The City is adding a new basketball court, pathways and seating to Fairfield Park as part of the Parks and Recreation Facilities Master Plan. This plan reviewed Toronto’s existing basketball facilities to assess whether improvements or new facilities are needed to meet the growing demand for the sport. The new court is proposed to be located at the south end of the open field.

  • Fall 2024: Hire a design team
  • Winter 2025: Community engagement and design development
  • Spring 2025: Detailed design
  • Summer 2025: Hire a construction team
  • Fall 2025: Construction starts
  • Late 2025: Construction complete

The timeline is subject to change.

Level of Engagement

This project has been classified as a Consult project based on theĀ International Association of Public Participation Spectrum. This means we obtain public feedback on existing analysis, alternatives, and/or proposals.