From September 8 to late November 2025, the northwest area of College Park will be closed for construction. Access to the park, homes and businesses will remain open.

The City is replacing the grass at the north entrance of College Park with artificial turf and adding new plantings and seating, along with a pathway connecting the north entrance to the skate trail. The project aims to enhance the space, reduce muddy conditions caused by worn-down grass and create a defined pedestrian pathway.

    • Spring 2025: Stakeholder engagement and design development
    • Summer 2025: Detailed design and hire a construction team
    • Fall 2025: Construction starts and completes

    The timeline is subject to change.

    September 2025

    Construction Update

    Construction for the park improvements will start on September 8 and is anticipated to take 10 to 12 weeks to complete. Fencing will be installed around the construction site, and access to homes and businesses will be maintained.