym north wall are complete. Additional site restoration work and water leak repairs will be conducted in spring 2021.
Warden Hilltop Community Centre is located near Warden Avenue and St. Clair Avenue East in Scarborough. The building’s foundation and roof structure require repairs in order to improve overall drainage and water issues in the north-east corner of the gymnasium. The scope of work includes: