A new multi-use Community Recreation Centre (CRC) with an Aquatic Centre, Child Care Centre and a Toronto Public Library branch is coming to the Bayview Village community.
The timeline is subject to change.
Sign up for updates related to the Ethennonnhawahstihnen’ Community Recreation Centre & Library or unsubscribe from the mailing list.
From October 18 to November 3, 2022, community members between the ages of 13 and 29 were invited to complete an online survey and interactive thought exchange activity to share and rate ideas for programs and activities that could be offered at the community recreation centre.
The thought exchange generated 99 ideas and 2,324 ratings from 194 participants. The highest-rated program or activity ideas included:
The most popular programs, activities or amenities presented in the survey are summarized below:
Half of participants (50 per cent) identified as a woman or girl and 41 per cent identified as a man or boy. One in five (20 per cent) participants identified as an immigrant, newcomer, or refugee.
On October 19, 2022, a virtual public meeting took place to explore programming opportunities at the community recreation centre. Participants were asked to review and confirm the findings of the online survey and interactive thought exchange activity that took place in September 2022, and to share additional ideas, comments or questions.
Download the summary report.
On September 28, 2022, a meeting took place at Parkway Forest Community Centre. The project team explored a variety of activity and program ideas and opportunities for the new Community Recreation Centre with participants.
From September 9 to September 23, 2022, community members were invited to complete an online survey and interactive thought exchange activity to share and rate ideas for programs and activities that could be offered at the community recreation centre.
The thought exchange generated 268 ideas and 6,817 ratings from 303 participants, with 74 per cent living within a 30-minute walk from the centre. The highest-rated program or activity ideas included:
The most popular programs, activities or amenities presented in the survey are summarized below:
Construction is progressing and over 95 per cent of the building is complete. The contractor is focusing on millwork installation, final finishes and outdoor hard surfacing work. The project is anticipated to achieve substantial completion in April 2023. After construction is substantially completed, City staff will have access to the new community recreation centre to start setting up while the contractor completes deficiencies and weather-dependent work. A soft opening is anticipated for June. The exact dates will be posted on this page as soon as they are available.
Construction is progressing and work to key interior and exterior finishes is advancing. The project is 95 per cent complete. Due to continued issues with supply chain material delivery, the contractor is now targeting substantial completion by March 2023.
Construction is progressing. Exterior landscaping and main canopy is advancing. Interior spaces are being completed including tiling of the pool, flooring, millwork, painting, doors and hardware, and fixtures The acoustic ceiling, running track guardrail cladding and painting in the main gymnasium are complete and the space is ready for hardwood floor installation.
Construction of the building envelope, mechanical and electrical systems has significantly progressed. Additional site and landscape work is advancing, including terrazzo tiling and work to the gymnasium floor. The swimming pool shells are fully tiled and exterior right of way work will start in early September. The contractor anticipates substantial construction completion by winter 2022.
Work on the project continues to progress with the zinc cladding panels and glazing 70 per cent complete. The main entrance structure is 90 per cent complete allowing the necessary preparation for the sidewalk work. The pool shell is being water tested and prepared in advance of tiling, which will take at least three months. The wood ceiling in the pool and all the ceiling framing for the gymnasium, library and multipurpose rooms is complete and 73 per cent of the terrazzo floor in the public circulation area has been installed.
Painting continues throughout the building and parking structure. The gymnasium ceiling panels are on-site and will take around one month to install, following the floor installation. The mechanical and electrical work is over 85 per cent complete. The work done to date represents approximately 78 per cent of the contract work completed.
The Community Recreation Centre is officially named Ethennonnhawahstihnen’ Community Recreation Centre and Library at North York Community Council on February 23, 2022. Visit the About the Project section for more information about the site background and rationale for the new name.
The contractor has completed 95 per cent of the above grade structure and is advancing the exterior building glazing. Work is continuing to advance for the exterior building envelop with roofing and cladding underway. Mechanical and electrical rough in work to the garage has been underway for some time and continues now at all levels. The work done to date represents approximately 67 per cent of their contract work completed.
The contractor continues with construction of the above grade structure, sequencing work at the south end of the building first, with work on the north end following a bit behind. The structure is largely completed. The contractor is currently working on the exterior building envelope with roofing and cladding underway. Mechanical and electrical rough in work has been underway for some time in the garage and continues now at all levels. The work done to date represents approximately 55 per cent of their contract work completed.
