A new 2604 m2 park is being designed at 1087 Leslie St., located at the northeast corner of Leslie Street and Eglinton Avenue East.

  • Winter 2021: Conceptual Design Development and Community Engagement
  • Spring 2021: Final Design Development
  • Summer 2021: Tender for Construction
  • Spring 2022: Anticipated construction

The timeline is subject to change.

Sign Up Now

Sign up for updates related to the new park at Leslie Street and Eglinton Avenue East or unsubscribe from the mailing list.

While we aim to provide fully accessible content, there is no text alternative available for some of the content on this site. If you require alternate formats or need assistance understanding our maps, drawings, or any other content, please contact Andrey Pravosoudov at 416-420-5648.

An aerial image of the final concept plan for the new park at the Leslie and Eglinton development is shown. The concept plan includes a separated junior and senior kid's playground areas located on the east side of the park, an overlook area moved to the park's north-east corner, a south entrance plaza and shade pergola with vines, and a paved walkway stretching from the north-east and south-west corners of the park
A larger version of this image opens in a new window.

The design for the new park includes:

  • Separated junior and senior playground areas located on the east side of the park
  • An overlook area at the s north-east corner of the park
  • A south entrance plaza and shade pergola with vines
  • A paved plaza entrance and walkway from the north-east and south-west corners of the park
  • Bike racks on the north-west corner of the park
  • Removal of the sloped amphitheatre seating area and expansion of the large open lawn area
  • Removal of the circuit pathway around the lawn area

May 2021

Design Finalized

Using community and stakeholder feedback, the design plan for the new park was finalized. Visit the Design section for more information.

February 2021

Online Survey

From January 22 to February 14, 2021, an online survey was conducted to gather feedback on the early design plan and playground equipment options for the new park coming. The survey received 275 responses.

Download the survey results summary.