The contractor continues with the building structure, sequencing work at the south end of the building first with work on the north end following a bit behind. The contractor currently has completed the roof structure to the south end of Level 3, and has commenced installing the Level 3 structural columns at the north end (Gymnasium). Mechanical and electrical rough-in work has been underway for some time in the underground garage levels. The work done to date represents approximately 49 per cent of the construction contract work completed.
There has been some schedule slippage attributable to the impact of the COVID-19 construction industry shutdown and related reductions in labour efficiency and supply challenges. Substantial Performance of the contract is now expected in Q2 or Q3 2022, with completion expected by the beginning of Q4 2022 – ready for City staff to start occupying the building around that time. The centre is anticipated to be open to the public a few weeks following that (sometime during winter 2022/early 2023). This schedule may be improved upon if everything goes as per schedule and will be revisited closer to substantial completion (Q2 or Q3 2022) when the project is further advanced.
The contractor is nearing completion of the three-storey underground parking garage concrete structure, with construction more advanced at the south end of the building and the work at the north end following closely behind. The contractor has formed the Level 1 ground floor slab at the south end and is working to complete the P1 Level at the north end (basement mechanical rooms). This represents approximately 35 per cent of the contract work completed.
There have been some schedule slippage attributable to the COVID-19 delay. The contractor’s most recent schedule indicates Substantial Performance of the contract is expected for the end of Q4 2021, and completion expected by the beginning of Q2 2022 – ready for City staff to start occupying the building around that time. The centre is anticipated to be open to the public a few weeks following that (sometime within Q2 2022).
The contractor continues with the construction of the P3 level basement garage concrete walls and columns, the P3 level basement garage concrete slab on grade and the P2 level basement garage suspended concrete floor slab, starting at the south and progressing northward. Installation of underground drains and buried ducts continues. The contractor is 22 per cent complete the contract work by construction value. There has been some schedule slippage due to weather-related lost construction days.
The contractor continues with foundation footings, starter walls, and P3 level basement columns which were started at the south end and are progressing northward. Installation of underground drains has started.
Ethennonnhawahstihnen’ Community Recreation Centre and Library is situated within the footprint of the larger Concord Park Place multi-tower residential condominium redevelopment at 1001 Sheppard Ave. E. Concord Adex Investments Limited, through Section 37 and Section 42 agreements, conveyed the property immediately south of Bessarion TTC Station to the City of Toronto (Block 10, now known as 100 Ethennonnhawahstihnen’ Lane). Concord Adex Investments Limited has contributed funds for the construction of the new facility.
The new community recreation centre, street, and adjacent area are located within 800 metres of a significant Huron-Wendat archaeological site, the Moatfield Ossuary and village (1280 CE to 1320 CE).
An important and unique finding at this site was the presence of many people who lived in good health, with few injuries and past the age of 50.
Recognizing the significance of the site, in 2019, the City of Toronto Indigenous Affairs Office reached out to the Mississaugas of the Credit First Nation and Huron-Wendat Nation to understand how the City could commemorate the site and foster dialogue between current residents and Indigenous communities.
Ultimately, the Wendat name, Ethennonnhawahstihnen’ (meaning “where they had a good, beautiful life”) was suggested by the Huron-Wendat Nation to rename nearby Woodsy Park (located at 80 McMahon Drive) and Woodsy Park Lane.
In a separate process, the Toronto Public Library (TPL) Board approved the name “Ethennonnhawahstihnen’ Branch” for the new onsite TPL branch on January 24, 2022, based on advice from the TPL Naming Committee and the TPL Indigenous Advisory Council, which endorsed the name, with the understanding that Ethennonnhawahstihnen’ was the preferred name of the Huron-Wendat Nation.
Indigenous placemaking and reconciliation does not end with a name. The City of Toronto is committed to working with Indigenous communities to explore future opportunities for Indigenous placemaking, placekeeping and programming.
Additional information about the decision to name Ethennonnhawahstihnen’ Community Recreation Centre is available in the North York Community Council background report.
Ethennonnhawahstihnen’ Community Recreation Centre is located at 100 Ethennonnhawahstihnen’ Lane, adjacent to Ethennonnhawahstihnen’ Park.
While we aim to provide fully accessible content, there is no text alternative available for some of the content on this site. If you require alternate formats or need assistance understanding our maps, drawings, or any other content, please contact Mario Pecchia at 416-395-7916 or Mario.Pecchia@toronto.ca.
The main level of the CRC will include:
The second level of the CRC will include:
The third level of the CRC will include:
There will be 196 parking spaces on the lower-level of the CRC which will be operated by Toronto Parking Authority.